Subject:
STATUS REPORT – ALUM ROCK PARK
IMPROVEMENTS
COUNCIL DISTRICT: Citywide
SNI AREA: N/A
The purpose of this memo is to provide a status report on the improvements to Alum Rock Park related to the closure of Alum Rock Avenue and the opening of Penitencia Creek Road within Alum Rock Park.
Direct staff to develop a Capital Improvement Program (CIP) project to restore the banks of the Penitencia Creek channel and landscape and refer it to the FY 2002-2003 CIP process.
On May 1, 2001, the City Council approved the memo entitled Alum Rock Park Access and Crothers Road. This memo approved the recommendations from the staff report entitled Alum Rock Park Status Report, dated April 27, 2001. The following are the recommendations of that report, with a brief summary of staff’s actions:
a) Approve the proposed capital improvements to the Penitencia Creek Park Entrance and Trail within Alum Rock Park as part of the 2002-2006 Capital Improvement Program for Parks & Community Facilities.
b) Continue to work with the affected neighborhood to calm traffic on Penitencia Creek Road.
c) Continue to prohibit public vehicular traffic on Alum Rock Avenue between Crothers Road and Penitencia Creek Road. Authorize the use of the road for service vehicles, emergency vehicles, pedestrian and equestrian and bicycle traffic only.
d) Continue to prohibit public vehicular traffic on Crothers Road between Alum Rock Avenue and Miradero Road.
· Completed
Furthermore, the memo entitled Alum Rock Park Access and Crothers Road directed staff to:
1. Implement traffic and parking control and pedestrian safety measures on Penitencia Creek Road and Alum Rock Avenue. These should be implemented as soon as possible, and the Administration is directed to work with county and state agencies as necessary to move ahead quickly.
2. Implement measures to ensure pedestrians use the Creek Trail and stay off of Penitencia Creek Road. These measures should at least include improved signage at the entrance of Alum Rock Park, at Quail Hollow/Eagle Rock Parking Lot, at the intersection of Alum Rock Avenue and Penitencia Creek Road, and at both entrances of the Rusticlands Picnic Area. Other appropriate measures should be considered as necessary to achieve this goal.
3. Work with the community to develop and implement a plan to decrease the impact of fire along Crothers Road.
4. Work with the County of Santa Clara to determine feasibility, cost, and value of repairing Crothers Road for only emergency access, and report back to Council within the next 120 days.
5. Research and identify all possible sources of funding to fully reopen Alum Rock Avenue and Crothers Road for long-term and safe public use and report back to Council within the next 120 days. This effort should be coordinated with County staff as appropriate. A recommendation to Council regarding further feasibility studies should be brought forward with information regarding likely outside funding sources within the next 120 days.
ANALYSIS
Research
and Identify All Possible Sources of Funding to Fully Reopen Alum Rock Avenue
and Crothers Road for Long-Term and Safe Public Use, And Recommend Further
Feasibility Studies
Norfleet Consultants was
hired to provide geologic technical data for this report. Norfleet Consultants stated that although
the hillside may be partially stabilized, the cost to do so would be fiscally
and environmentally excessive. The
active landslide complex is approximately 375 feet wide and some parts of the
slide may be as much as 75 feet deep.
The slide has been active on an intermittent basis for thousands of
years and, absent a massive stabilization effort, will continue to move in very
wet years in the future. The slide
reactivated in 1998 as a result of the combination of extremely heavy rainfall
during a six-week period in January and February and ongoing erosion of the toe
of the slide by Penitencia Creek. The
slide also moved to a lesser degree in 1983 and 1987 when rainfall patterns and
amounts were similar, but the rain was spread out over a wider time
period. Absent a massive stabilization project that would cause
significant environmental damage to the park and Penitencia Creek--and for
which regulatory permits may be impossible to obtain--the slide will continue
to move intermittently for the foreseeable future.
