To: HONORABLE MAYOR AND From: Katy Allen
CITY COUNCIL
Subject: TRAFFIC SIGNAL UNIT 1A Date: 10-29-03
CONCOURSE
& LUNDY –
UTILITY
EASEMENTS
Council District: 4
Adoption of a resolution:
a. Authorizing
the City Manager to accept a public utility easement from Bedford Property
Investors, Inc., for a public utility easement located near the Concourse and
Lundy intersection for a cost not to exceed $1,159 and to execute all documents
necessary to complete the transaction; and
b. Approving of an agreement for
purchase of a public utility easement located north of the Concourse and Lundy
intersection, by and between the City of San José and Flextronics International
USA, Inc., for $1,230.
CEQA: Exempt, PP01-11-193.
BACKGROUND
The installation of a new traffic signal system at Concourse Drive and Lundy Avenue intersection is part of Traffic Signal Unit 01A Project. Traffic Signal Unit 01A Project includes four intersections on which the City will install signal standards, signal display equipment, conduit and electrical systems, vehicular and pedestrian detection systems, street lighting, and related improvements.
The property being
received from Bedford Property Investors and Flextronics is property necessary
in order to run the necessary cable to the traffic signal to provide it with
power. Under the franchise agreement between
the City and PG&E, PG&E has no responsibility to purchase private
property rights for a City project making it necessary for the City to purchase
these rights. The City is acquiring
easements for this project so that a service point can be provided to activate
the traffic signal system at Concourse Drive and Lundy Avenue
intersection. A map showing the subject
property is attached as Exhibit A.
Multiple communications both oral and written occurred between City staff and representatives of Flextronics and Bedford Property Investors. Final agreement was reached with both Bedford Property Investors and Flextronics for the transfer of the Property.
Preparation of this staff memo has been coordinated with the City Attorney’s Office, the City Manager’s Budget Office and the Departments of Transportation and Planning, Building and Code Enforcement.
The public utility easements will cost an estimated $2,389. Nominal escrow fees are also anticipated. These costs will be funded as part of the Traffic Signals project in the Building and Structure Construction Tax Fund.
|
Fund # |
Appn # |
Appn Name |
RC # |
Total Appn |
Amt for Contract |
Adopted Budget Page |
Last Budget Action |
|
429 |
4321 |
Traffic Signals |
115503 |
$4,203,000 |
$2,389 |
864 |
10/14/03, Ord. No. 26997 |
CEQA
Exempt, PP01-11-193.
KATY ALLEN
Director, Public Works Department