Subject:         STATUS REPORT – ALUM ROCK PARK IMPROVEMENTS

 

COUNCIL DISTRICT:           Citywide                                 

SNI AREA:           N/A                                                                

 

The purpose of this memo is to provide a status report on the improvements to Alum Rock Park related to the closure of Alum Rock Avenue and the opening of Penitencia Creek Road within Alum Rock Park. 

 

BACKGROUND

 

On May 1, 2001, the City Council approved the memo entitled Alum Rock Park Access and Crothers Road.  This memo approved the recommendations from the staff report entitled Alum Rock Park Status Report, dated April 27, 2001.  The following are the recommendations of that report:

 

a)      Approve the proposed capital improvements to the Penitencia Creek Park Entrance and Trail within Alum Rock Park as part of the 2002-2006 Capital Improvement Program for Parks & Community Facilities.

b)      Continue to work with the affected neighborhood to calm traffic on Penitencia Creek Road;

c)      Continue to prohibit public vehicular traffic on Alum Rock Avenue between Crothers Road and Penitencia Creek Road.  Authorize the use of the road for service vehicles, emergency vehicles, pedestrian and equestrian and bicycle traffic only.

d)      Continue to prohibit public vehicular traffic on Crothers Road between Alum Rock Avenue and Miradero Road.

 

Furthermore, the memo entitled Alum Rock Park Access and Crothers Road directed staff to:

 

1.      Implement traffic and parking control and pedestrian safety measures on Penitencia Creek Road and Alum Rock Avenue.  These should be implemented as soon as possible, and the Administration is directed to work with county and state agencies as necessary to move ahead quickly. 

2.      Implement measures to ensure pedestrians use the Creek Trail and stay off of Penitencia Creek Road.  These measures should at least include improved signage at the entrance of Alum Rock Park, at Quail Hollow/Eagle Rock Parking Lot, at the intersection of Alum Rock Avenue and Penitencia Creek Road, and at both entrances of the Rusticlands Picnic Area.  Other appropriate measures should be considered as necessary to achieve this goal. 

3.      Work with the community to develop and implement a plan to decrease the impact of fire along Crothers Road.

4.      Work with the County of Santa Clara to determine feasibility, cost, and value of repairing Crothers Road for only emergency access, and report back to Council within the next 120 days.

5.      Research and identify all possible sources of funding to fully reopen Alum Rock Avenue and Crothers Road for long-term and safe public use and report back to Council within the next 120 days.  This effort should be coordinated with County staff as appropriate.  A recommendation to Council regarding further feasibility studies should be brought forward with information regarding likely outside funding sources within the next 120 days.

 

CURRENT STATUS OF IMPROVEMENTS AND RECOMMENDATIONS

 

Alum Rock Park Penitencia Creek Parking Lot and Creek Trail - Capital Improvements

 

Parks, Recreation and Neighborhood Services (PRNS) staff has meet with the Department of Public Works (DPW) to initiate the improvements to the Penitencia Creek Trail and the Penitencia Creek parking lot.  These projects are included in the 2002-2006 CIP for Parks & Community Facilities.

 

Work With the Affected Neighborhood to Calm Traffic on Penitencia Creek Road

 

DOT has met with affected residents regarding the location of the road bump on the County portion of Penitencia Creek Road.  The resident input was received and the proposed installation location was approved.  DOT has also responded to a number of phone calls regarding the status of the traffic calming measures and based upon additional resident input has increased the use of NASCOP to include weekend deployments.

 

Implement Traffic and Parking Control and Pedestrian Safety Measures on Penitencia Creek Road and Alum Rock Avenue

 

PRNS staff has met with representatives from the California Highway Patrol (CHP), Santa Clara County Sheriff’s Office (SCCSO), Santa Clara County Department of Roads and Airports (SCCDRA) and various City departments to ensure their commitment to public safety and to deal with traffic and parking issues on Penitencia Creek Road and Alum Rock Ave.  The CHP and SCCSO have stated they will respond to requests for service from park staff to enforce parking and traffic laws in the unincorporated areas adjacent to Alum Rock Park.  Park staff has met with representatives from the SCCDRA to work on parking control signage on the unincorporated roadways.  They are processing the requests for new signage, and expect that it will be installed in September.

 

PRNS has provided extra staff and signage at the Alum Rock Ave. entrance to Alum Rock Park on weekends and holidays to redirect visitors to the new entrance.  Park staff estimates that over 1000 flyers have been distributed at this location.  Approximately 100 vehicles per weekend day in June have been redirected to the new entrance.  In July and August, the number of vehicles coming to the closed Alum Rock Avenue entrance dropped to approximately 50 vehicles per weekend day.  Staff is noticing that one third of the vehicles driving to the closed Alum Rock Avenue entrance are returning visitors who have already been advised of the road closure.  Park informational flyers to encourage compliance with posted speed limits and to encourage usage of the Creek Trail are also available.