As previously discussed
with the Council, long term solution(s) to fully reopen Alum Rock Avenue and
Crothers Road include the following options:
1. Constructing
an A-Frame concrete pier structure with Tie-Backs into the hillside under Alum
Rock Avenue. As currently envisioned,
the piers would extend down to 110 feet.
A concrete beam would tie the piers together at the top and serve as the
base for Alum Rock Avenue. The
estimates indicate this repair would cost over $6 million--possibly much
more--and would require over three years to construct. Since parts of the roadway would still
continue to move incrementally after completion of the project, ongoing
maintenance would be required. There
is no guarantee this alternative would result in a viable long term solution
for Alum Rock Avenue.
2. Constructing a bridge across the slide area on Crothers Road to reconnect the stable portions of Crothers Road. This proposal requires a structure 600 feet long and 30 feet wide. The foundation involves deep piers with grade beams and tie-backs similar to the proposal for the Alum Rock Park Entrance Road. The bridge proposal is estimated at $12 million dollars exclusive of any land acquisition that may be required. This proposal differs from the A- Frame structure in that it is truly a bridge spanning the slide area in three or more sections. The hillside would continue to move under the bridge structure, therefore this repair method does not stabilize the hillside.
Due to the complexity
and scale of the geotechnical investigation necessary to determine exact design
parameters for either project, a great deal of uncertainty remains regarding
the feasibility and cost of either proposal.
In addition, it is not clear whether the various environmental
regulatory agencies will allow either type of project to be constructed in such
environmentally sensitive areas given the magnitude of the environmental
impacts that will result from construction.
There are no inexpensive options for re-opening either Alum Rock Avenue
or Crothers Road for long-term public use.
If the decision is made
to move forward regarding re-opening either Alum Rock Avenue or Crothers Road,
the next step in the process would be to retain appropriate geological/
geotechnical and environmental consultants to perform extensive studies of the
landslide and determine whether the necessary permits could be obtained. Staff estimates the combined costs of such
studies to be approximately $750,000.
PRNS has explored possible
sources of funding to fully reopen Alum Rock Avenue and Crothers Road for
long-term and safe public use without attempting to stabilize the entire
landslide. John Montgomery, the City’s
lobbyist in Washington D.C., has researched possible funding sources with
members in Congress. The City’s
lobbyist in Sacramento also researched possible state funding to support this
need. Both lobbyists have stated that no funds are available to support the
stabilization of the hillside, or the repair of the roadways.
Given the geologic
complexity to stabilize the hillside, Norfleet Consultants states that this
slide will continue to move indefinitely.
In light of the difficulties, uncertainties, and significant costs
inherent in attempting to re-open either Alum Rock Avenue or Crothers Road,
staff does not recommend any further study be done for these areas
Toe
Buttress Repair
Staff consulted with
Norfleet Consultants to provide preliminary cost estimates for toe support of
the Crothers Road landslide at the Penitencia Creek. The cost to remove the toe of the landslide along the Penitencia
Creek and construct a reinforced earthen buttress to provide support for the
toe of the landslide is in the range of $900,000 to $1,300,000.
This cost estimate only
includes grading, geotextile reinforcement, subsurface drainage, rip-rap,
mobilization, engineering and construction management. It is a minimum size estimate only. Design level investigations may require the
buttress to be significantly larger both in size and cost.
The estimate does not
include the cost of obtaining permits, cost of rerouting or covering Penitencia
Creek, replacement of trees/vegetation, cost of pre/post construction
biological/vegetation/archeological/creek surveys, city/park expenses, and the
repair or replacement of adjacent park facilities. These items could significantly increase the time and cost of the
repairs. The project could take as long
as five years to complete at a cost exceeding
$3,000,000.
A toe buttress may
stabilize the lower part of the landslide complex, but will not prevent
movement of the upper part of the landslide.
The landslide complex is quite long, and consists of several linked
blocks. Over time, the upper blocks
will continue to deform (slide downhill) until they snag up against the toe
buttress. Movement of the upper blocks
could be in the range of several feet both horizontally and vertically, and it
could take 5 to 20 years for this to occur.
