Subject:            POLICE COMMUNICATIONS BUILDING RE-ROOF SUPPLEMENTAL MEMO

 

COUNCIL DISTRICT:  3 

 

 

REASON FOR SUPPLEMENTAL MEMO

 

This memorandum provides additional information following the bid opening on June 14, 2001.

 

RECOMMENDATION

 

Report on bids and award of contract for the Communications Building Re-Roof Project to the low bidder, Best Roofing and Waterproofing, Inc., in the amount of $424,838, and approval of a contingency in the amount of $45,000. CEQA: Exempt.

BACKGROUND

 

The Police Communications Building was constructed in 1988.  The roof system which incorporates a running track available to all police and communications personnel has a projected life span of 15 years, subject to actual use.  Because the actual use of the roof system has been heavier than the level of use that was projected when the Communications Building was constructed, the roof has been leaking for several years and has required multiple repairs.  One component of the existing roofing system, a waterproofing membrane applied directly to the concrete roof-deck has multiple blisters and tears that have resulted from heavy use of the rooftop facilities.  Based upon these factors, the City’s consultant has evaluated the roof and has recommended its replacement.

 

The scope of the project includes removal of existing and installation of a new roofing system.  Plans and Specifications were prepared by the City’s consultant, Skyline Engineering. 

 

A memorandum dated June 4, 2001 was forwarded to the City Council for the June 26, 2001 Council meeting.  The purpose of this supplemental memorandum is to provide additional information obtained after the bid opening.

 

ANALYSIS

 

Bids were received on June 14, 2001 with the following results:

 

 

Contractor

 

Bid Amount

Variance

Amount

Over/(Under)

Percent

 

 

 

 

Alpha Restoration and Waterproofing

  (So. San Francisco)

$599,985

$269,085

82

Best Roofing and Waterproofing

  (Hayward)

$424,838

$  94,838

29

Engineer’s Estimate

$330,000

---

---

 

The low bid submitted by Best Roofing and Waterproofing, Inc. is 29 percent higher than the Engineer’s Estimate.  Staff contacted both bidders to discuss the bid results.  Based on these discussions, staff attributes the higher than expected bids to a limited staging area, confined access, and night work specified for noisy operation, as requested by the Police Department.  In light of these aspects of the project, staff considers this to be a reasonable price for the construction of this project.

 

PUBLIC OUTREACH

 

This project was listed on the City’s Internet Bid Line and advertised in the San José Mercury News and San José Post Record.  Bid packages for all public works construction projects are routinely provided to a standard list of various contractor organizations, builder’s exchanges and disadvantaged business organizations, including United Minority Business Enterprises and the San José Minority Business Development Center.

 

COORDINATION

 

This proposed project has been coordinated with the Departments of Police and General Services and the Offices of the City Attorney, Risk Manager and Equality Assurance.

 

COST IMPLICATIONS

 

1.         COST OF RECOMMENDATION: $424,838

 

2.                  COST OF PROJECT:

Construction                                                                                     $424,838

Consultant Agreement                                                                                                        25,000

Design and Construction Management                                                                   105,000

Contingency                   45,000

                        TOTAL                                  $599,838

 

3.                  SOURCE OF FUNDING:  001Capital Improvements  

 

4.                  ESTIMATED START DATE OF CONSTRUCTION: August, 2001

 

5.                  ESTIMATED COMPLETION DATE OF CONSTRUCTION: November, 2001

 

BUDGET REFERENCE

 

Fund:

001

APPN:

6868

RC:

115423

Amount:

$600,000

Budget Document:

2000-2001 Appropriation Ordinance, Section 2.26, item 7(z30)

 

NONDISCRIMINATION

 

The City of San José Nondiscrimination Requirements are included in this project as required by Chapter 4.08 of the San José Municipal Code.

 

CEQA

 

Exempt.

 

 

RAJEEV BATRA

Acting Director, Public Works Department