| |
1999-2000 Capital Budget Overview and 2000-2004
Capital Improvement Program
Highlights | Policy
Direction | Significant Issues | 5-Year
Revenue Summary | Operating Budget Impact | Conclusion
September 1, 1999
HONORABLE MAYOR AND COUNCILMEMBERS:
On June 29, 1999 the City Council adopted the 2000-04 Capital Improvement
Program (CIP) and the 1999-2000 Capital Budget. The CIP and Budget, presented in
this document, are intended to guide the City in the planning, scheduling and
budgeting of capital improvement projects during the five-year period. This
overview provides a summary of the significant issues, policy directions and
changes from the Proposed Capital Budget and CIP. To provide further background
regarding the development of the Budget and CIP, the introduction to the
Proposed Capital Budget and CIP and several Council-approved policy direction
memoranda are reprinted as appendices to this document.
The process of developing the Capital Budget and Capital Improvement Program
started in October 1998 with five-year capital revenue projections. Initial
policy directions from the City Council were provided in the budget direction
memoranda issued by the Mayor Hammer on November 25, 1998 and Mayor
Gonzales on March 17, 1999. The Proposed Capital Budget and CIP was published on
April 1, 1999 in accordance with the City Charter. The final process in the
development of this document was the review of the Proposed Capital Budget and
CIP by the Council during budget hearings held in May and June. During those
hearings, a number of changes were approved by the Council in response to
recommendations made by the Mayor, Councilmembers and the Administration.
As has been the case in recent years, the Redevelopment Agency Capital
Improvement Program is presented in a separate document prepared by Agency
staff. The Agency CIP does, however, include projects which will be managed by
City departments. Many of the Agency's projects have a significant impact on the
City's plans and operations. The impact of some of the projects in the Agency's
CIP are discussed later in this overview.
The Adopted 2000-04 CIP totals $1.6 billion. This is a 3% increase from the
$1.55 billion included in the Adopted 1999-2003 CIP. The Adopted 1999-2000
Capital Budget totals $639 million, an increase of $112 million (21%) from the
Adopted 1997-98 Capital Budget, which totaled $527 million. This increase
primarily results from the addition of unexpended funds for projects originally
intended to be completed in the prior year. Due to delays for various reasons,
the unexpended funds have been rebudgeted into the 1999-2000 to complete the
projects. The following chart illustrates the allocation of the Capital Budget
by type of program.
D
Note: The Underground
Infrastructure Systems category includes Storm Drainage, Municipal Water
Utilities, Water Pollution Control, Underground Utilities and Sanitary
Sewers. The Transportation Related programs category includes Traffic,
Off-Street Parking and the Residential Construction Tax Contribution Fund.
The Municipal Facilities category includes Communications, Municipal
Improvements and Service Yards.
HIGHLIGHTS
OF THE 2000-2004 CAPITAL IMPROVEMENT PROGRAM
The continuing inability to fund several key components of the capital
program at a level consistent with the City's infrastructure needs or desired
levels of service remains the key policy concern inherent in the City's Capital
Improvement Program. Even with recent significant improvements in the City’s
economy, revenues available for capital improvement investment fall short of
what is needed.
While recognizing the inadequacy of current funding sources, much can still
be accomplished over the next five years. Among the planned outcomes of this
Adopted CIP are:
- A new Civic Center will be constructed in the downtown area to consolidate
city functions and avoid increasing rental costs.
- The sidewalk repair grant program has been revised to provide free
sidewalk repairs to homeowners, instead of the 1/3 cost sharing program.
- An Intelligent Transportation System project will implement an advanced
traffic management system in the area around San Jose International Airport.
Funding is also provided in the Airport Capital Program to address
deficiencies identified in the upcoming Terminal and Transportation Study.
- Funding for the construction of a new Federal Inspection Service (FIS)
building at the Airport is included in the 1999-2000 Capital Budget. The FIS
facility is necessary to serve international passenger and cargo flights.
This project will replace a current facility that consists of older
multi-wide trailers located away from both Terminal A and C, requiring
transportation of passengers and baggage back to the terminals.
- With $19.8 million in funding for the purchase of new materials, the
Library will significantly exceed its annual book acquisition goal and add
new materials at all facilities, including non-English language materials,
children's books, large type books, audio books, and media materials.
- A new School Walking Routes project will enhance pedestrian safety in
school areas and provide pedestrian safety education services to elementary
and middle schools.
- The new Intelligent Transportation System: SMART Corridor project
implements an advanced traffic management system along the Route 17/880
corridor between Los Gatos and Milpitas.
- The Neighborhood Traffic Modeling project is a new annual program that
supports preservation of neighborhood quality in conjunction with traffic
level of service policy modifications.
- Fourteen new traffic signals are planned, along with major modifications
to nine more intersections. The specific intersections to receive new or
modified traffic signals are listed in the Traffic program overview.
- Two hundred and thirty five new streetlights are planned for each year of
this CIP. The locations are citywide and this level of funding supports our
ten-year backlog elimination strategy.