This type of repair will
not, and is not intended to prevent all movement of the landslide complex. After the complex has stabilized, it may
deform under very wet conditions, but it should not experience large-scale
movement in the range of 5 to 10 feet.
Due to the complexity of
the upper part of the landslide complex, staff does not recommend a repair or
stabilization method for the remainder of the landslide. The landslide complex, with its multiple
linked blocks, will continue to move indefinitely. The environmental and financial costs of any repair method for
this area would be excessive.
Norfleet Consultants
suggested an alternate method to potentially minimize the effects of the Penitencia
Creek on the toe of the Crothers Road landslide. Norfleet suggested restoring the banks of the Penitencia Creek in
the area of the toe to a bioengineered natural setting. This plan would include
creating a flood plain area across from the toe. This type of restoration will not, and is not intended to,
prevent all movement of the landslide complex.
Norfleet Consultants were not able to provide a
cost estimate for this type of a project.
PW and PRNS are currently designing other restoration repairs to the
banks of the Penitencia Creek within Alum Rock Park. The repair method that Norfleet Consultants suggests is similar
to the projects being developed for the Alum Rock Park 1998 Storm Damage Repair
Project. PW and PRNS have developed the
Alum Rock Park Riparian Management Plan Draft as part of the Alum Rock Park
1998 Storm Damage Repair Project. This
riparian management plan would provide the basis for the repair method
suggested by Norfleet consultants.
Based on the area of the proposed flood plain, the linear distance of
the creek area to be restored, obtaining permits, cost of rerouting Penitencia
Creek, replacement of trees/vegetation, cost of pre/post construction
biological/vegetation/archeological/creek surveys, city/park expenses, and the
repair or replacement of adjacent park facilities, the project is estimated to
cost between $500,000 and $1,000,000.
The
recommended source of funds for this proposed project is the City-Wide
Construction and Conveyance Tax Fund.
If this solution is recommended, the project can be referred to the
Capital Budget process for FY 2002-03. The
project would include appropriate geological/geotechnical and environmental
consultants to perform extensive studies of the creek area and determine
whether the necessary permits could be obtained. The start of this project will
be contingent upon obtaining all required permits and associated environmental
reviews.
Restoring the toe/creek
bank will preserve the ecological resources of the riparian habitat along the Penitencia
Creek in Alum Rock Park and in time it may decrease the rate of hillside
movement. If the rate of movement is
slowed, this may make it feasible to reconsider repairing and reopening Alum
Rock Avenue and Crothers Road to some vehicular traffic. The bioengineered
repair method is consistent with the Alum Rock Park Riparian Management Plan
Draft. The Alum Rock Park Riparian
Management Plan Draft provides a comprehensive set of goals, policies, and
management actions that integrate watershed resources and reflects the unique
quality of the park’s riparian and aquatic resources. The Penitencia Creek in Alum Rock Park provides habitat for a
number of species that are listed as a species of concern by the State of
California, and/or as a candidate for listing as endangered, is listed as
threatened, or is a species of special concern by the Federal government. Restoring the toe/creek bank will improve
the habitat of the area, thus the survivability of these species. This will in turn improve the ecosystem of
Alum Rock Park.
Restoring the toe/creek
bank will also benefit the park and
downstream communities by improving the creeks capacity to absorb high creek
flows during heavy winter rains. The potential effect will be felt by the
downstream neighborhoods by a reduction of flood occurrences.
PRNS has meet with the PW to initiate the
improvements to the Penitencia Creek Trail and the Penitencia Creek parking
lot. These projects are included in the
2001-2006 CIP for Parks & Community Facilities.
