
To: HONORABLE
MAYOR AND
From:
Del D. Borgsdorf
CITY COUNCIL Susan
F. Shick
Subject: CONSTRUCTION IMPACT Date: 9-29-03
MITIGATION ORDINANCE
Council District: Citywide
a) Approval of an ordinance amending Title 13 of the Municipal Code to revise Chapter 13.36, and amending various sections in Chapter 15.50 of Title 15 setting forth a requirement that a Construction Impact Mitigation Plan be prepared for all major construction projects, unless the City has otherwise entered into an agreement requiring such a Plan.
b) Approval of a resolution amending Resolution No. 71216, as amended, the City’s schedule of administrative fines, to establish a $5,000 per day administrative fine for violations of the Construction Improvement Mitigation Plan ordinance and Construction Improvement Mitigation Plan requirements, to take effect upon the same date as the ordinance.
c) Direction to City and SJRA staff to comply with the provisions of the Ordinance for all City and SJRA major construction projects.
BACKGROUND
The intent of the Construction Impact Mitigation Ordinance is to reduce the impacts on residents and businesses from major construction projects.
This issue has previously been discussed at Council meetings on May 28 and September 26, 2002. This issue has previously been discussed at the Building Better Transportation (BBT) Committee on April 7, June 2, August 4, and September 8, 2003 and at the Driving a Strong Economy Committee on August 25, 2003.
During these working sessions, there has been discussion on the following topics:
ANALYSIS
From discussions at
Committee and Council meetings as well as public outreach meetings, there is
consensus that the most significant construction impacts are from publicly
funded projects, such as VTA rail projects, extensive public infrastructure
projects, such as sewer and storm drain improvements, and from quasi-public and
private projects such as energy, water and telecommunications utility provider
projects. In addition, there is a need
for more attention to be focused on construction impact mitigation for smaller
projects. Current regulations are
sufficient to require adequate construction impact mitigation for most private
developer projects.
Attached to this
report is a recommended ordinance (Attachment B) to require the preparation of
a Construction Impact Mitigation Plan (CIMP) for “major construction projects”
(as defined below) and a recommended resolution (Attachment C) establishing a
$5,000 per day administrative fine for violations of the CIMP requirements
which would take effect upon the same date as the ordinance if adopted by
Council.
The proposed
ordinance would apply to all major construction projects that require a public
right-of-way encroachment permit from the City. It would not directly apply to City and SJRA construction
projects since these projects do not require encroachment permits. For this reason, the second recommendation
directs City and SJRA staff to comply with the provisions of the ordinance for
all City and SJRA-funded major construction projects.
Some of the upcoming
major construction projects in San Jose are rail transit projects within the
street right-of-way. VTA has proposed
and staff concurs that a cooperative agreement between the City and the VTA may
be a more flexible means for clearly delineating the obligations and
responsibilities for construction impact mitigations for VTA projects. In recognition of the benefits of
cooperation versus regulation, the proposed ordinance would not be applicable
to major construction projects where Construction Impact Mitigation plans are
addressed in agreements that are approved by the City Council. The requirements within the ordinance serve
as the basis when negotiating such agreements.
The proposed
ordinance defines a major construction project as one where the work in the
existing public right-of-way has a value in excess of $10 million and where at
least one of the following conditions exists:
Projects with a $10
million threshold include the vast majority of the major public and
quasi-public projects with significant construction impacts. However, it would be very rare for a private
development project, other than utility and telecommunication projects, to meet
the $10 million threshold. By using a
value-based threshold, the CIMP Ordinance will be applicable to the majority of
the projects that create the impacts of concern to the Council and the public,
while excluding the majority of projects that already are significantly
regulated. The other three thresholds
will exclude large projects if there does not appear to be actual physical
impacts from the project on traffic or pedestrian access.
