
To: HONORABLE MAYOR AND From: Stephen M. Haase
CITY COUNCIL Dale Foster
Subject: CONSTRUCTION FIRE
protection Date: November
14, 2003
ORDINANCE
COUNCIL DISTRICT: City Wide
RECOMMENDATION
Approve an Ordinance amending Title 17 of the San Jose Municipal Code by adding a new Chapter 17.82 relating to Construction Fire Safety (Attachment A).
On June 24, 2003, during
discussion of the recommendation for an ordinance to enhance fire safety during
construction of large wood-frame buildings, Council directed staff to:
· Provide
additional information on construction fire safety practices in other
jurisdictions
· Explain
why 350,000 square foot was selected as the "trigger" for requiring
fire resistive walls ("mitigating fire protection barriers" or
"MFPBs") to be installed and explore whether other triggers might be
appropriate.
SURVEYS OF OTHER JURISDICTIONS
In September and October
2002, Fire and Building staff surveyed 33 jurisdictions, identified in
Attachment "B", by email or phone.
Attachment "C" provides a summary of construction fire safety
measures exceeding Uniform Code requirements that were identified by the jurisdictions
that responded to the 2002 survey.
During this survey, staff
learned that a large fire had destroyed much of the original wood frame
construction in a large Ventura County multi-family project. As a condition to rebuild, Ventura County
set a limitation of a maximum of 200,000 square feet of exposed lumber at any
one time. This restriction was not an
ordinance or code change, but rather a one-time requirement that applied to
that one project only. Portland also
had a large fire in a project under construction. Portland continues to permit wood-framed
construction without special requirements until the building exceeds 4 stories,
but for buildings over four stories, compartmentalization must be provided and
sprinkler systems activated as soon as possible. (See Attachment C). Wood
framed structures over four stories are not permitted in the State of
California.
In July and August 2003,
Fire staff conducted a survey of 22 additional medium to large municipalities. Attachment
"D" provides a summary of the construction fire safety measures
exceeding Uniform Code requirements that were identified by the 12
jurisdictions that responded to the 2003 survey. Although there were similar fires in Minneapolis and Las Vegas,
there is no city in the country that has an ordinance imposing square footage
limits on unprotected combustible construction.
"TRIGGER" FOR REQUIRING MITIGATING FIRE PROTECTION BARRIERS
The June 24th staff
recommendation was to apply the most stringent new ordinance requirements,
relating to Mitigating Fire Protection Barriers, only to projects exceeding
350,000 square feet of wood framing.
This 350,000 square foot threshold trigger was developed through a collaborative process with City staff
and the development community.
After reconsideration of this
trigger for MFPBs, staff is now recommending an additional trigger of two
hundred thousand (200,000) square feet for buildings that are more than fifty
feet in height above the adjoining natural ground surface. Attachment A highlights this change in the
proposed ordinance as well as other minor technical changes.
Installing mitigating fire protection barriers will not prevent a fire from occurring, however the barriers may help limit the spread and size of a fire. Developers, contractors and community interest groups expressed concern that setting too low a threshold for MFPBs would result in substantial additional project costs and construction delays, which would potentially deter or reduce the number of units built in future developments, and increase the rental or sale price for new units due to:
· Inefficiencies
in methods of construction, i.e. the normal construction sequence would be
altered by certain trades working at different times and in different areas
(rather than contiguously) and, some trades (e.g.: framers and drywall
workers) forced to work in multiple construction phases (i.e. start/stop
cycles, rather than a continuous flow of construction activity). According to
the development community, these inefficiencies would result in several months
of delays and result in significant cost increases.
· Delays
in construction would result in increased indirect costs (costs of supervising
the project, and materials/equipment required for building).
· Delays
in construction would result in significant loss in anticipate rent revenues.