PW staff stated that the
preliminary schedule for the improvements to the Penitencia Creek Parking Lot
and Creek Trail will be as follows:
Bid process – April 2002
Construction contract awarded – May 2002
Project completed – October 2002
Work
With the Affected Neighborhood to Calm Traffic on Penitencia Creek Road
In
addition to meeting with the public at the community meetings hosted by Council
members Reed and Campos, DOT has met with affected residents regarding the
location of the road bump on the County portion of Penitencia Creek Road. DOT
specifically met once with a resident regarding the road bumps, and once
regarding stop signs on Penitencia Creek Road. DOT considered the resident’s
comments when approving the proposed installation location. DOT has also responded to a number of phone
calls regarding the status of the traffic calming measures and based upon
additional resident input has increased the use of NASCOP to include weekend
and mid-day deployments. Higher NASCOP
enforcement levels will occur during the warmer months. It will be scheduled regularly, but on a
random basis to ensure effectiveness.
Implement
Traffic and Parking Control and Pedestrian Safety Measures on Penitencia Creek
Road and Alum Rock Avenue
PRNS staff has met with
representatives from the California Highway Patrol (CHP), Santa Clara County
Sheriff’s Office (SCCSO), Santa Clara County Department of Roads and Airports
(SCCDRA) and various City departments to ensure their commitment to public
safety and to deal with traffic and parking issues on Penitencia Creek Road and
Alum Rock Ave. The CHP and SCCSO have
stated they will respond to requests for service from park staff to enforce
parking and traffic laws in the unincorporated areas adjacent to Alum Rock
Park.
The CHP does not track
calls for service in a way that is meaningful for this report. Therefore, the
CHP could not provide any data on their traffic and parking enforcement. The CHP did state they have responded to
calls for service in the neighborhoods adjacent to Alum Rock Avenue and
Penitencia Creek Road. Park staff has
noticed an increase in CHP presence in and around the roadways surrounding Alum
Rock Park.
The SCCSO does track
calls for service for the Alum Rock Park area, and was able to provide staff
with data for this report. The SCCSO
stated that they responded to approximately 15 calls for service between
January 1, 2001 and September 20, 2001.
Sheriff’s Deputies handled approximately15 other self initiated events
during this period. Sheriff’s Deputies
also logged daily patrol checks in the Alum Rock Park area. Both calls for service and self initiated
calls were characterized as vehicles or people who were not known to the
residents, noise and litter complaints, and family or juvenile disturbances. Of all the calls, approximately 13 occurred
during daylight hours, approximately 5 resulted in parking citations, and an
additional 5 resulted in the vehicles being towed and cited.
Park staff has met with
representatives from the SCCDRA to work on parking control signage on the
unincorporated roadways. Traffic
engineers from the SCCDRA stated that they would be installing a total 18 no
parking signs on Alum Rock Avenue, Cannon Vista Drive, Crothers Road, Chula
Vista Drive, Canyon Drive, and the frontage road that runs along Alum Rock
Avenue from Crothers Road to Brundage Drive.
They will also be installing a red painted asphalt curb on the frontage
road that runs along Alum Rock Avenue from Crothers Road to Brundage
Drive. The SCCDRA expects to have the
signs and berm installed by October 12.
This additional parking
control signage eliminates the confusion of where the motoring public can park
in this area. It also removes hazardous
parking that until now blocked access for emergency vehicles. Additionally, the posted no parking areas
will assist the CHP and SCCSO with parking enforcement on the unincorporated
roadways around Alum Rock Park. The intended purpose of this parking control
signage is to reduce the impact of parking related to Alum Rock Park on the
surrounding neighborhood.
PRNS has provided extra
staff and signage at the Alum Rock Avenue entrance to Alum Rock Park on
weekends and holidays to redirect visitors to the new entrance. Park staff estimates that over 1,000 flyers
have been distributed at this location.
Approximately 100 vehicles per weekend day in June have been redirected
to the new entrance. In July and
August, the number of vehicles coming to the closed Alum Rock Avenue entrance
dropped to approximately 50 vehicles per weekend day. Staff is noticing that one third of the vehicles driving to the
closed Alum Rock Avenue entrance are returning visitors who have already been
advised of the road closure. Park
informational flyers to encourage compliance with posted speed limits and to encourage
usage of the Creek Trail are also available.
