Subject: THE ALAMEDA AT CLEAVES IMPROVEMENTS
COUNCIL DISTRICT: 6
SNI Area: NA
Report on bids and award of contract for The Alameda at Cleaves Improvements Project to the low bidder, Bellicitti & Pelliccitti Construction, in the amount of $251,600, and approval of a contingency in the amount of $25,000. CEQA: Exempt
BACKGROUND
The San José Redevelopment Agency (SJRA) has requested the Department of Public Works to demolish a house and construct a new parking lot at The Alameda at Cleaves Avenue. The scope of the project includes demolition, soil grading, and installation of new asphalt and concrete paving, electroliers, landscaping and irrigation.
Bids were received on August 9, 2001 with the following results:
|
Contractor |
Base
Bid Amount |
Variance
Amount |
Over/Under
Percent |
|
HRB Construction
(San José) |
$272,100 |
$82,100 |
43 |
|
Top Grade Construction
(Livermore) |
$261,261 |
$71,261 |
37 |
|
Wattis Construction
(San José) |
$256,655 |
$66,655 |
35 |
|
Bellicitti & Pellicciotti
(Santa Clara) |
$251,600 |
$61,600 |
32 |
|
Engineer's Estimate |
$190,000 |
--- |
--- |
The low bid submitted by Bellicitti & Pellicciotti is 32 percent Higher than the Engineer’s Estimate. Staff attributes these bids to the “small job” nature of this project, and considers this to be a reasonable price for the construction of this project.
A contingency in the amount of $25,000 is requested for any unforeseen conditions which may arise during construction of this project.
This proposed project was listed on the City’s Internet Bid Line and advertised in the San Jose Mercury News and San Jose Post Record. Bid packages for all Department of Public Works construction projects are routinely provided to a standard list of various contractor organizations, builder’s exchanges, and disadvantaged business organizations, including United Minority Business Enterprises and the San José Minority Business Development Center.
This proposed project has been coordinated with the Redevelopment Agency, Planning, Building and Code Enforcement Department, and the Offices of the City Attorney, Budget, Risk Manager, and Equality Assurance.
1. COST OF RECOMMENDATION: $251,600
|
|
Project Development |
$ 3,400 |
|
|
|
Construction |
251,600 |
|
|
|
Design and Construction Management |
80,000 |
|
|
|
Contingency |
25,000 |
|
|
|
TOTAL |
$360,000 |
|
2. SOURCE OF FUNDING: 450 – SJRA Capital Projects Fund
3. ESTIMATED START DATE OF CONSTRUCTION: November, 2001
5. ESTIMATED COMPLETION DATE OF CONSTRUCTION: March, 2002
|
Fund: |
450 |
|
APPN: |
6803 |
|
RC: |
115973 |
|
Amount: |
$331,000* |
|
Budget Document: |
2001-2002 Appropriation Ordinance,
Section 20.05, item 3w |
*$44,000 was transferred for this project in 2000-2001 FY with PSM#236. $316,000 has been transferred by SJRA with Second Amendment to PSM#236 and the appropriation amendment was adopted by City Council on September 25, 2001.
The City of San José Nondiscrimination Requirements are included in this project as required by Chapter 4.08 of San José Municipal Code.
CEQA
Exempt.
RAJEEV BATRA
Acting Director, Public Works Department