Subject: CDBG:
DELNO STREET RECONSTRUCTION PROJECT
COUNCIL DISTRICT: 3
SNI AREA: N/A
Report on bids and award of contract for the CDBG: Delno Street Reconstruction Project to the lowest responsive bidder, JJR Construction, Inc., in the amount of $283,475, and approval of a contingency in the amount of $28,000. CEQA: ND.
The Pavement Management System (PMS) of the Infrastructure Management System has identified minor streets in need of reconstruction. These streets were prioritized by the Department of Transportation on the basis of visible pavement defect data and the condition of existing sanitary and storm sewer facilities.
The PMS has identified Delno Street in the Sherwood residential area as a minor street in need of reconstruction (see attached map). This project is partially funded by the Community Development Block Grant (CDBG) program. Additional funding sources are the Sanitary Sewer and Storm Drain capital programs.
The scope of work for this proposed project includes replacement of nearly 300 feet of deteriorated asphalt pavement, curb, gutter, sidewalk, driveways, modifications of existing street lighting, and upgrading the existing sanitary sewers and storm drain facilities.
Bids were received on June 28, 2001 with the following results:
|
|
Variance |
Over/(Under) |
|
|
Contractor |
Bid Amount |
Amount |
Percent |
|
|
|
|
|
|
MCH General Engineering Contractor, Inc. |
$339,935 |
$91,890 |
37% |
|
(San José, CA) |
|
|
|
|
Wattis Construction Company, Inc. |
318,730 |
70,685 |
29% |
|
(San José, CA) |
|
|
|
|
JJR Construction, Inc. |
283,475 |
35,430 |
14% |
|
(San Mateo, CA) |
|
|
|
|
Norman B Hough, Inc. |
253,728 |
5,683 |
2% |
|
(Campbell, CA) |
|
|
|
|
Engineer's Estimate |
248,045 |
--- |
--- |
|
Vanguard Construction |
230,800 |
(17,245) |
(7%) |
|
(Oakland, CA) |
|
|
|
There was one
addendum to the plans and specifications issued during the project
advertisement period. The two lowest
bidders, Vanguard Construction and Norman B Hough, Inc. submitted their bid
proposals without copies of a signed addendum.
This omission is a cause for the rejection of their bids, in accordance
with Section 2-1.14 of the Standard Specifications.
JJR Construction,
Inc. had the next low bid. Its bid,
accompanied by a signed addendum, is 14 percent higher than the Engineer’s
Estimate. CDBG funding requires
that the construction of the project be completed by December of 2001. Due to this time constraint, it is not
feasible to reject all bids and re-bid the project. Staff recommends that the contract be awarded to JJR Construction
Company, Inc., despite the variance from the EE.
The
differences between JJR’s bid and the Engineer’s Estimate are mainly in the
prices of roadway items such as asphalt paving and concrete curb, gutter, and
sidewalk. JJR’s unit prices may reflect
uncertainties in the cost of raw materials due to volatility in the price of
energy and petroleum.
This work
includes numerous conform areas to existing improvements, and it is expected
that unforeseen conditions may be encountered during construction. Therefore, a $28,000 contingency is
requested for this project to cover these and other potential unforeseen
conditions.
This project is being coordinated with the neighborhood association. Additionally, it was listed on the City's Internet Bid Line and advertised in the San Jose Mercury News and San Jose Post Record. Bid packages for all public works construction projects are routinely provided to a standard list of various contractor organizations, builder's exchanges and disadvantaged business organizations, including United Minority Business Enterprises and the San José Minority Business Development Center.
This project was coordinated with utility companies, the Departments of Transportation and Parks, Recreation and Neighborhood Services, and the Offices of Equality Assurance, Risk Manager and the City Attorney.
1.
COST OF RECOMMENDATION:
$283,475
2. ESTIMATED COST OF PROJECT:
Project Development $ 25,000
Construction 283,475
Design & Construction Management 120,000
Contingency 28,000
TOTAL $456,475
3. SOURCE OF FUNDING: 441 – Community Development Block Grant Fund
545 – Sewer Service and Use Charge Capital Fund
469 – Storm Drainage Service Capital Fund
4. ESTIMATED START DATE OF CONSTRUCTION: September, 2001
5. ESTIMATED COMPLETION DATE OF CONSTRUCTION: December, 2001
Fund: 441 545 469
Appn: 6976 4271 4287
R.C.: TBD 113423 115833
Amount: $247,544 $4,200,000 $529,000
Budget Document: Appropriation Appropriation 2001 – 2002 Appropriation
Ordinance #26415 Ordinance #26415 Ordinance #26415
Sect. 13.01, Item 7e Sect. 4.02, Item 1j Sect. 3.07, Item 1f
The City of San José Nondiscrimination Requirements are
included in this project as required by Chapter 4.08 of the San José Municipal
Code.
Exempt.
RAJEEV BATRA
Acting Director, Public Works Department