To: HONORABLE
MAYOR AND From: Katy Allen
CITY
COUNCIL Sara
L. Hensley
Subject: PLAZA DE CESAR
CHAVEZ Date: 10-29-03
ELECTRICAL UPGRADES
Council
District: 3
Report on
bids and take appropriate action based on the evaluation of bids for the Plaza
de Cesar Chavez Electrical Upgrades Project, and approval of a fifteen percent
contingency.
CEQA: Exempt,
PP03-06-202.
BACKGROUND
Plaza de Cesar Chavez Park is an existing three acre urban park located in downtown San José on Market Street between West San Carlos and West San Fernando Streets (map attached). The most recent park renovation occurred in 1989 and included a central pathway, stage area, fountain and various seating areas. The park is the site of several events throughout the year including “Music in the Park” and “Christmas in the Park.”
The park electrical service and fountain pump system have each required extensive repairs over the past several years due to age deterioration, general wear and corrosion due to moisture inside the service vaults. In addition, increased electrical service requirements for “Christmas in the Park” and other events have stressed the available limits of the existing electrical system. It is necessary to renovate and upgrade these systems to prevent possible disruption of the electrical service during special events and to ensure the fountain operates properly.
This project includes a new electrical service for the stage area, replacement of the east (main) vault with new park electrical distribution equipment, renovation and upgrade of the central (fountain) vault electrical and mechanical components, upgraded electrical service for the Christmas tree and improved electrical service to the south island. The contract is structured so that construction activities begin in January 2004, after Christmas in the Park 2003, with completion of the stage area in May 2004 before the Music in the Park season begins. The remaining improvements will be completed in November 2004, prior to Christmas in the Park.
Items in the base bid scope of work for this project include installation of new electrical service to the north stage area, a new east vault and electrical equipment, irrigation and turf repair.
In
addition to the base bid scope of work there are four Add Alternate bid items
as follows:
|
|
Engineer’s Estimate |
|
Add
Alternate No. 1: Central Vault
Electrical Upgrades |
$230,000 |
|
Add
Alternate No. 2: Central Vault
Mechanical Upgrades |
$100,000 |
|
Add
Alternate No. 3: Christmas Tree
Electrical |
$90,000 |
|
Add
Alternate No. 4: South Island
Electrical |
$30,000 |
An
exemption for environmental clearance was granted for this project.
A
supplemental memorandum will be provided after bids are opened on October 30,
2003.
Although Council policy
provides for a standard contingency of ten percent on underground projects, a
contingency budget of $220,000, approximately 15 percent, is recommended for
this project due to the extensive underground work and lack of accurate
drawings of the park utilities.
To solicit contractors, this
project was listed on the City’s Internet Bid Line and advertised in the San José Post Record. Bid packages for all Department of Public
Works construction projects are provided to various contractor organizations
and builder’s exchanges.
Staff will inform the Downtown
Association and businesses surrounding the site of the project of all impacts
to the area.
This project and memo have been
coordinated with the Departments of General Services and Planning, Building and
Code Enforcement, the City Attorney’s Office and the City Manager’s Budget
Office.
COST IMPLICATIONS
1. AMOUNT
OF RECOMMENDATION: (Engineer’s Estimate) $1,450,000
2. COST OF PROJECT:
|
Project Delivery |
$480,000 |
* |
|
Construction |
1,450,000 |
|
|
Contingency |
220,000 |
|
|
TOTAL |
$2,150,000 |
|
* A total of $167,551 was expended/encumbered
in Fiscal Year 2002-2003 for project delivery costs.
3. SOURCE
OF FUNDING: 391 – C&C Tax fund, City-Wide
4. FISCAL IMPACT: This project is consistent with the Council-approved Budget
Strategy Economic Recovery section in that it will spur construction spending
in our local economy. The annual
operating and maintenance costs of this project have been reviewed, and it has
been determined that the project will reduce maintenance costs and will have no
significant adverse impact on the General Fund operating budget.
BUDGET REFERENCE
|
Fund # |
Appn # |
Appn. Name |
RC # |
Total Appn. |
Amt. for Contract |
Adopted Budget Page |
Last Budget Action (Date, Ord. No.) |
|
391 |
4496 |
Plaza de Cesar Chavez Electrical
Vaults |
12250B |
$2,032,000 |
$1,450,000 |
Page 605 |
10/14/03, Ord. No. 26997 |
Exempt, PP03-06-202.
KATY
ALLEN SARA
L. HENSLEY
Director,
Public Works Department Director,
Parks, Recreation and
Neighborhood
Services