Almost $36 million is planned for the acquisition, construction, and
renovation of park and recreation facilities and an additional $37 in reserves
and fund balances will be available for future improvements. Some of the parks
and recreation facilities to receive significant improvements over the next
five-year period include:
| Aborn Park |
Almaden Winery Park |
Alum Rock Park |
| Backesto Park |
Bernal Park |
Boggini Park |
| Brigadoon Park |
Brooktree Park |
Canoas Park |
| Columbus Park |
Chynoweth Park |
Edenvale Garden Park |
| Guadalupe River Park |
Happy Hollow |
Hathaway Park |
| Los Paseos Park |
Lincoln Glen Park |
Mabury Park |
| Mayfair Park |
McLaughlin Park |
Mise Park |
| Overfelt Gardens |
Parkview Park |
Parma Park |
| Parque de la Amistad |
Ramblewood Park |
Pfeiffer Park |
| Rose Garden |
Solari Park |
Wallenberg Park |
| Watson Park |
William Street Park |
Windmill Springs Park |
2000-2004 POLICY DIRECTION
The 2000-2004 Capital Improvement Program was developed in accordance with
policy direction provided by the Council. Initial direction was provided in the 1999-2000
Budget Priorities and Direction memorandum approved by Council on December
7, 1998. Additional policy direction impacting the Capital Budget and CIP was
provided in Budget Direction memoranda approved by Council on March 12, 1999 and
June 22, 1999.
The following is a summary of the specific directions contained in those
documents and how they have been responded to in this Program:
Capital Improvement Policies
The Council directed that the following types of projects be considered
high priority in developing the Capital Budget:
1. Projects which enhance or maintain public health and safety
2. Projects which reduce or have minimal impact on operating and
maintenance costs
3. Projects which leverage effective use of grant funds
4. Projects which stimulate growth in the local economy and yield
fiscal benefits to the City
5. Projects which implement prior Council-adopted reports and
strategies
6. Projects which prevent additional deterioration of the City's
existing infrastructure
Capital projects have been measured against the Capital Improvement Program
Priorities. The priority addressed by each project is identified by number on
the project detail page.
West Valley Branch Replacement
The Council directed that funds in the Branch Library Reserve be earmarked
for the replacement of the West Valley branch library. The cost of a new
20,000 square foot facility with 85 parking spaces is estimated to be $7.9
million. The following sources of funding were identified in the Council’s
direction: $3 million from the Construction Excise Tax Fund transferred to the
Library Construction and Conveyance Tax Fund, $3.7 million from the General
Fund, and $1.2 million in Library Construction and Conveyance Tax funds
previously earmarked for the new Biblioteca Latinoamericana, which the
Redevelopment Agency absorbed into its budget. The earmarked funding has been
programmed for the West Valley Branch in the CIP and construction could begin
as early as spring of 2000.
Neighborhood Revitalization
Council directed that up to $1 million of any Construction Excise Tax
revenue exceeding the current budget be allocated toward the Neighborhood
Revitalization project for the next two years. Revenues for fiscal year
1998-99, however, did not exceed the estimate so no additional funds will be
transferred.
Infrastructure Maintenance
In order to address the need for additional funds to preserve components of
the City's infrastructure, Council has for the last six years directed that
$500,000 from any excess General Fund balance be allocated for infrastructure
maintenance. Excess fund balance, if available, is usually identified
following the completion of the annual financial audit. In coordination with
the Mayor's Office, specific recommendations for the use of any such funds
would be presented as part of the 1999-2000 Mid-Year Budget Review.
Direction in the March 17, 1999 message included:
Library Branch Master Plan
The Administration was directed to work with the Mayor’s Office, though
the Master Plan process, to evaluate the capital program related to branch
library expansion and construction to ensure that facility sizes are
established to most effectively serve all of our library patrons. The Library
Branch Master Plan is still under development.
Direction in the June 22, 1999 message included:
Master Plans
The City is currently developing master plans for many facilities,
including libraries, fire stations, parks and recreation facilities and police
and fire training centers. The Council directed that a new policy be developed
requiring viable financing options for both capital and operating expenses to
be included in each master plan.
Charter Change – Budget Timing
The City Charter requires publication of the Capital Budget ninety days
before the end of the fiscal year and the Operating Budget thirty days before
the end of the fiscal year. The Council directed the Administration to review
the possibility of a charter change to allow the capital budget to be
presented at the same time as the operating budget.
Unallocated Funds
A total of $4 million of one-time funds was left unallocated in the budget
process. The Administration was directed to report back to the Council in
September with a recommendation to allocate these funds to neighborhood
infrastructure needs such as sidewalks, tree trimming, streetlights,
transportation improvements, street maintenance, public facilities and any
other deferred funding priorities in our neighborhoods.
OTHER SIGNIFICANT CHANGES FROM THE PROPOSED CAPITAL IMPROVEMENT PROGRAM
The following discussion highlights several of the most significant revisions
to the Proposed Capital Budget and CIP resulting from Council decisions made
during the May and June budget hearings. More detailed descriptions of these
changes are included in the overview section of each program.
Civic Center Relocation
On June 8, 1999, the City Council/Redevelopment Agency Board approved the
relocation of the Civic Center to a new downtown location at an estimated cost
of $214 million. The Council also approved budget amendments to provide $20
million in initial variable rate financing for design and financing costs in
the first year of the program.
