To:   HONORABLE MAYOR AND                   From:   Katy Allen

                        CITY COUNCIL                                                        James R. Helmer

 

   Subject:   OAKLAND ROAD WIDENING               Date:   10-06-03

                         PROJECT (PHASE 1)

 

 Council District:  4

 

RECOMMENDATION

 

Report on bids and take appropriate action based on the evaluation of bids for the Oakland Road Widening Project from Brokaw Road to Commercial Street, and approval of a ten percent contingency. 

CEQA:  ND, PP03-06-209 – Pending.

 

 

BACKGROUND

 

Oakland Road is an existing two to four-lane major arterial in North San José.  This roadway is scheduled for widening to six lanes from Montague Expressway south to Commercial Street in the Adopted 2003-2004 Traffic Capital Budget.  The project will remove bottlenecks, improve traffic flow and level of service, and increase capacity on one of the City’s major commute corridors.  The segment of Oakland Road between Brokaw Road and Commercial Street is the first phase of several construction contracts (location map attached).  The remaining segments of Oakland Road will be constructed immediately following acquisition of right-of-way and the widening of two railroad crossings by the Union Pacific Railroad Company.

 

The scope of this 1.2 miles segment from Brokaw Road to Commercial Street includes sidewalks, curbs, gutters, driveways, asphalt concrete pavement, streetlights, traffic signal detector loops and storm drainage improvements.

 

Construction is scheduled to begin in December with completion in March.

 

 

ANALYSIS

 

A supplemental memo will be provided after bids are opened on October 2, 2003 and the adoption of the Mitigated Negative Declaration on October 14, 2003.

 

Council Policy provides for a standard contingency of five percent on public works street projects.  However, on this project a ten percent contingency is being requested because the project is along an old State Route where old record drawings of underground utilities are unavailable and unforeseen conditions may require additional work. 

 

 

PUBLIC OUTREACH

 

To solicit contractors, this project was listed on the City’s Internet Bid Line and advertised in the San José Post Record.  Bid packages for all public works construction projects are provided to various contractor organizations and builder’s exchanges.  In addition, a community meeting will be held on October 2, 2003 as part of the CEQA environmental process.

 

 

COORDINATION

 

This project and memo have been coordinated with the City Attorney’s Office, City Manager’s Budget Office, Planning, Building and Code Enforcement Department and the Union Pacific Railroad Company.

 

 

COST IMPLICATIONS

 

1.      COST OF RECOMMENDATION:  (Engineer’s Estimate) $391,300

 

2.      COST OF PROJECT (First Phase):

Project Delivery

$  98,000

Construction

391,300

Contingency

39,000

      TOTAL

$528,300

 

3.      SOURCE OF FUNDING:  429 Building and Structure Construction Tax Fund

 

4.      FISCAL IMPACT: This project is consistent with the Council-approved Budget Strategy Economic Recovery section in that it will spur construction spending in our local economy.  The proposed operating and maintenance costs for this project have been reviewed and it has been determined that the project will have no significant adverse impact on the General Fund operation budget.

 

BUDGET REFERENCE

 

Fund

  #

Appn.

  #

 

Appn. Name

 

RC #

Total

Appn.

Amt. for

Contract

2003-04

Adopted

Budget Page

Last Budget Action

(Date, Ord.No.)

429

6339

Oakland Road: Route 101 to Montague

 

059583

$4,044,000

$391,300

815

 

 

 

CEQA

 

ND, PP03-06-209, Pending.

 

 

KATY ALLEN                                                            JAMES R. HELMER

Director, Public Works Department                              Director of Transportation