If the ordinance were to
result in developers reducing the size of structures to avoid the costs
associated with MFPBs, owner/developers might choose to build large development
projects in adjacent jurisdictions rather than San Jose. Over the past three years the City has
approved permits for the construction of the following number of projects based
upon size of the wood-framed buildings:
|
Project Size (in square feet) |
Total Number of Projects |
|
Greater than 350,000 |
8 |
|
200,001 to 350,000 |
10 |
|
100,001 to 200,000 |
4 |
|
50,000 to 100,000 |
4 |
The 200,000 sq. ft threshold
limit for projects over 50 feet above natural grade will require projects like
Santana Row to have Mitigating Fire Protection Barriers at lower thresholds due
to these taller structures presenting greater firefighting challenges. In recommending this additional threshold,
staff took into consideration the one time 2 million board feet construction
size (approximately 200,000 square feet) threshold that was applied by Ventura
County.
The Santana Row building
that burned in the August 19, 2002 fire (Building 7) had two levels of parking,
resulting in the podium on which the wood frame construction was built, being
approximately 18 feet above grade.
Building 7 also had mixed occupancy - commercial use surrounding the
parking space at grade level. The
commercial uses needed 18 feet of height, thus the podium level was higher than
typical residential structures that are 13 feet. Requiring MFPBs at 200,000 square feet on buildings that have
wood framing more than fifty feet above ground level makes sense because these
taller buildings present more challenges to firefighter safety and firefighting
effectiveness.
The standard that staff is proposing makes
sense, is justified in improving safety for the community and will require a
Santana Row like project to have improved safety during wood frame
construction. In addition, the new Fire
Protection Plan and Fire Safety Officer requirements, which will apply to all
projects involving 50,000 square feet or more of combustible construction,
should lower the risk of fire occurrence in these projects.
COORDINATION
The proposed recommendations
have been coordinated between the Department of Planning, Building & Code
Enforcement, Fire Department and the City Attorney’s Office.
PUBLIC OUTREACH
An Informational Memo dated
May 5th, summarizing the activities and recommendations of the
industry workshops and focus group meetings, was sent to the Mayor and the
Council. Additional meetings were held
with industry representatives after the June 24th Council meeting.
COST IMPLICATIONS
No new fees for review and
approval of Fire Protection Plans are proposed at this time. The review and approval process of these
Plans will be part of the plan review process for which fees are already
charged.
It is expected that there
will be a minor financial impact on the construction industry as a result of
adoption of this ordinance.
IMPLEMENTATION
After the proposed ordinance
is approved, the Fire Chief will adopt implementing regulations as authorized
by the ordinance, and the Building Division and Fire Department staff will
finalize the development of procedures, checklists and outreach material to
implement the recommendations.
CEQA
Exempt. PP03-11-358
DALE FOSTER STEPHEN
M. HAASE, DIRECTOR
Acting Fire Chief Planning,
Building and Code Enforcement
Attachment A
ORDINANCE
NO. ____________
AN ORDINANCE OF THE CITY OF SAN JOSE AMENDING TITLE 17 OF THE SAN JOSE
MUNICIPAL CODE BY ADDING A NEW CHAPTER 17.82 RELATING TO FIRE SAFETY DURING
CONSTRUCTION
WHEREAS, the California Fire Code as adopted by the City of
San Jose in Chapter 17.12 of the San Jose Municipal Code, regulates fire safety
during construction; and
WHEREAS, the Uniform Building Code as adopted by the City of
San Jose in Chapter 17.12 and Title 24 of the San Jose Municipal Code,
establishes fire safety standards that buildings must meet prior to occupancy;
and
WHEREAS, in September 2002, the Council of the City of San Jose
directed City staff to investigate improving City regulation of construction
practices to increase fire protection during the construction of large
wood-frame buildings; and
WHEREAS, City staff have surveyed other jurisdictions and
conducted workshops and study sessions with the goal of identifying potential
new regulations that would achieve two main objectives:
1. Reduce the potential for occurrence of a fire
while large wood-frame buildings are under construction; and
2. Facilitate the ability to fight a fire that
starts when a large wood-frame building is under construction, by limiting fire
spread; and
WHEREAS, the Council
of the City of San Jose desires to enact new regulations to apply during the
construction of certain wood frame buildings, without altering such building
standards or fire safety regulations as may otherwise be established by the San
Jose Municipal Code, or other applicable law or regulation, including but not
limited to the Uniform Building Code or California Fire Code;
NOW THEREFORE BE IT ORDAINED BY THE COUNCIL OF THE
CITY OF SAN JOSE:
Title 17 of the San José Municipal
Code is hereby amended by adding a new Chapter to be numbered and entitled and
to read as follows:
Part 1
General Provisions
17.82.100
Purpose
The purpose of this Chapter is to
minimize the potential for the occurrence and spread of fires, and to
facilitate firefighting efforts, during construction of wood frame buildings.