Sidewalk Repair Program
A new sidewalk repair program was approved which will provide grants to
homeowners for the full cost of repair. In the past, the City provided grants
for only one-third of the repair costs. Additional funding of $1.3 million was
added to cover the additional costs of the new program.
New Projects
Other significant new projects or expenditures adjustments directed by the
City Council included:
- An additional $1 million was provided for the development of a golf course
at Capitol Expressway and Tuers Road along the Coyote Creek.
- $300,000 was allocated for a new park in the Buena Vista neighborhood.
- A new gymnasium at PAL Stadium was approved at a cost of $300,000.
- Funding was provided ($285,200) to provide a new heating and air
conditioning system at Kirk Community Center.
- Funding in the amount of $250,000 was provided for a new traffic signal at
Santa Teresa Boulevard and Encinal Drive.
- $200,000 was provided for the installation of a soundwall along Meridian
Avenue.
Increased Construction and Conveyance Tax Revenue Estimates
Following the publication of the Proposed CIP, the City experienced an
increase in home sale activity which resulted in higher than anticipated
Conveyance Tax receipts. As a result, the 1998-99 estimate for Construction
and Conveyance Tax receipts was increased by $4.5 million, from the $21
million used in the Proposed CIP to $25.5 million. The additional funds were
distributed to various Capital programs according to the Council-approved
formula, but primarily benefited the Parks, Library, Service Yards and Fire
programs.
SIGNIFICANT ISSUES
Airport Area Transportation Improvements
The Airport is currently conducting a comprehensive Terminal and
Transportation Study. The transportation component of this study is
anticipated to be completed in the fall of 1999. The completed study will
develop and document existing and future transportation demand information,
and strategies to achieve greater public transportation utilization, as well
as identify roadway improvements both at and near the Airport. In order to
begin to address necessary improvements identified in the study, $2 million
has been included in the 1999-2000 Capital Budget for the Transportation
Improvements project. In addition, a Traffic Mitigation project provides a
total of $2,250,000 to begin work toward traffic improvements related to the
implementation of the Airport Master Plan. The project will provide initial
funding to identify, design, and construct specific projects needed to address
the recommendations of the Terminal and Transportation Study.
In addition to these Airport traffic improvements, there are two other
projects in the Traffic CIP that will address traffic issues near the Airport.
The first project is the Intelligent Transportation Systems (ITS): Airport
Area project, which will implement an advanced traffic mitigation system in
the area around the Airport, intended to improve traffic flow, reduce
emergency vehicle response times, and provide traveler information. The second
project is the Route 880/Coleman Interchange project, which will provide for
conceptual engineering and preparation of Environmental Impact Studies for a
future potential project to upgrade the Coleman Avenue interchange at Route
880. Construction of this upgrade will greatly improve traffic safety and
reduce congestion in the vicinity of the Airport.
Airport Noise Attenuation
Approximately $34.5 million is included in the CIP for the Noise
Attenuation and Acoustical Testing projects. It is anticipated that the
current ACT Program, which includes the treatment of 1,500 dwellings and other
noise sensitive land use properties, will be completed by 2000. These
dwellings are within the 65 decibel Community Noise Equivalent Level (CNEL)
noise contour area of San Jose and Santa Clara. In addition, $7.5 million has
been included in the Noise Attenuation project to provide acoustical treatment
of several schools that are within the 60 CNEL area. These facilities include
the Washington Elementary School, Center for Employment and Training, Sacred
Heart education facility, and the Montague Elementary School. The Acoustical
Testing Category Area II and III projects provide for the testing of
additional dwellings within the projected 60-65 CNEL noise contour to consider
their eligibility for treatment based on interior noise standards, as directed
by Council.
Communications Equipment
Our latest estimates indicate that without additional funds, the
Communications Program will begin experiencing shortfalls in funding required
to meet scheduled equipment replacements within the five-year horizon of this
CIP. Projected shortfalls begin in 2001-02 ($83,000) and continue for the
remaining two years of the plan: $1.1 million in 2002-03, and $683,000 in
2003-04. Without an alternate funding strategy, these shortfalls will severely
impact the scheduled replacement of equipment in those years, including the
replacement of critical Public Safety Mobile Data System equipment. The
shortfalls would continue to increase in future years under the current
funding structure. As directed by Council, a strategy to address this gap will
be developed as part of the next Capital Improvement Program.
It will also be necessary to monitor impacts on the Communications Program
which will result from recent legislation related to the Federal
Communications Commission (FCC), called "refarming". Refarming is a
new FCC program that will allow for a more efficient use of the radio
frequency spectrum. The program is being implemented, in part, by a FCC
mandate requiring all radio equipment sold today to be compliant with a new
set of equipment standards. Since the majority of all existing radio systems,
including the City’s, are based on the older equipment standards, radio
manufacturers have been "forced" to design and sell dual standard
equipment. This new equipment is more expensive and sophisticated than older
equipment with only a single standard, but has to be purchased in order to
accommodate the FCC’s "phased in" solution to increasing the
efficiency of the radio frequency spectrum. Higher costs for equipment
resulting from this change have been included in this plan.