If a CIMP is required, the proposed ordinance defines the study area to be all residents and businesses within a 500-foot radius of the project site. The proposed ordinance will require the project sponsor to prepare a study to determine all potential impacts on businesses and residents within this study area, resulting from the proposed construction project. The proposed ordinance recognizes that environmental and physical impacts of construction may already have been studied and assessed under the CEQA process and allows the Construction Impact Mitigation Plan to incorporate by reference such analysis and any proposed mitigation measures discussed in any CEQA document prepared for the same project.
The proposed ordinance defines the requirements of a Construction Impact Mitigation Plan. The CIMP will be required to include:
a) Detailed description of the project, including site maps, construction phasing schedule, location and timing of activities.
b)
Detailed
analysis of potential impacts to the study area.
c)
Detailed
description of proposed mitigation measures.
d) A comprehensive communications plan, including public information and outreach efforts.
The proposed ordinance
requires that impacts are to be reasonably mitigated to the extent
practicable. A number of potential
mitigation measures are included, but other mitigation measures can be proposed
by the project proponent. The following
measures are listed as examples in the proposed ordinance.
a)
Limited hours
of construction;
b)
Provision of
alternative access routes;
c)
Outreach to
business to schedule utility outages;
d)
Increased
signage to provide visibility, notice of alternative parking, notice of
alternative access;
e)
Marketing
assistance, technical business support, and cross-promotion efforts with
adjacent businesses.
f)
Direct or
indirect financial assistance, such as, but not limited to, that which may be
available through government loan or grant programs.
The proposed
ordinance requires that the CIMP be approved by the City Council prior to the
Director of Public Works issuing an encroachment permit under Titles 13 and 15
of the Municipal Code. For projects
covered by a Council-approved cooperative agreement, the agreement will address
both the content and process for the development and implementation of a
Construction Impact Mitigation Plan for the project.
One other issue
expressed by the BBT Committee was the concern when there are concurrent large
private developments and/or major public projects proximate to one
another. The cumulative impacts of
these projects often warrant special attention and close coordination between
project proponents. To address this
situation, additional coordination must and will take place at all stages of
project implementation. Staff from
PBCE, DOT, DPW and SJRA will work more closely on coordinating both public and
private projects to ensure that appropriate coordination takes place during the
construction phases of a project.
In addition, the
current encroachment permit ordinance is recommended to be modified in two
ways: First, since current encroachment
permits have a life of six months and have to be renewed if the project remains
longer in the public right-of-way, staff recommends a provision that the permit
can be revised at the time of renewal or extension if construction conditions
or conditions in the area of the project have changed. Second, it is recommended that the fines and
penalties section of the CIMP Ordinance also apply for non-compliance with
normal encroachment permit conditions.
PUBLIC OUTREACH
Outreach was conducted with utility companies (San Jose Water, Comcast, SBC, PG&E), the Contracting Community (AGC), Business Community (Chamber of Commerce, Manufacturing Group), Neighborhood / Business Associations (Downtown Association, NBD Members, SNI Committee), the Development Community (Public Works/Development Industry Meeting, Planning Roundtable) and ethnic Chambers of Commence (Hispanic, Black and Vietnamese).
COORDINATION
This memo and draft ordinance have been coordinated with the City Attorney’s Office, and the Departments of Public Works, Transportation, and Planning, Building and Code Enforcement.
The adoption of this ordinance would require that sponsors of “major construction projects” bear the following additional costs:
1. Costs of preparing a Construction Impact Mitigation Plan
2. Costs of implementing impact mitigation measures
When the City or SJRA is a sponsor of a major construction project, the proposed policy would increase the cost of the project. There will also be costs for City staff to review construction impact mitigation measures for major construction projects for projects not sponsored by the City or SJRA. Neither the sponsor costs nor the City staff costs can be estimated at this time. These costs could be substantial.
Performance objectives and measurement criteria will be developed and recommended to Council upon adoption of this ordinance.
CEQA
Exempt, PP03-09-304
DEL D. BORGSDORF SUSAN F. SHICK
City Manager Executive Director