Subject:     STREET LIGHTS CITYWIDE 2001 PROJECT SUPPLEMENTAL MEMO

 

COUNCIL DISTRICT:  Citywide

 

REASON FOR SUPPLEMENTAL MEMO

 

This memorandum provides additional information following the bid opening on May 24, 2001.

 

RECOMMENDATION

 

Report on bids and award of contract for the Street Lights Citywide 2001 Project to the sole bidder, Pacific Electric Co., in the amount of $378,229.65 and approval of a contingency in the amount of $38,000.  CEQA:  Exempt.

 

BACKGROUND

 

On May 22, 2001, a memorandum was forwarded to the City Council for the June 5, 2001, Council meeting.  The purpose of this supplemental memorandum is to provide additional information from the bid opening.

 

ANALYSIS

 

Bids were received on May 24, 2001, with the following results:

 

 

Contractor

 

Bid Amount

Variance Amount

Over/(Under)

Percent

Engineer’s Estimate

$414,000.00

--

--

Pacific Electric Company

  (San José)

378,229.65

(35,770.35)

(8.6)

 

The sole bid submitted by Pacific Electric Company is 8.6 percent below the Engineer’s Estimate.  This is considered a reasonable price based upon the Engineer’s Estimate and recent bid results of similar projects.

 

A $38,000 contingency is requested for any unforeseen conditions which may arise during construction of this project.

 

PUBLIC OUTREACH

 

This project was listed on the City's Internet Bid Line and advertised in the San José Mercury News and San José Post Record.  Bid packages for all public works construction projects are routinely provided to a standard list of various contractor organizations, builder's exchanges and disadvantaged business organizations, including United Minority Business Enterprises and the San José Minority Business Development Center.  Staff will attend community meetings if necessary, continue to distribute preliminary engineering notices to the residents near the project locations, and respond to comments and questions regarding the project.

 

 

COORDINATION

 

This project was coordinated with Pacific Gas and Electric Company, the Offices of Equality Assurance, Risk Manager and the City Attorney, and the Department of Parks, Recreation and Neighborhood Services.

 

COST IMPLICATIONS

 

1.         COST OF RECOMMENDATION:  $378,229.65

 

2.         COST OF PROJECT:

 

Project Development                                                                            $  58,000.00

Construction                                                                                           378,229.65

Design & Construction Management                                                       132,000.00

Contingency                                                                                             38,000.00

                             TOTAL                               $606,229.65

 

4.  SOURCE OF FUNDING:              001 – General Fund

                                                            465 – Construction Excise Tax Fund

 

3.      ESTIMATED START DATE OF CONSTRUCTION:  July, 2001

 

4.      ESTIMATED COMPLETION DATE OF CONSTRUCTION:  May, 2002

 

BUDGET REFERENCE

 

Fund :                            001

Appn:                            2872

R.C.:                              703009

Amount:                         $2,672,719

Budget Document:          2000-2001 Appropriation Ordinance #26141, Section 2.25, Item #n.13

 

Fund :                            465

Appn:                            5356

R.C.:                              113893

Amount:                         $1,260,000

Budget Document:          2000-2001 Appropriation Ordinance #26141, Section 2.4, Item #z.05.2

 

NONDISCRIMINATION

 

The City of San José Nondiscrimination Requirements are included in this project as required by Chapter 4.08 of the San José Municipal Code.

 

CEQA

 

Exempt.

 

 

RAJEEV BATRA

Acting Director, Public Works Department