Fire Protection Master Plan
The development of a comprehensive Fire Protection Master Plan was begun in
1998-99 and is anticipated to be completed for presentation to the City
Council later this fiscal year. This master plan will analyze the Fire
Department’s current delivery of service and identify improvements necessary
to provide the most effective and efficient emergency services to meet the
City’s current and future needs. It is anticipated that this study may
identify the need for several new stations that could have a significant
impact on both the Capital and Operating Budgets.
Fire Station Construction
The construction of a new facility for Station One on property adjacent to
the existing Fire Station One was started in the spring of 1999 with the new
facility scheduled to open in May 2000. The Redevelopment Agency is providing
most of the funding for the construction of this station.
The relocation of Fire Station 27 to a new facility at Bernal Road and San
Ignacio Avenue is anticipated to be completed in February 2000. The City, the
Redevelopment Agency, Shea Homes, and other developers will share the cost of
the station. The new location will provide better coverage in the Edenvale
area due to improved access to major roads.
Construction of a new Fire Station 31 in the Evergreen area is nearly
complete. The construction costs of this new station are being entirely paid
for by the Evergreen Specific Plan developers.
The Communications Hill Specific Plan states that developers must build a
turnkey fire station in order to complete development of Communications Hill.
In addition to the fire station, the developers have agreed to purchase fire
apparatus for the new station. The contribution from the developers to
purchase the apparatus has been included in the CIP. The operating and
maintenance costs of this new station will exceed $1 million per year.
Redevelopment Agency Library Projects
The Redevelopment Agency’s Capital Improvement Plan for the Neighborhood
Business Districts includes $6.2 million towards the development of a new
branch library and youth center in the Alum Rock neighborhood of East San
Jose. Preliminary discussions have been initiated with the East Side Union
School District and Santa Clara County as potential partners. Exploration of
this concept was included as part of the Library’s Facilities Master Plan.
Parking
Plans are currently being developed to construct two new parking facilities
in the downtown area with Redevelopment Agency funding. The first facility
will be located on the northeast corner of Fourth and San Fernando Streets.
The second facility will be located on the southeast corner of San Fernando
and Second Streets (Block 3). These facilities are targeted to become
operational in 2001-02 and 2002-03, respectively.
A third facility, targeted for completion in 2003-04, will be located in
the South of First Street Area (SoFA) and is planned to be, if feasible,
constructed with City Parking Funds, with the Redevelopment Agency funding
land acquisition for the project. An $8 million reserve is in the CIP to be
used to partially fund this facility. Once site acquisition plans have been
further developed, City staff, in conjunction with the Downtown Parking Board
and the Redevelopment Agency, will bring forth recommendations for the
remainder of the funding necessary for this facility to the City Council. Cost
estimates will depend on the specific location and size of the facility.
Preliminary cost estimates for the structure alone total $23-27 million.
Conceptual plans call for construction costs beyond the $8 million reserve to
be financed through revenue bonds supported by future revenues in the Parking
Fund. The impact of Phase Two of the new Free Parking Program and other
operational issues will, however, need to be closely evaluated in terms of
their impact on the ability of the Parking Fund to meet the bonding
requirements of a new parking facility. The preliminary estimates now
indicate, for example, that a shortfall in meeting the bonding requirements
could exist due to reduced revenues from the Phase Two Free Parking Program.
Storm Sewer Program
The Storm Sewer Capital Fund receives revenue from the Storm Sewer
Operating Fund for capital expenditures. The Storm Sewer Capital Fund provides
for capital improvement projects, street sweeping, storm system maintenance,
the Storm Drain Management System (SDMS), and the federally mandated Non-Point
Source Pollution Control Program. The Storm Sewer Fees are derived from annual
charges imposed on properties for these services. Each year, funding ($1.6 to
$3.3 million in this plan) is reserved for capital improvements. Only the
capital portion of this fund is displayed in the Capital Improvement Program.
A $100,000 annual reduction in the amount of funding previously scheduled to
be transferred from the Storm Sewer Operating Fund to the capital fund was
reflected in the Proposed CIP. This reduction reflected an estimate of the
effects of possible revisions to the Storm Sewer Fee structure then under
consideration by the City Council. Subsequent to the release of the Proposed
CIP, the City Council directed an additional reduction of $1.1 million in
1999-2000. In order to accommodate the additional reduction, it was necessary
to delay the Julian-Guadalupe project by two years and shift other project
expenditures to the Storm Drainage Fee Fund.
Other sources of funds for the Storm Sewer Capital Program include
Redevelopment Agency contributions for the Rincon storm sewer improvements,
developer contributions, interest earnings, and loan repayments. The
Redevelopment Agency has committed in its budget a total of $24,225,000 over a
three-year period for the construction of storm sewer improvements in the
North San Jose - Rincon De Los Esteros area. This amount is needed to
construct pump stations and major pipeline improvements to alleviate recurring
drainage problems experienced in the area bounded by Guadalupe River and
Coyote Creek between Highway 101 and Montague Expressway. The improvements
were identified in the Storm Drain Master Plan completed in January 1999. The
Rincon Storm System Improvement project, the second phase of activity in this
area, is fully funded from the Redevelopment Agency contribution. The first
phase of activity was construction of the Rincon Pump Station, which was
funded by both the Redevelopment Agency and the City.
