Posted on: June 6, 2019

CIP Monthly Status Report – April 2019

Aerial view of construction at the Regional Wastewater Facility.
In April, the Nitrification Clarifiers Rehabilitation – Phase 1 Project passed Stage Gate 5: Authorization to Bid in the Project Delivery Model. The City determined that all six contractors who submitted qualifications were eligible to bid on the project. The City plans to advertise the project in May and open bids in June.

The contractor on the Digester and Thickener Facilities Upgrade Project continued seismic ring beam concrete placement on all four digesters. The design-builder for the Cogeneration Facility Project continued to erect the concrete masonry unit walls of the main generator building, placing the eighth of nine lifts, and installed the mezzanine embeds for the south wall of the control room.

On the Blower Improvements Project, the project team began reviewing key submittals for the blower motors, reduced voltage starters, and variable frequency drives. The Headworks Project team held workshops to discuss cost estimating review planning, process control, and condition assessment planning. On the Digested Sludge Dewatering Facility Project, the project team continued negotiations with the top-ranked firm. Negotiations are expected to be completed in June.

CIP Monthly Status Report – April 2019