17.82.110 General
Requirements
A. The provisions of this Chapter shall apply only to
activities occurring during the construction of certain wood frame buildings as
specified herein. Nothing contained in
this Chapter shall be construed to alter such building occupancy standards or
fire protection measures for wood frame or other construction methods as may
otherwise be set forth in this Code.
B. No person shall engage in any aspect of construction on a
Large or Major Wood Frame Building Project, or permit or authorize any such
construction to occur, except in full compliance with this Chapter.
C. The property owner, as identified on the application for a
building permit for a Large or Major Wood Frame Building Project, shall be
liable for full compliance with this Chapter.
17.82.120 Administrative
Regulations
The Fire Chief and the Chief
Building Official are authorized to, from time to time, as necessary to
implement this Chapter, issue, review and revise administrative regulations to
implement the provisions of this Chapter, including but not limited to
regulations concerning the required content of Construction Fire Protection
Plans and the manner in which Fire Safety Officer duties are to be performed.
Part 2
Definitions
17.82.200
Definitions
The definitions contained in this
Part shall govern the interpretation of this Chapter. Where terms are not specifically defined in this Chapter, the
definitions contained In Chapters 17.04, 17.12 and Title 24 of this Code shall
control.
17.82.210 Building
Height
"Building
height" for the purpose of this Chapter 17.82 only shall mean the vertical
distance above a reference datum, measured to the highest point of the coping
of a flat roof, or to the deck line of a mansard roof, or to the average height
of the highest gable of a pitched or hipped roof. The reference datum shall be selected by either of the following,
whichever yields the greatest height of building: (1) The elevation of the
highest natural ground surface within a five (5) foot horizontal distance of
the exterior wall of the building when the highest such natural ground surface
is not more than ten (10) feet above the lowest grade; or (2) An elevation ten
(10) feet higher than the lowest grade when the natural ground surface
described in (1) is more than ten (10) feet above the lowest grade.
17.82.220
Construction
Fire Protection Plan
“Construction
Fire Protection Plan” means a document, which specifies measures and practices
to be incorporated into the construction process to minimize the potential for
the occurrence and spread of fires, and to facilitate firefighting efforts,
during building construction.
17.82.230 Exposed Wood
Framing
“Exposed Wood Framing” means the
area of a Large or Major Wood Frame Building Project that is enclosed, in whole
or in part, by wood stud framing and decking of the floor or roof above. Attics not designated for occupancy,
balconies open to the sky and other similar open space are not included in this
square footage calculation. For the
purpose of measuring total square footage of wood framing, any adjacent ongoing
wood frame construction is considered to be within the project when adjacent
structures are separated by less than sixty (60) feet of open air.
17.82.240
Fire
Safety Officer
“Fire Safety Officer” means an
individual employed on a construction job site whose job function is to
minimize the potential for the occurrence and spread of fires in accordance
with the requirements of this Chapter 17.82 and the approved Construction Fire
Protection Plan. The duties of a Fire Safety Officer shall be in addition to,
and do not supercede, the duties of any contractor or individual engaging in
activities which have the potential to cause the occurrence or spread of fire,
including but not limited to the duties specified in Article 49 of the 2001
California Fire Code, as adopted in Chapter 17.12 of this Code, or such other
fire safety code as may be adopted by the City from time to time.