Route 87
The highest priority regional project for the City of San Jose is the
upgrade of Route 87 to a freeway between Julian Street and Route 101. The
project will convert the existing four-lane Guadalupe Parkway to a six-lane
freeway. The purpose of the project is to relieve the severe congestion that
occurs along Guadalupe Parkway and to improve access to Downtown San Jose, the
Civic Center area, and the San Jose International Airport. The City of San
Jose and Caltrans are jointly implementing the project. The majority of the
project funding has been committed from state, federal, and other sources in
the amount of $149.2 million. The City has previously committed to providing
$22.3 million to help implement the project, the majority of which will be
repaid to the City by the Redevelopment Agency.
The estimated cost of the Route 87 project has increased significantly over
the past year, primarily due to the substantial escalation in property costs
for project land acquisition. A total funding increase of $29.85 million is
needed to complete the project. The City is working with Valley Transportation
Authority to obtain an increase in State funding for the project in the amount
of $22.0 million. Additionally, an increase in the City and Redevelopment
Agency funding for the project in the amount of $7.85 million has been
included in this CIP. In order to fund the City’s portion of the increased
cost ($4.47 million), three projects were required to be deferred by one or
two years. The Senter Road: Capitol to Monterey project and the Berryessa
Road: Commercial to Mabury project were deferred one year. The Berreyessa
Road: Commercial to Jackson project was deferred two years. These projects
were selected based on the significant amount of funding required in the first
three years of the CIP. The increase in local funding is necessary to fulfill
the City’s project implementation responsibilities and to support Caltrans
with project design and management to assure a timely project completion. The
City’s completion goal for the Route 87 freeway is December 2001.
Transportation Infrastructure Needs
The General Plan assumes a build out of the City’s planned land uses by
the year 2010. The local transportation infrastructure improvements needed to
support the build out are estimated at $670 million (in current dollars). The
majority of this need, $500 million, is the cost of building out the major
street system to meet the adopted level of service policy goals. The following
chart lists the City’s various needs by type.
Inventory of Transportation Infrastructure Needs ($ Millions)
| Arterials and Collectors |
|
|
- Major Street System Capacity Development (Level of Service
Improvements)
|
|
$ 500
|
| Operations and Safety |
|
|
|
|
|
40
|
|
|
|
15
|
- Pedestrian Facilities (Sidewalks, Curb Ramps)
|
|
10
|
- Bicycle Facilities (Bike Lanes, Bike Paths)
|
|
35
|
| Rehabilitation |
|
|
- Bridge Rehabilitation/Replacement
|
|
25
|
|
|
|
10
|
| Environmental Enhancements |
|
|
- Median Island Landscaping
|
|
35
|
| |
|
|
| |
TOTAL |
$ 670
|
There continues to be a substantial disparity between available resources
and the identified City transportation needs for both infrastructure
development and maintenance. In order to support a complete build out of the
General Plan land uses by the year 2010, the prorated infrastructure need over
the next five-year period would be approximately $305 million; but only $226
million in funding is currently available. Additionally, street maintenance
needs over the five-year period are estimated to be $112 million, with only
$84 million in funding available. If these shortfalls are not eventually
addressed, over time the City’s infrastructure will deteriorate and economic
growth could be slowed by restraints on development imposed by regional
authorities with jurisdiction over traffic congestion and air quality.
Street Maintenance
A significant effort has been made in this CIP to increase funding for
street maintenance. The CIP includes $15.3 million for slurry seal and
resurfacing, $29.6 million for Measure "A/B" funded street
maintenance, and $6.3 million for TEA 21 funded street maintenance. In order
to receive Measure "A/B" funds for street maintenance, the program
requires agencies to comply with the maintenance of effort (MOE) component.
This requirement assures the VTA that the grant funds are not used to replace
local funds currently allocated for pavement maintenance. To meet this
requirement, the Street Maintenance program was increased by $2.0 million per
year. The CIP also reflects transfers to the General Fund for Maintenance
($6.7 million) and Slurry Seal ($2.0 million), debt service payments for
street improvements already completed ($4.5 million) and a Reserve for TEA 21
Grant Projects – Cycle II Projects ($15 million). The total annual Street
Maintenance is approximately $22 million based on a ten-year backlog
elimination strategy. The additional funding provides almost all that is
needed to meet this goal in the first three years of the program, however,
significant shortfalls occur in the final two years as the Measure
"A/B" funding is no longer available.
Parkland Dedication Fees and Turnkey Projects
In March of 1998, the City Council completed a comprehensive review of the
fee structures for both the Parkland Dedication Ordinance and the Park Impact
Fee Ordinance. This program requires dedication of land and/or payment of fees
from developers to meet the needs for park and recreation facilities generated
by new housing development. Fees collected through this program are
accumulated in the Park Trust Fund.
The result of the 1998 review was the first upward adjustment of fees in
the ten-year history of the program. In addition to the fee changes, revisions
were made to address other needed adjustments in the ordinances. With this new
fee structure and program changes, activity in the Park Trust Fund is already
beginning to increase, as indicated by the number of allocations for projects
in the Park and Community Facilities Development Capital Program.