Increased police patrols
have occurred both inside Alum Rock Park and along Penitencia Creek Road
leading to the park at the request of the residents living near the park. The
Patrol Division, Horse Mounted Unit, and the Traffic Enforcement Unit have
increased their presence in the area. Each patrol in an area is not documented
since the officers go into an area for more police presence but do not put
themselves out of service so they are available for emergency responses. Therefore, the time they spend in the area
to deter violations is not captured in the computer system. Initially citations
and warnings totaled 80 during the last two weeks of May, and the first two
weeks of June. These numbers took a dramatic drop during the next four weeks to
36. During these last four weeks the citations totaled 48. Complaints from the
residents related to the late night drinking in the area leading to the park
have decreased to zero.
DOT has installed road
bumps and centerlines with raised reflectorized markers within Alum Rock
Park. Additionally, DOT is working with
the County to install road bumps on the unincorporated portion of Penitencia
Creek Road just outside of Alum Rock Park, as that portion of the road is under
County jurisdiction. At DOT’s request,
the County is fast-tracking the encroachment permit process to allow the
installation of the road bumps. DOT
expects to complete the permit approval process with the County in the next two
weeks and proceed with the installation of the road bump.
DOT has also implemented
NASCOP enforcement along Penitencia Creek Road, and the NASCOP data indicates
that the percentage of drivers exceeding the speed limit by 10 miles per hour
or more ranges between four and eight percent, which is between low and average
for this type of roadway.
August weekday 24-hour
traffic count data shows average and 85th percentile speeds have
remained the same on Penitencia Creek Road since before it was opened to the
park. However, there has been a
three-mile per hour increase in the 85th percentile speed east of
Toyon Avenue. Most weekday speeding
occurs during mid-day and before the morning rush hour.
NASCOP will be used
regularly during the middays in a manner similar to that mentioned above. In an effort to assist motorists in
identifying the new entrance route, DOT has installed additional enlarged signs
that provide direction to Alum Rock Park from Alum Rock Avenue, White Road and
McKee Road.
DOT will provide
information gathered by the deployment of NASCOP to the Police Department. This information will assist the Police
Department in identifying times and locations so that they can better manage
their resources.
DOT staff also
researched Councilmember Reed’s request to paint speed limits on the pavement
of Penitencia Creek Road. Past
experience in San Jose has shown that such markings work for short periods of
time before portions of the marking are worn away by tire wear. Additionally, the reflective coatings flake
off. Both of these failures of the
street markings render them ineffective.
However, a longer lasting and more effective solution would be the
installation of additional, over-sized speed limit signs. The additional signs will be installed by
the end of October.
DOT installed new gates
across Crothers Road to replace the removable bollards and is installing
parking prohibition signs on the City right-of-way adjacent to the Alum Rock
Avenue closure fence. These new signs
will be installed by the end of October.
These measures are in response to public concerns over parking
intrusions by park users who choose not to use Penitencia Creek Road.
Implement
Measures to Ensure Pedestrians Use the Creek Trail and Stay Off of Penitencia
Creek Road
PRNS staff has installed
trail signage inside of Alum Rock Park that directs trail users onto Penitencia
Creek Trail and off of Penitencia Creek Road.
The sign locations include the Penitencia Creek Road entrance, Quail
Hollow Bridge area, Rusticlands area, and Creek Trail egresses onto Penitencia
Creek Road and Alum Rock Avenue.
Additionally, park staff has laid telephone poles lengthwise from the
Penitencia Creek Road entrance gate to the Penitencia Creek stairs/trail
head. This was done to provide a
distinguishable path to the trailhead and encourage Creek Trail usage.
City staff is
researching the feasibility of developing Reach I of the Penitencia Creek
Trail. This particular section of trail
will connect to Alum Rock Park near the new Penitencia Creek entrance. Staff has identified possible properties for
acquisition. These acquisitions may be
funded through the Santa Clara County Open Space Authority.