17.82.250 Hot Work
“Hot Work”
means construction activities including, but not limited to, cutting, welding,
use of open torch, brazing, and glass blowing, which are regulated by Article
49 of the 2001 California Fire Code, as adopted in Chapter 17.12 of this Code,
or by any similar fire safety code or provision as may be adopted by the City
from time to time.
17.82.260 Large
Wood Frame Building Project
“Large Wood Frame Building
Project” means a building project utilizing Exposed Wood Framing in the
construction of fifteen (15) or more attached dwelling units, or construction
exceeding a total of fifty thousand (50,000) square feet.
17.82.270 Major Wood Frame
Building Project
“Major Wood Frame Building Project” is Large Wood Frame
Building Project which will either:
(1) exceed
three hundred fifty thousand (350,000) square feet; or
(2) exceed two hundred thousand (200,000) square feet if the Project
exceeds fifty feet in height as defined in Section 17.82.210.
17.82.280 Maximum Allowable
Exposed Wood Framing Limit
"Maximum Allowable Exposed Wood Framing Limit"
means:
(1) three
hundred fifty thousand (350,000) square feet; or
(2) two hundred thousand (200,000) square feet for a Large Wood Frame
Building Project which exceed fifty (50) feet in height as defined in Section
17.82.210.
17.82.290 Mitigating Fire
Protection Barriers
“Mitigating Fire Protection
Barrier” means at least one layer of 5/8 inch gypsum board or other fire
resistive blocking located at the end of a fire resistive area or separation
wall or party wall, and installed such that the Mitigating Fire Protection
Barrier(s) and fire resistive wall(s) enclose area(s) of not less than ten
thousand (10,000) square feet and not more than fifty thousand (50,000) square
feet.
Part 3
Specific Requirements
17.82.300 Construction
Fire Protection Plan Requirements
A. No building permit shall be issued which allows the
commencement of wood frame construction on a Large or Major Wood Frame Building
Project, unless the Fire Chief has provided written approval of a Construction
Fire Protection Plan for the project.
B. Construction Fire Protection Plans for a Large or Major Wood
Frame Building Project, shall state how the requirements of this Chapter and
all other fire safety requirements shall be met during construction of the
project. Construction Fire Protection
Plans for Major Wood Frame Building Projects shall, in addition, state how off
hours security will be addressed, and how construction sequencing, including
the installation of Mitigating Fire Protection Barriers, will be utilized to
minimize the potential for the occurrence and spread of fire.
C. No person shall engage in, permit, authorize or allow any
aspect of construction on any project for a Construction Fire Protection Plan
unless the Fire Chief has provided written approval of a Fire Protection Plan
for the project.
D.
No person shall engage in, permit, authorize or allow any aspect
of construction on any project for which a Construction Fire Protection Plan
has been approved except in full compliance with the approved Construction Fire
Protection Plan for the project.
E.
The approved Construction Fire Protection Plan shall be a condition
of the building permit and a copy of the Plan shall be maintained on site at
all times during construction of the project.
17.82.310 Fire
Safety Officer Requirements
A. No person shall perform, permit, authorize or allow any Hot
Work on any Large or Major Wood Frame Building Project, after wood framing has
commenced, unless a Fire Safety Officer is present on the project site at all
times while Hot Work is being performed.