It is anticipated in future years that the bulk of the contributions under
the Parkland Dedication Ordinance will be in the form of parkland dedication
and development that occurs as part of new housing projects. Nevertheless, in
many cases in-lieu fees will be accepted and there will be a significant
increase in this fund over time. The Council-approved methodology for the
allocation of these fees is to budget actual receipts, since it is not
possible to accurately project whether the developer will choose to develop a
facility or pay the in-lieu fee.
Unfunded Projects
A list of unfunded projects that would require General Fund support is
included in the Municipal Improvements section of the document to more
completely catalogue critical maintenance needs. Funding all 21 projects on
this list would require General Fund allocations of over $14.7 million over
the five year period. Based on recent five-year General Fund forecasts, of
course, this level of funding will not be possible. The list is included to
provide a set of projects that could be considered should additional funding
become available.
A more comprehensive list of unfunded capital needs was prepared for
informational purposes and given to Council as part of the 1996-97 Mid-Year
Budget Review. The list represented the unfunded needs identified by
departments with responsibility for capital facilities. Enterprise facilities
such as the Airport and Water Pollution Control Plant were not included since
these facilities are funded directly from user fees. In compiling the lists of
unfunded needs, departments identified the approximate cost of meeting service
level goals identified in the General Plan or other strategic planning
documents. Most of the service level goals do not include specific sites or
facilities, but rather reflect an estimate of facilities needed based on
population. Most of the costs reflect an order of magnitude estimate, based on
average land acquisition or construction costs at this time. Actual costs of
capital facilities acquisition and development would vary in the future due to
factors such as inflation, location or design. The total cost of the unfunded
capital needs identified in that report exceeded $1.9 billion. This list will
be updated for use in the next Capital Improvement Program to include the
results of strategic plans currently under development.
The needs were categorized into the following seven groups:
| Park and Community Facilities |
$ 743,500,000
|
| Traffic |
662,904,000
|
| Conventions, Arts and Entertainment |
206,405,000
|
| Storm Drainage |
185,000,000
|
| Municipal Improvements |
72,678,000
|
| Fire |
25,109,900
|
| Library |
23,690,000
|
| Communications |
11,455,000
|
| |
|
| TOTAL |
$ 1,930,741,900
|
Although the unfunded list appears overwhelming, many items on the list
represent long-term, rather than short-term, needs. It is intended that this
information be used to develop strategies for upcoming five-year Capital
Improvement Programs. Each year, as funding becomes available, projects from
these lists are reviewed and proposed to address needs.
Central Service Yard
The recently completed first phase of construction at the new Central
Service Yard remodeled facilities for vehicle maintenance functions, General
Services’ Administration, the Public Works Engineering Services Division,
and maintenance operations previously located at the Empire Street Yard. Phase
I of the project also moved the Purchasing and Stores operation from its
previous location at the Las Plumas Warehouse. Archive and storage facilities
have also been made available for the Historical Museum collection, the Fire
Muster Team, and Christmas in the Park exhibits. Improvements include paving,
security, and other site improvements. In order to provide sufficient funding
to complete the first phase of the project on schedule, an interfund loan of
$2.9 million from the Sanitary Sewer Connection Fee Fund to the Service Yard
Construction and Conveyance Tax Fund was approved. The loan will be repaid, at
the pooled investment rate of return, using the proceeds from the sale of the
Las Plumas and the Stockton and Julian warehouses anticipated in 1999-2000. In
December 1998, the City Council approved Phase II of the Central Service Yard
Master Plan, as well as an accompanying financing strategy. The second phase
of construction will accommodate the relocation of all Main Yard functions to
the Central Service Yard. These improvements, totaling $19 million, are being
funded by the sale of bonds and the sale of surplus City land, including the
Main Yard and the Roberts Road Children’s Shelter site. The proceeds for the
Roberts Road Children’s Shelter site used for this project are above the $2
million already committed toward a swimming pool project in South/Central San
Jose.
Water Pollution Control Plant Expansion
Due to extensive efforts in water conservation, water recycling and
technology improvements in flow metering, the 1998 dry weather flow was
reduced by 6 million gallons per day (mgd). As a result, the plant expansion
project first included in the Adopted 1999-2003 CIP is now projected to be
deferred beyond 2004.
FIVE-YEAR
REVENUE SUMMARY
The 2000-04 CIP derives its funding from a variety of sources. The following
table provides a listing of those sources grouped by major category, along with
a comparison with the Adopted 1999-2003 Program.
D
|
Source
|
1999-2003 CIP
($ millions) |
2000-2004 CIP
($ millions) |
Difference
($ millions) |
| |
|
|
|
| Beginning
Fund Balances |
$ 256.2
|
$ 300.1
|
$ 43.9
|
| Sale of
Bonds |
463.2
|
465.2
|
2.0
|
| Other
Agencies/Grants |
204.9
|
187.5
|
(17.4)
|
| Fees
and Charges |
186.6
|
191.4
|
4.8
|
| Interfund
Transfers |
339.5
|
343.0
|
3.5
|
| General
Fund |
32.4
|
39.4
|
7.0
|
| Interest
Income |
54.9
|
38.4
|
(16.5)
|
| Other
Income |
14.8
|
34.0
|
19.2
|
|
|
| TOTAL |
$ 1,552.5
|
$ 1,599.0
|
$ 46.5
|
The increase in Beginning Fund Balances primarily reflects delays in
completion of prior year projects. Most of this additional fund balance will be
rebudgeted into the current year in order to complete projects originally
anticipated to be completed last fiscal year.
