To:   HONORABLE MAYOR AND                   From:   Katy Allen

                        CITY COUNCIL                                                        Jane Light

 

Subject: ALUM ROCK BRANCH                        Date:          11-17-03

                        LIBRARY

 

Council District:  5

SNI:  East Valley/680 Communities

 

REASON FOR SUPPLEMENTAL MEMO

 

To provide additional information after bids were opened.

 

 

RECOMMENDATION

 

Report on bids and award of contract for the construction of the New Alum Rock Branch Library Project to the low bidder, West Bay Builders, Inc., to include the base bid and Add Alternates Nos. 1, 2 and 4 in the amount of $8,225,000, and approval of a contingency in the amount of $822,000.

CEQA:  Negative Declaration, H02-064.

 

 

ANALYSIS

 

Bids were opened on October 30, 2003 with the following results:

 

 

Contractor

 

Base Bid

Add. Alt. No. 1, 2, 4

Total Bid

Variance Amount

Over/(Under)

Percent

Zovich Construction

  (Hayward, CA)

$9,250,000

 

 

$284,500

$9,534,500

 

 

$1,623,500

17

Ralph Larsen & Sons

(Belmont, CA)

8,536,000

 

330,000

8,866,000

 

955,000

11

Robert Bothman

  (San Jose, CA)

8,165,000

 

 

295,000

8,460,000

 

 

549,000

7

Howard S. Wright Const.

  (Sacramento, CA)

8,050,000

 

 

370,000

8,420,000

 

 

590,000

7

John Plane Construction

  (Burlingame, CA)

8,070,000

 

 

313,000

8,383,000

 

 

472,000

6

West Bay Builders, Inc.

  (San Rafael, CA)

7,925,000

 

300,000

8,225,000

 

314,000

4

Engineer's Estimate

 $7,580,000

    331,000

 7,911,000

 

--

--

 

 

 

Contractor

Add Alt.

No. 1

Add Alt.

 No. 2

Add Alt.

 No. 3

Add Alt.

 No. 4

Zovich Construction                            

$86,500

$122,000

$210,000

$76,000

Ralph Larsen & Sons                    

120,000

125,000

200,000

85,000

Robert Bothman          

125,000

130,000

208,000

40,000

Howard S. Wright Const.

109,000

216,000

167,000

45,000

John Plane Construction                           

60,000

130,000

544,000

123,000

West Bay Builders, Inc.

90,000

160,000

230,000

50,000

Engineer's Estimate

171,000

122,000

49,000

38,000

 

The low bid submitted by West Bay Builders, Inc., to include the base bid and Add Alternate Nos. 1, 2 and 4 is four percent above the Engineer’s Estimate.  Add Alternate No.3, Staff Workstations, will not be accepted, because it has been determined that the cost would be less if purchased separately. The bid is considered acceptable for the work involved.

 

Council Policy provides for a standard contingency of ten percent on public works projects involving the construction of a building.  The standard contingency is appropriate for this project.

 

 

COST IMPLICATIONS

 

1.

AMOUNT OF RECOMMENDATION: $8,225,000

 

 

2.

COST OF PROJECT:

 

 

 

Project Delivery

 2,013,000

*

 

Construction

8,225,000

 

 

Contingency

822,000

 

 

TOTAL

$11,060,000

 

 

*A total of $1,314,192 was expended/encumbered in fiscal years 2001/02 and 2002/03 for project delivery costs.

 

3.         SOURCE OF FUNDING:  472 – Branch Libraries Bond Projects Fund

 

4.         FISCAL IMPACT:  This project is consistent with the Council-approved Budget Strategy Economic Recovery section in that it will spur construction spending in our local economy. The impact to the operating budget from the opening of this facility will initially be partially offset by savings resulting from the closing of the Joyce Ellington Branch for reconstruction through March 2007.

 

 

BUDGET REFERENCE

 

 

Fund

#

 

Appn.

#

 

Appn. Name

 

RC #

 

Total

Appn.

 

Amt. For Contract

Adopted Budget Page

Last Budget Action

(Date, Ord. No.)

472

6999

Alum Rock Branch

 118489

9,807,000*

 8,225,000

366

10/14/03, Ord. No. 26997

 

*This budget reference is for the current fiscal year only.  The remaining costs of the project have been expended in prior years or will be expended next fiscal year.  An additional $148,000 is budgeted in the Library Bond Fund in 2004-05 for project costs.

 

 

CEQA

 

Negative Declaration, H02-064.

 

 

JANE LIGHT                                                       KATY ALLEN

Library Director                                                    Director, Public Works Department