Subject: CENTRAL SERVICE YARD EMERGENCY
GENERATOR
Report on bids and award of contract for the Central Service Yard Emergency Generator Project to the low bidder, Steiny and Co., Inc., in the amount of $270,620, and approval of a contingency in the amount of $30,000. CEQA: Exempt.
The
City of San José has a policy of installing emergency electrical power
generators at all service yards. An
emergency power generator can provide enough power to a facility to assure
continued operation during extended PG&E power outages. The Department of
General Services requested that the Department of Public Works provide
engineering services to prepare contract drawings and specifications to install
an emergency generator at the Central Service Yard.
Bids were received on May 10, 2001 with the following results:
|
Contractor |
Base Bid |
Variance Amount |
Over/ (Under) Percent |
|
|
|
|
|
|
SheetsEnterprises (San José) |
$453,807 |
$128,807 |
39.6 |
|
Bay Counties Electric, Inc. (San José) |
352,900 |
27,900 |
8.5 |
|
Engineer’s Estimate |
325,000 |
--- |
--- |
|
McDonald Electric, Inc. (San Martin) |
305,844 |
19,156 |
(5.8) |
|
Steiny and Co., Inc. (Vallejo) |
270,620 |
54,380 |
(16.7) |
The low bid submitted by Steiny and Co., Inc. in the amount of $270,620 is 16.7 percent lower than the Engineer’s Estimate. Staff considers this to be a good price for the work involved in this project.
A contingency in the
amount of $30,000 is requested for unforeseen conditions that may arise during
construction.
This proposed project was listed on the City’s Internet Bid Line and advertised in the San José Mercury News and San José Post Record. Bid packages for all Department of Public Works construction projects are routinely provided to a standard list of various contractor organizations, builder’s exchanges, and disadvantaged business organizations, including United Minority Business Enterprises and the San José Minority Business Development Center.
This project has been coordinated with the Department of General Services, and the Offices of the City Attorney, Risk Manager, and Equality Assurance.
1. COST OF RECOMMENDATION: $270,620
2. COST OF PROJECT:
Contingency 30,000
3. SOURCE OF FUNDING: 395 – Construction and Conveyance Tax – Service Yards
4. ESTIMATED START DATE OF CONSTRUCTION: July, 2001
5. ESTIMATED COMPLETION DATE OF CONSTRUCTION: September, 2001
Budget Document: 2000-01 Appropriation Ordinance, Section 12.50, Item 1(o)
* The $23,620 needed to complete the funding of this project will be provided from
appropriation 6088, Service Yards Equipment, which will be for material costs.
The City of San José Nondiscrimination Requirements are included in this project as required by Chapter 4.08 of the San José Municipal Code.
Exempt.
RAJEEV BATRA
Acting Director, Public Works Department