The increase in the Sale of Bonds reflects the deferral of the Water
Pollution Control Plant financing ($96 million) offset by increases in projected
financing for Airport Master Plan projects ($67 million), Civic Center
Relocation ($20.5 million) and the Central Service Yard ($10.2 million).
The most significant reduction from the previous five-year plan was in
anticipated grants from other agencies. This primarily reflects the receipt of
State Revolving Fund Loans for the Water Recycling Project in the prior year.
Since these loans were of a one-time nature, they are no longer reflected in
this CIP.
Interfund Transfers are the second largest source of revenue in the 2000-04
Capital Improvement Program. The largest transfers are transfers within and
among Airport funds ($100.4 million) and from the Sewer Service and Use Charge
Fund to the Sanitary Sewer Capital program ($80 million) and to the Water
Pollution Control program ($29 million). In addition, $48.3 million is being
transferred to the Water Pollution Control program in a combination of City and
tributary agencies contributions for Plant projects. Other large transfers
include the Library Benefit Assessment District funds used for capital
expenditures ($16.0 million), the Parking Program ($10.9 million) and Parks
funds ($32.7 million) and Storm Sewage funds ($13.8 million).
The decrease in interest income primarily reflects reduced projected interest
earnings on bonds and commercial paper to be issued for Airport projects.
Fees and Charges represent the largest earned revenue source and fourth
largest category of funding. The 2000-04 total of $189 million is an increase of
$5 million from the level included in the 1999-2003 CIP. This small increase
primarily reflects a small upward revision to projections for construction
activity during the five-year period and the addition of water utility fees
previously budgeted in the Operating Budget.
The following table compares the components of the 2000-04 Fees and Charges
estimates with those included in the Adopted 1999-2003 CIP.
D
|
Source
|
1999-2003 CIP
($ millions) |
|
2000-2004 CIP
($ millions) |
|
Difference
($ millions) |
|
|
|
|
|
|
| Construction
and Conveyance Tax |
$ 72.2
|
|
$ 71.8
|
|
$ (0.4)
|
| Construction
Excise Tax |
58.4
|
|
61.5
|
|
3.1
|
| Building
and Structure Tax |
40.3
|
|
40.3
|
|
0.0
|
| Sanitary
Sewer Connection Fees |
8.1
|
|
7.8
|
|
(0.3)
|
| Storm
Drainage Fees |
3.0
|
|
2.9
|
|
(0.1)
|
| Major
Water Facilities Fees |
2.8
|
|
2.8
|
|
0.0
|
| Water Utility Fees |
0.0
|
|
2.6
|
|
2.6
|
| Residential
Construction Tax |
1.7
|
|
1.7
|
|
0.0
|
|
|
|
|
|
|
| TOTAL |
$ 186.5
|
|
$ 191.4
|
|
$ 4.9
|
The increase in major construction-related revenues ($3.1 million)
anticipated in this plan would primarily benefit the Traffic Capital Program.
The following chart illustrates the projected revenue and actual tax receipts
for these major revenues.
D
The small decrease from prior projections for anticipated Construction and
Conveyance Tax collections ($449,000) reflects projections for a slightly slower
housing resale market. This reduction, which is actually $1 million less than
originally forecasted last November, impacts the Parks, Library, Service Yards,
Fire, and Communications programs.
D
ART IN PUBLIC PLACES
In December 1984, the Council initiated the Art in Public Buildings Program,
which directed 1% of construction project budgets over $500,000 to be allocated
for public art. In 1988, the Council increased the public art allocation to 2%
of construction budgets. The 1999-2003 Capital Improvement Program includes
eighteen public art allocations for eligible construction projects. All other
construction projects with budgets exceeding $500,000 were deemed to be
ineligible under the provisions of the program as approved by Council. In
addition to the projects included on this list, the Redevelopment Agency also
allocates funds for public art projects in their CIP. The public art allocations
included in the 2000-04 are listed on the following chart.
ART IN PUBLIC PLACES
|
FUND |
|
PROJECT |
YEAR |
AMOUNT |
|
|
|
|
|
| Airport R & R |
|
Federal Inspection Service
Facility |
1999-2000 |
$ 151,000
|
| Council District 4 |
|
Cataldi Park Renovation |
1999-2000 |
18,000
|
| Council District 4 |
|
River Oaks Park |
1999-2000 |
7,000
|
| Council District 8 |
|
Groesbeck Hill Park Renovation |
1999-2000 |
13,000
|
| Council District 8 |
|
Meadowfair Park |
1999-2000 |
3,000
|
| Council District 8 |
|
Welch Park |
1999-2000 |
2,000
|
| City-Wide Parks |
|
Camden Pool |
1999-2000 |
10,000
|
| City-Wide Parks |
|
Guadalupe River South |
2002-2003 |
12,000
|
| City-Wide Parks |
|
Happy Hollow Infrastructure
Renovation |
1999-2000 |
29,000
|
| City-Wide Parks |
|
Historical Museum Parking Lot |
1999-2000 |
17,000
|
| City-Wide Parks |
|
Japanese Friendship Garden/Koi
Pond |
1999-2000 |
10,000
|
| City-Wide Parks |
|
Kelley Park Parking Lot |
1999-2000 |
15,000
|
| City-Wide Parks |
|
Los Gatos Creek Trail |
1999-2000 |
12,000
|
| Lake Cunningham |
|
Parking Improvements |
1999-2000 |
37,000
|
| Lake Cunningham |
|
Perimeter Landscaping |
2001-2002 |
22,000
|
| Library C&C |
|
West Valley Branch Library |
1999-2000 |
156,000
|
| Civic Center |
|
Civic Center Relocation |
1999-2000 |
400,000
|
| Construction Excise |
|
Transit Mall |
1999-2000 |
300,000
|
|
TOTAL |
|
|
|
$ 1,214,000
|
OPERATING BUDGET IMPACT
Projects in the 2000-04 Capital Improvement Program will result in
significant additional operating costs in the General Fund as the result of
implementing capital projects.
