Posted on: February 8, 2019

CIP Monthly Status Report – December 2018

CIP Vendor Fair Presentation
In December, the Digester and Thickener Facilities Upgrade Project continued concrete placement for the digester roofs and ring beam foundations. Installation of digester exterior insulation and gas domes began, and the sludge screening building walls were completed.

A review of major equipment submittals was completed, and the contractor ordered flow meters for the Advanced Facility Control & Meter Replacement – Phase 1 Project.

The Cogeneration Facility Project continued installation of masonry walls for the generator building, and hot water supply, return piping and biogas piping for the gas purification system. Work started on the electrical duct banks for the cooling towers and gas purification system.

The Blower Improvements Project team prepared for construction to begin in January 2019. Condition assessments of the storm and sanitary sewers were completed for the Storm Drain System Improvements Project. The Filter Rehabilitation Project completed the filter column pilot testing to identify the filter media configuration for further testing under a full-scale pilot in one of the existing filter basins.