 

Increased police patrols have occurred both inside Alum Rock Park and along Penitencia Creek Road leading to the park at the request of the residents living near the park. The Patrol Division, Horse Mounted Unit, and the Traffic Enforcement Unit have increased their presence in the area. Initially citations and warnings totaled 80 during the last two weeks of May, and the first two weeks of June. These numbers took a dramatic drop during the next four weeks to 36. During these last four weeks the citations totaled 48.

 

DOT has installed road bumps and centerlines with raised reflectorized markers within Alum Rock Park.  Additionally, DOT is working with the County to install road bumps on the unincorporated portion of Penitencia Creek Road just outside of Alum Rock Park, as that portion of the road is under County jurisdiction.  DOT expects to complete the permit approval process with the County in the next three weeks and proceed with the installation of the road bump.

 

DOT has also implemented NASCOP enforcement along Penitencia Creek Road, and the NASCOP data indicates that the percentage of drivers exceeding the speed limit by 10 miles per hour or more ranges between four and eight percent, which is between low and average for this type of roadway.  The higher speeding percentages occur during the weekends.

 

August weekday 24-hour traffic count data shows average and 85th percentile speeds have remained the same on Penitencia Creek Road since before it was opened to the park.  However, there has been a three-mile per hour increase in the 85th percentile speed east of Toyon Avenue.  Most weekday speeding occurs during mid-day and before the morning rush hour. 

 

DOT will continue to work with the Police Department to modify speed enforcement to focus on weekends and middays.  In an effort to assist motorists in identifying the new entrance route, DOT has installed additional enlarged signs that provide direction to Alum Rock Park from Alum Rock Avenue, White Road and McKee Road.

 

 

DOT staff also researched Councilmember Reed’s request to paint speed limits on the pavement of Penitencia Creek Road.  Past experience in San Jose has shown that such markings work for short periods of time before portions of the marking are worn away by tire wear.  Additionally, the reflective coatings flake off.  Both of these failures of the street markings render them ineffective.  However, a longer lasting and more effective solution would be the installation of additional, over-sized speed limit signs.  The additional signs will be installed within 30 days.

 

DOT is currently constructing new gates across Crothers Road to replace the removable bollards that exist now and is installing parking prohibition signs on the City right-of-way adjacent to the Alum Rock Avenue closure fence.  These measures are in response to public concerns over parking intrusions by park users who choose not to use Penitencia Creek Road.

 

Implement Measures to Ensure Pedestrians Use the Creek Trail and Stay Off of Penitencia Creek Road

 

PRNS staff has installed trail signage inside of Alum Rock Park that directs trail users onto Penitencia Creek Trail and off of Penitencia Creek Road.  The sign locations include the Penitencia Creek Road entrance, Quail Hollow Bridge area, Rusticlands area, and Creek Trail egresses onto Penitencia Creek Road and Alum Rock Avenue.  Additionally, park staff has laid telephone poles lengthwise from the Penitencia Creek Road entrance gate to the Penitencia Creek stairs/trail head.  This was done to provide a distinguishable path to the trailhead and encourage Creek Trail usage.

 

City staff is researching the feasibility of developing Reach I of the Penitencia Creek Trail.  This particular section of trail will connect to Alum Rock Park near the new Penitencia Creek entrance.  Staff has identified possible properties for acquisition.  These acquisitions will be funded through the Santa Clara County Open Space Authority.

 

Work with the Community to Develop and Implement a Plan to Decrease the Impact of Fire along Crothers Road

 

PRNS staff is working with the community to address fire issues within and adjacent to Alum Rock Park.  Park staff is on schedule for maintaining the park’s fire breaks.  At the request of residents that live along Crothers Road and Peacock Gap Road, park staff has contracted the removal of eucalyptus trees and pine trees that were determined to pose a hazard.  Park staff will coordinate the control and removal of grasses and brush along the Crothers Road park boundary.   Park Rangers continue to monitor the weather and fire conditions inside the park.

 

The City Arborist is coordinating the removal of eucalyptus trees on undeveloped property along Dorel Drive at the intersection of Otto Court.  In addition to these trees, DOT is researching the feasibility of removing eucalyptus trees on adjacent private property.

 

The Fire Department has met on several occasions to discuss the Urban Wildland-Interface Pre-fire Plan for the East Foothills area, including Alum Rock Park.  Participating agencies have included the park’s Ranger staff, California Division of Forestry (CDF), San Jose Information Technologies Department, San Jose Police Department, Santa Clara County Sheriff's Department, and others.  Fire Department staff continues to make progress in compiling information and coordinating meetings with participating agencies.

 

In addition, the Fire Department has:

q       met with DOT to discuss and evaluate road bumps proposed to be placed along the road approaching and inside of the Penitencia Creek Road entrance to Alum Rock Park.

q       met with the Country Club Heights homeowners association to address their concerns regarding Eucalyptus trees and grass in the area surrounding this residential development.  Staff is waiting for their input on the trees.

q       provided the Alum Rock Park Ranger staff with Knox lock boxes to be placed on Crothers Road and the Penitencia Creek Road entrance to Alum Rock Park for access to keys for entrance by emergency fire apparatus.

q       continued to remain informed of changes to access points to Alum Rock Park and the surrounding interface neighborhood.

q       distributes fire hazard information to all Fire stations citywide.