In compliance with Council policy, preliminary estimates of the impact of
capital projects on the General Fund have been formulated and summarized in the
following chart. (The estimated costs are provided by the departments and have
not yet been subject to a full analysis by the Budget Office.)
| |
|
2000-01 |
|
2001-02 |
|
2002-03 |
|
2003-04 |
|
|
|
|
|
|
|
|
|
| Park and Community Facilities |
|
$ 111,000
|
|
$ 105,000
|
|
$ 107,000
|
|
$ 109,000
|
| Other Agency Park Projects |
|
570,000
|
|
587,000
|
|
616,000
|
|
647,000
|
| West Valley Branch Library |
|
|
|
256,000
|
|
266,000
|
|
278,000
|
| Alum Rock Branch Library (RDA) |
|
|
|
519,000
|
|
555,000
|
|
594,000
|
| Communications Hill Fire Station |
|
|
|
|
|
|
|
1,338,000
|
| Street Landscaping |
|
121,000
|
|
121,000
|
|
121,000
|
|
121,000
|
| Street Lighting |
|
3,500
|
|
16,000
|
|
28,000
|
|
40,000
|
| Traffic Signals |
|
47,600
|
|
74,600
|
|
118,600
|
|
151,600
|
|
|
|
|
|
|
|
|
|
| TOTAL |
|
$ 853,100
|
|
$ 1,678,600
|
|
$ 1,811,600
|
|
$ 3,278,600
|
Additional and often very significant operating budget impacts will also
result from such Redevelopment Agency projects as the proposed Symphony Hall and
Fox Theater. Operating costs and agreements with non-profit operators of these
facilities have not yet been developed.
Changes in the Parkland Dedication Ordinance, discussed earlier in this
overview, could also have a significant impact on the General Fund since the
changes would encourage more "turnkey" park developments.
The CIP for neighborhood parks focuses capital improvements on rehabilitation
and renovation, rather than acquiring or developing new facilities with
significant operating and maintenance impact. Significant funding has been
programmed into reserves, however, for future projects to meet neighborhood
needs for parkland and recreation facilities.
Policies, guidelines and criteria for identifying the operating and
maintenance impact of capital projects were developed to clearly identify the
operating budget impact prior to funding capital projects. Under the approved
policy, the funding sources for operating costs of a capital project in excess
of $100,000 per year would need to be identified prior to the approval of the
project.
Two City projects, the West Valley Library and Communications Hill Fire
Station, have been identified as falling into this category. The operating
expenses for these facilities, however, would not begin until future years.
Funding for these expenses, which will most likely be from the General Fund,
will be addressed in future forecasts.
RELATIONSHIP TO THE GENERAL PLAN AND URBAN DEVELOPMENT POLICY
A review of the impact of the Capital Improvement Program in relation to the
City's General Plan has been included in the overview section of many capital
programs. The most detailed impacts on the General Plan are described in the
Library, Traffic and Parks programs, which have specific General Plan goals.
CONCLUSION
Consistent with the November 1998 Forecast, our projections indicate that the
strong revenue growth in capital revenues in the last several years has slowed,
with the one exception of Construction and Conveyance Tax revenues, which have
maintained strong collections. Fortunately, we are not experiencing declines
beyond those that had already been projected. It must be noted again, however,
that the City's ability to maintain its existing facilities is limited by
insufficient revenues and the backlog of deferred maintenance.
As a result, the unfunded capital needs discussed in this overview and in
each of the program sections continue to be of great concern. Even in an
improved economy, the current revenue sources dedicated to capital programs are
inadequate to provide the needed level of support for necessary projects. The
addition of new facilities will only worsen that situation. It is critical,
therefore, that we give priority with existing funds to the renovation and
adequate maintenance of our current facilities.
On a more positive note, however, despite the many projects which continue to
be unfunded, or funded below the desired level, San Jose will still be able to
provide for a significant investment in infrastructure and community
improvements over the next five years.
Overall, I am confident that staff and the Council working together will
continue to find creative ways to address the City's capital needs with the
resources available.
It is important to close with an acknowledgment of the outstanding efforts
provided by the various City staff members who participated in the development,
analysis, and production of the Capital Budget and CIP.
DEBRA J. FIGONE
ACTING CITY MANAGER
Back to Top
|
|