Work
with the Community to Develop and Implement a Plan to Decrease the Impact of
Fire along Crothers Road
PRNS and the Fire
Department are working with the
community to address fire issues within and adjacent to Alum Rock Park. Park staff has completed the maintenance of
the park’s firebreaks along the North rim of the park. At the request of residents that live along
Crothers Road and Peacock Gap Road, park staff has contracted the removal of
eucalyptus trees and pine trees that were determined to pose a hazard. The remaining hazardous trees in this area
will be removed by October 12. Park
staff coordinated the control and removal of grasses and brush along the
Crothers Road park boundary. Park
Rangers continue to monitor the weather and fire conditions inside the park.
The Fire Department has
met on several occasions to discuss the Urban Wildland-Interface Pre-fire Plan
for the East Foothills area, including Alum Rock Park. Participating agencies have included PRNS,
OES, California Department of Forestry (CDF), San Jose Information Technologies
Department, San Jose Police Department, Santa Clara County Sheriff's
Department, and others. Fire Department
staff continues to make progress in compiling information and coordinating
meetings with participating agencies.
The Office of Emergency
Services and Councilmember Reed hosted two recent community meetings to provide
the public with information regarding fire preparedness. Those meetings were held on September 17 and
24, 2001. Staff from the Fire
Department, Police Department, San Jose Prepared, PRNS, CDF, and the Valley
Transportation Authority all discussed programs and actions they are doing to
minimize fire danger to the community, and actions the community can take to be
prepared for emergency situations.
In addition, the Fire
Department has:
q Met with DOT to discuss and evaluate road bumps
that were installed on Penitencia Creek Road inside of Alum Rock Park, as well
as the proposed road bumps to be placed along the road approaching the entrance
to Alum Rock Park.
q Met with the Country Club Heights homeowners
association to address their concerns regarding vegetation issues in the area
surrounding this residential development.
q Provided the Alum Rock Park Ranger staff with
Knox lock boxes to be placed on Crothers Road and the Penitencia Creek Road
entrance to Alum Rock Park for access to keys for entrance by emergency fire
apparatus. Park staff installed the
Knox lock boxes.
q Continued to remain informed of emergency access,
traffic flow, water supply and vegetation management issues related to Alum
Rock Park and the surrounding interface neighborhood. Also made dispatch
adjustments to respond to emergencies within Alum Rock Park.
q Distributes daily weather reports to all Fire
stations citywide to develop awareness for potential hazardous fire conditions.
California Department of Forestry (CDF) response status is also broadcast.
q Contributed to the community meetings held by the
Office of Emergency Services and Councilmember Reed.
Work
with the County of Santa Clara to Determine Feasibility, Cost, and Value of
Repairing Crothers Road for Only Emergency Access
At the beginning of August, PW and the County met and discussed the construction of a retaining structure for Highland Drive above Crothers Road. Constructed has commenced, the structure is comprised of three-foot diameter piers over ninety feet deep spaced every six feet. It has three rows of tie-backs and is over 120 feet long. Completion of this $1.5 million structure is scheduled for mid-December. The County is using Crothers Road for construction access.
Emergency access to Crothers Road was facilitated by the installation of the new gates by DOT. Upon completion of the Highland Drive retaining structure by the County, Crothers Road will be available for emergency access only. DOT has completed minimal grading and addition of base rock material so that lightweight emergency vehicles can have access on this stretch of Crothers Road. The slide continues to move and expand even during dry weather. It will be continuously monitored for excessive displacement and closed to emergency access should hazardous conditions develop.
Staff from the Departments of Public Works, Transportation, Fire, Police, and Parks, Recreation and Neighborhood Services continues to work together to ensure that the Council’s direction is met. Staff has also coordinated their efforts with the County of Santa Clara and the State of California.
MARK LINDER
Director of Parks, Recreation
and Neighborhood Services