Subject: FOURTH MAJOR INTERCEPTOR PHASE V/VA PROJECT
COUNCIL DISTRICT: 4
Report on bids and award of contract for the Fourth Major Interceptor Phase V/VA Project to the low bidder, Mountain Cascade, Inc., in the amount of $21,687,958, and approval of a contingency in the amount of $ 2,169,000. CEQA: Resolution No. 60197.
The City’s sanitary sewer interceptor system on Zanker Road receives flow from the City of San José, West Valley Sanitary District, the City of Santa Clara, and County Sanitation District No. 2-3. The interceptor system extends from the Water Pollution Control Plant (WPCP) south along Zanker Road to Highway 101. South of Highway 101, the interceptor system splits into two separate systems. The easterly portion of the system extends along 5th and 7th Streets and terminates at 7th and Empire Streets. The westerly portion of the system extends along 4th Street and terminates at 4th and Burton Streets.
A design study of the City’s sanitary sewer interceptor system was completed by James M. Montgomery, Consulting Engineers, in 1986 in response to odor complaints and hydrogen sulfide corrosion in the interceptor system and junction structures. The study provided recommendations for the rehabilitation or replacement of three existing interceptors and the construction of a Fourth Major Interceptor parallel to the existing pipelines in Zanker Road from the WPCP to 7th and Empire Streets. The Fourth Major Interceptor is intended to accommodate additional flows from the ultimate build out of the urban service areas which discharge to the interceptors. It also will provide a means of flow diversion when one of the other interceptors is taken out of service for maintenance or rehabilitation. The Fourth Major Interceptor Project has been planned to be constructed in seven phases. The first four phases have been completed on Zanker Road from the water pollution control plant to Trimble Road.
In
June 1999, Council approved an agreement with Brown and Caldwell, an engineering
consultant, for the design and construction monitoring of the Fourth Major
Interceptor Phase V/VA project. The
Phase V/VA project of this multi-phased project is located along Zanker Road
between Trimble Road and Highway 101.
The project proposes to (1) remove and replace the 60-inch brick sewer
with a 66-inch diameter sewer, (2) construct a new 66-inch diameter Fourth
Major Interceptor, and (3) replace two sanitary sewer junction structures due
to the severe corrosion.
The
Phase V/VA Project will be completed in ten stages. The traffic control plans require the contractor to set-up two
way traffic (one lane each direction) in the southbound lanes of Zanker Road to
accommodate traffic around each stage of construction. The plans require removing and/or modifying
the median islands to construct detours for traffic control and to provide
access to adjacent driveways. Staff
coordinated the restoration of the median islands with the Redevelopment
Agency.
In
order to minimize the impacts to traffic, construction activities within the
intersections of Zanker Road and Trimble Road, Charcot Avenue, and Brokaw Road
will be completed during weekdays from 8:00 p.m. to 5:00 a.m. and during
weekends from 8:00 p.m. Fridays to 5:00 a.m. Mondays. Working hours for the general construction for the interceptors,
storm drains, and structures have been established as weekdays from 7:00 a.m.
to 4:30 p.m., with no material deliveries to the site until after 8:30 am. This will maximize productivity and minimize
cost on this project. General
construction activities will be isolated from the traffic flow; therefore, will
not further impact traffic during the peak commute periods.
Bids for this project were received on May 17, 2001. The bid results are as follows:
|
|
|
Variance |
Over/(Under) |
|
Contractor |
Bid Amount |
Amount |
Percent |
|
|
|
|
|
|
Ranger Pipeline (San
Francisco, CA) |
$30,765,239 |
$11,947,427 |
63% |
|
Colich Construction (Torrance, CA) |
24,856,450 |
6,038,638 |
35% |
|
Brundidge Construction (Clackmas, OR) |
23,675,505 |
4,857,693 |
26% |
Mountain Cascade
(Livermore, CA)
|
21,687,958
|
2,870,146
|
15%
|
|
Engineer’s Estimate |
18,817,812 |
|
|
The low bid submitted by Mountain
Cascade, Inc is 15% above the Engineer’s Estimate. The difference was reflected in the item for the 66-inch diameter
sanitary sewer. The Contractor’s price
for the item is approximately $3.3 million higher than the estimated cost. The higher price is attributed to higher
costs to 1) purchase aggregate materials for trench backfill and concrete
materials for the new sewer pipe, 2) transport import and excavated trench
materials to and from the site, and 3) dispose excavated materials. Rising fuel prices have been a significant
factor for the higher cost to transport materials and for the higher costs to
manufacture backfill and concrete materials.
Based on staff’s evaluation of the bid proposals, Mountain Cascade’s bid
is a reasonable price for the proposed project.
Due to the complex nature of this project, the possibility of utility conflicts, the potential for encountering hazardous materials and changes to the traffic control plans, a $2,169,000 contingency is requested for unforeseen conditions that may arise during construction.
This proposed project was listed on the City’s Internet Bid Line and advertised in the San José Mercury News and San José Post Record. Bid packages for all public works construction projects are routinely provided to a standard list of various business organizations, including Unity Minority Business Enterprises and the San José Minority Business Development Center. An information packet will be distributed to the impacted businesses within the project area prior to construction.
This project is being coordinated with the Departments of Planning, Building and Code Enforcement and Transportation, and the Offices of the City Attorney, Risk Manager, and Equality Assurance.
1. COST OF RECOMMENDATION: $21,687,958
2. COST OF PROJECT:
|
|
Prior Fiscal Year |
|
Current Fiscal Year |
|
FY 2001-02 |
|
|
|
|
|
|
|
|
Project Development |
$ 107,000 |
|
|
|
|
|
Construction |
|
|
$ 21,687,958 |
|
|
|
Design & Construction Management |
22,000 |
|
141,000 |
|
$ 870,000 |
|
Consultant Services |
1,300,000 |
|
|
|
|
|
Contingency |
|
|
|
|
2,169,000 |
|
|
|
|
|
|
|
|
TOTAL |
$1,429,000 |
|
$21,828,958 |
|
$3,039,000 |
3. SOURCE OF FUNDING: 540 – Sanitary Sewer Connection Fee Fund
545 – Sewer Service & Use Charge Capital Improvement Fund
4. ESTIMATED START DATE OF CONSTRUCTION: September, 2001
5. ESTIMATED COMPLETION DATE OF CONSTRUCTION: May, 2003
Fund: 540 545
Appn: 4267 4267
R.C.: 064383 064383
Amount: $14,400,000* $3,821,000
Budget Document: 2000 – 2001 Adopted CIP 2000 – 2001 Adopted CIP
Item No. 8, Page 573 Item No. 8, Page 573
*An appropriation adjustment in the amount of $3,625,000 has been recommended to City Council as part of the June 19th Appropriation Ordinance amending the Capital Improvement Program.
The
City of San José Nondiscrimination Requirements are included in this project as
required by Chapter 4.08 of the San José Municipal Code.
Resolution No. 60197.
RAJEEV BATRA
Acting Director, Public Works Department