SUBJECT: APPROVAL OF CHANGE ORDER NO. 4 AND INCREASE CONTRACT CONTINGENCY FOR THE SAN JOSE/SANTA CLARA WATER POLLUTION CONTROL PLANT FY 97/98 CAPITAL IMPROVEMENT PROGRAM, RAILCAR PLATFORMS AND COVER PROJECT
RECOMMENDATION
Approval of:
1.
Change Order No. 4
with Rushford Construction, Incorporated for the construction project entitled
“San Jose/Santa Clara Water Pollution Control Plant, FY 1997/1998 Capital
Improvement Program, Railcar Platforms and Cover Project,” in an amount of
$68,526;
2.
Increasing the project
contingency by $92,000 and thereby increasing the total contract amount from
$242,089 to $334,089; and
3.
Extending the term
of the agreement to December 15, 2001.
BACKGROUND
This project provides for the construction of a canopy above the treatment plant’s railcars of chlorine and sulfur dioxide gases. On April 20, 1999, Council awarded a construction contract in the total amount of $242,089 for the subject project to Rushford Construction, which included a contingency of $40,000. The project allowed for 150 calendar days for completion and the contract start date was June 18, 1999, with a completion date of November 14, 1999.
The project bid called for the contractor to retain a structural engineer to design the footing for the canopy. After the contractor’s shop drawings for the canopy were submitted and approved by the design engineers, the contractor proceeded to order the canopy materials and delivered the materials on site. Upon the start of physical construction work in September 1999, the contractor encountered changes in site conditions that required redesign of the canopy. Specifically, electrical duct banks found at the site interfered with the construction of the canopy piers.
Change Order No. 4 would provide for the following activities:
1. Construct four 24-inch diameter concrete drilled piers at 30-foot depth and four 36-inch diameter concrete drilled piers at 35-foot depth. This includes the construction of two additional piers. The cost for this work is $63,978.
2. Raise and consolidate two south platform support foundations. The contractor is required to perform manual excavation of this area since it is in close proximity to the chemical railcars. The cost for this work is $4,548.
The contractor is working diligently with staff to complete this project before the wet weather period begins, which poses more hazardous conditions for the work around this hazardous chemical area. Staff requests extension of the original completion date to December 15, 2001. Staff further requests that, in order to avoid delaying the project further at this critical time period, the contingency amount be increased by $92,000 to a total of $132,000. This would result in a remaining available project contingency of $35,462, which would enable staff to make timely decisions on any additional work that may arise, considered critical given that the project is only 64 percent complete.
PUBLIC OUTREACH
Not applicable.
COORDINATION
The project has been coordinated with the Offices of the City Attorney, Equality Assurance, and Risk Management, and was scheduled to be heard at the September 13, 2001, Treatment Plant Advisory Committee meeting.
The cost of this recommendation is $92,000. Funds are available with the existing appropriation in the Treatment Plant Capital Fund.
|
CONTRACT AMOUNTS |
|
|
Original
Contract Original
Project Contingency Original Total Contract Proposed
Additional Project Contingency Proposed Total Contract |
$
202,089 $ 40,000 $ 242,089 $ 92,000 $ 334,089 |
|
USE OF PROJECT
CONTINGENCY |
|
|
Original
Project Contingency Proposed
Additional Project Contingency Proposed Total Project
Contingency Uses CO
#1 (Approved & Paid) CO
#2 (Approved & Paid) CO
#3 (Approved & Paid) CO
#4 (Recommended) Total Project Contingency Uses Remaining Available Project
Contingency |
$ 40,000 $ 92,000 $ 132,000 $ 5,239 13,510 9,263 68,526 $ 96,538 $ 35,462 |
BUDGET REFERENCE
Amount: $92,000
Page
725
The City of San Jose Nondiscrimination Requirements are included in this project as required in Chapter 4.08 of the San Jose Municipal Code.
CEQA
CEQA: Exempt
CARL W. MOSHER
Director, Environmental Services Department