 

Work with the County of Santa Clara to Determine Feasibility, Cost, and Value of Repairing Crothers Road for Only Emergency Access

 

At the beginning of August, the County began construction of a retaining structure for Highland Drive above Crothers Road.  The structure is comprised of three-foot diameter piers over eighty feet deep spaced every six feet.  It has three rows of tie-backs and is over 120 feet long.  Completion of this $1.5 million structure is scheduled for mid-December.  The County is using Crothers Road for construction access.

 

Emergency access to Crothers Road will be facilitated by the installation of the new gates by DOT.  Upon completion of the Highland Drive retaining structure by the County, Crothers Road will be available for emergency access only.  DOT has completed minimal grading and addition of base rock material so that light weight emergency vehicles can have access on this stretch of Crothers Road.  The slide continues to move and expand even during dry weather.  It will be continuously monitored for excessive displacement and closed to emergency access should hazardous conditions develop.

 

Research and Identify All Possible Sources of Funding to Fully Reopen Alum Rock Avenue and Crothers Road for Long-Term and Safe Public Use, And Recommend Further Feasibility Studies

 

The active landslide complex is approximately 375 feet wide and some parts of the slide may be as much as 75 feet deep.  The slide has been active on an intermittent basis for thousands of years and, absent a massive stabilization effort, will continue to move in very wet years in the future.  The slide reactivated in 1998 as a result of the combination of extremely heavy rainfall during a six-week period in January and February and ongoing erosion of the toe of the slide by Penitencia Creek.  The slide also moved to a lesser degree in 1983 and 1987 when rainfall patterns and amounts were similar, but the rain was spread out over a wider time period.  Absent a massive stabilization project that would cause significant environmental damage to the park and Penitencia Creek--and for which regulatory permits may be impossible to obtain--the slide will continue to move intermittently for the foreseeable future.

 

PRNS staff has explored possible sources of funding to fully reopen Alum Rock Avenue and Crothers Road for long-term and safe public use without attempting to stabilize the entire landslide.  The City’s lobbyist in Washington D.C. is communicating with members in Congress to identify possible Federal funding for this purpose.  The City’s lobbyist in Sacramento is also researching possible state funding to support this need.  Both lobbyists are pursuing all possible avenues and staff is also researching other possible sources of funding, such as grants, for this purpose.  At this time, the lobbyists have identified three possible funding sources to investigate: the California Office of Emergency Services, the Community Development Block Grants, and the Federal Highway Administration.  Alum Rock Park may be able to receive funding from these sources, but the prospects for such funding appear poor.

 

As previously discussed with the Council, long term solution(s) to fully reopen Alum Rock Avenue and Crothers Road include the following options:

 

1.      Constructing an A-Frame Structure concrete pier structure with Tie-Backs into the hillside under Alum Rock Avenue.  As currently envisioned, the piers would extend down to 110 feet.  A concrete beam would tie the piers together at the top and serve as the base for Alum Rock Avenue.  The estimates indicate this repair would cost over $6 million--possibly much more--and would require over three years to construct.  Since parts of the roadway would still continue to move incrementally after completion of the project, ongoing maintenance would be required.  There is no guarantee this alternative would result in a viable long term solution for Alum Rock Avenue. 

 

2.      Constructing a bridge across the slide area on Crothers Road to reconnect the stable portions of Crothers Road.  This proposal requires a structure 600 feet long and 30 feet wide.  The foundation involves deep piers with grade beams and tie-backs similar to the proposal for the Alum Rock Park Entrance Road.  The bridge proposal is estimated at $12 million dollars exclusive of any land acquisition that may be required. 

 

Due to the complexity and scale of the geotechnical investigation necessary to determine exact design parameters for either project, a great deal of uncertainty remains regarding the feasibility and cost of either proposal.  In addition, it is not clear whether the various environmental regulatory agencies will allow either type of project to be constructed in such environmentally sensitive areas given the magnitude of the environmental impacts that will result from construction.  In short, there are no attractive options for re-opening either Alum Rock Avenue or Crothers Road for long-term public use. 

 

If the decision is made to move forward regarding re-opening either Alum Rock Avenue or Crothers Road, the next step in the process would be to retain appropriate geological/ geotechnical and environmental consultants to perform extensive studies of the landslide and determine whether the necessary permits could be obtained.  Staff estimates the combined costs of such studies to be approximately $750,000.  If the Council decides to proceed with the studies, then staff would continue their efforts to secure state and federal funds to underwrite the costs.  Staff can return in 90 days with a status reports on our efforts to secure such funding.  In light of the significant costs, difficulties and uncertainties inherent in attempting to re-open either Alum Rock Avenue or Crothers Road, staff recommends that any further study be done only if state or federal funding is obtained.

 

COORDINATION

 

Staff from the Departments of Public Works, Transportation, Fire, Police, and Parks, Recreation and Neighborhood Services continues to work together to ensure that the Council’s direction is met.  Staff has also coordinated their efforts with the County of Santa Clara and the State of California.

 

 

MARK LINDER

Director of Parks, Recreation

  and Neighborhood Services