B. A Fire Safety Officer shall monitor, confirm and document
the following:
1. That a fire watch as required by Article 87 of the
California Fire Code, as adopted in Chapter 17.12 of this Code, or by any
similar fire safety code or provision as may be adopted by the City from time
to time has been provided during all Hot Work operations;
2. That storage, use and handling of flammable liquids conforms
to all federal, state and local, legal and administrative requirements;
3. That construction debris is promptly removed from the
project site;
4. That fire protection equipment, including fire
extinguishers, fire hydrants, standpipes, and other fire service connections,
are in place and operational, as required by law or specified in the approved
Construction Fire Protection Plan;
5. That Mitigating Fire Protection Barriers are in place on any
Major Wood Frame Building Project, in accordance with this Chapter and the
construction sequencing requirements of the approved Construction Fire
Protection Plan;
6. That such other requirements relating to fire safety have
been met, as may be specified in this Code, in the regulations adopted pursuant
to this Chapter, or in the approved Construction Fire Protection Plan.
17.82.320 Basic
Fire Protection Facilities
A. No person shall commence, permit, authorize or allow wood
framing or engage in any construction activity after the commencement of wood
frame construction, on a Large or Major Wood Frame Building project unless an
all weather access road is in place meeting the requirements of Section
17.12.430 of this Code, or such other fire apparatus access requirements as may
be specified in the Construction Fire Protection Plan for the project, or in
any development or building permit for the project, are in place and
functional.
B. No person shall commence, permit, authorize or allow wood
framing or engage in, permit, authorize or allow any construction activity
after the commencement of wood frame construction, on a Large or Major Wood
Frame Building Project, unless all fire protection equipment, including fire
extinguishers, fire hydrants, standpipes, and other fire service connections,
are in place and operational, as required by law or specified in the approved
Construction Fire Protection Plan.
17.82.330 Mitigating
Fire Protection Barriers
No person
shall continue, permit, authorize or allow any construction activity on any
Major Wood Frame Building Project, unless Mitigating Fire Protection Barriers
are in place and operational, in accordance the approved Construction Fire
Protection Plan, to maintain the project at or below the applicable Maximum
Allowable Exposed Wood Framing Limit.
|
PASSED
FOR PUBLICATION of title this _____ day of ___________, 2003, by the
following vote: |
|||
|
AYES: |
|
||
|
NOES: |
|
||
|
ABSENT: |
|
||
|
DISQUALIFIED: |
|
||
|
|
RON
GONZALES Mayor |
||
|
ATTEST: |
|
||
|
PATRICIA L. O’ HEARN City Clerk |
|
||
Attachment "B"
List of Jurisdictions
Surveyed in 2002:
* Beverly Hills
* Burbank
* Downey
* El Segundo
* Gardena
* Glendale
* Inglewood
* Los Alamitos
* Los Angeles City
* Los Angeles County
* Long Beach
* Malibu
* Manhattan Beach
* Monterey Park
* Newport Beach
* Norwalk
* Oceanside
* Orange County
* Palmdale
* Pasadena
* Portland, Oregon
* Redondo Beach
* San Dimas
* Santa Clara County
* Santa Clarita
* Santa Monica
* Seattle, Washington
* Simi Valley
* Thousand Oaks
* Ventura
* Vernon
* West Covina
* Whittier
Jurisdiction |
Type of Projects affected |
Fire Safety Measures Exceeding Uniform Fire Code Requirements |
|
Portland, OR |
5 story wood frames[1] |
City of Portland has
enacted major provisions after a 1999 fire that was quite similar to the
Santana Row Fire. Some of the requirements are listed below: · Submit a fire protection plan · Activate sprinklers as soon as possible · Install standpipes at each stair as construction progresses upward · Secure site 24/7 including security personnel and fencing. · Compartmentalization by area separation walls with temporary
protection of openings in such
walls (Area Separation Walls will be
as required based on Building Code) · Temporary protection of openings in floors (these openings in floor are temporary openings in floors
during construction) · Maintain structural stability by installing all required connection
hardware |
|
Los Angeles, CA |
All
wood framed buildings |
Designate
a Fire Safety inspector during all construction hours |
|
Seattle, WA |
All wood framed buildings |
Limitations on the number
of LPG tanks stored at site |
|
Downey, CA |
All
wood framed buildings |
· Construction site shall be
secured (fenced, locked and patrolled) 24 hours, seven days per week. |