Subject: STREET LIGHTS CRACKDOWN 99 PROJECT

 

COUNCIL DISTRICT:  Citywide

 

 

RECOMMENDATION

 

Approval of Contract Change Order (CCO) No. 6 with Pacific Electric Company for the Street Lights Crackdown 99 Project in the amount of $13,478, for a total contract amount of $226,626.37.  CEQA:  Exempt.

 

BACKGROUND

 

On June 22, 1999, the City Council approved an award of a construction contract for the Street Lights Crackdown 99 Project to Pacific Electric Company, in the amount of $191,165. The scope of work for this project includes the installation of electroliers, conduits, conductors, aerial power cables, pull boxes, underground services, relocation of electroliers, and installation of street light luminaires.

 

Five contract change orders in a total amount of $21,983.37 for the installation of conduit, special street light foundations, salvage of electroliers, rewiring existing electroliers, and removal of tree stumps and roots have previously been approved by the Director of Public Works or the City Council.  Approval of this contract change order by the City Council is being requested since the amount of the contract change order exceeds the authority of the Director of Public Works by exceeding the remaining contingency for this project.

 

ANALYSIS

 

Since the time this contract was originally awarded in mid-1999, it has become increasingly difficult and more expensive to get service from Pacific Gas and Electric Company (PG&E).  This has caused significant delays in delivering projects that require PG&E cooperation.  The need to acquire new service points from PG&E for this project can be reduced by modifying and reusing existing electrical connections.  The connections proposed for modification provide service to existing street lights and can be altered to provide power to new street lights, thereby avoiding new electrical connections and minimizing PG&E connection fees and delays.   The proposed contract change order would compensate the contractor for the additional work to modify existing electrical service connections.  In addition, this proposed contract change order also provides for rewiring and conduit modifications on Bellhurst Avenue and on East San Salvador Street in order to reuse the existing underground conduit system and avoid costly construction of a new underground conduit system.

 

PUBLIC OUTREACH

 

This project was listed on the City's Internet Bid Line and advertised in the San José Mercury News and San José Post Record.  Bid packages for all public works construction projects are routinely provided to a standard list of various contractor organizations, builder's exchanges and disadvantaged business organizations, including United Minority Business Enterprises and the San José Minority Business Development Center.

 

COORDINATION

 

This project was coordinated with citizens and neighborhood associations, Pacific Gas and Electric Company, and the Offices of the City Attorney, Risk Manager, and Equality Assurance.

 

COST IMPLICATIONS

 

1.         COST OF RECOMMENDATION:  $13,478

 

2.         COST OF PROJECT:

 

Project Development                                                                        $   3,000.00

Construction                                                                                      191,165.00

Design & Construction Management                                                    57,500.00

CCOs#1,2,3,4 & 5                                                                             21,983.37

CCO#6                                                                                               13,478.00

Remaining Contingency                                                                          2,816.63

                                               TOTAL                                            $289,943.00

 

3.              SOURCE OF FUNDING:       441 - CDBG Fund

465 – Construction Excise Tax Fund

 

4.         STARTING DATE OF CONSTRUCTION: September, 1999

 

5.         ESTIMATED COMPLETION DATE OF CONSTRUCTION: June, 2001

 

BUDGET REFERENCE

 

Fund:                                   441

Appn:                                  5395

R.C.:                                    104973

Amount:                               $120,005

Budget Document:                2000-2001 Appropriation Ordinance #26141, Section 13.01, as amended on 10/17/00, Item g.8

 

Fund:                                   465

Appn:                                  5356

R.C.:                                    104983

Amount:                               $1,260,000

Budget Document:                2000-2001 Appropriation Ordinance #26141, Section 2.4, Item z05

 

NONDISCRIMINATION

 

The City of San José Nondiscrimination Requirements are included in this project as required by of Chapter 4.08 of the San José Municipal Code.

 

CEQA

 

Exempt.

 

 

RAJEEV BATRA

Acting Director, Public Works Department