CITY OF SAN
JOSÉ, CALIFORNIA Department of Planning, Building and Code Enforcement 801 North First Street, Room 400 San José, California 95110-1795 |
Hearing
Date/Agenda Number C.C.:
12-02-03 Item |
|
|
|
File Number PDC03-073 |
|
|
STAFF REPORT |
Application Type Conforming Planned Development Rezoning |
|
|
|
Council District 4 |
|
|
|
Planning Area North San Jose |
|
|
|
Assessor's
Parcel Number(s) 097-45-048 |
|
|
PROJECT DESCRIPTION |
Completed by:
Mike Mena |
|
|
Location: West side of North First Street, either
side of Component Drive |
||
|
Gross Acreage: 40.92 |
Net Acreage: 40.92 |
N/A |
|
Existing Zoning:
IP
(PD) |
Existing
Use: Vacant |
|
|
Proposed Zoning:
IP
(PD) |
Proposed Use: Research and Development/Offices |
|
|
GENERAL PLAN |
Completed by: MM |
|
|
Land
Use/Transportation Diagram Designation IP Industrial Park |
Project
Conformance: [x] Yes [ ]
No [ ] See Analysis
and Recommendations |
|
|
SURROUNDING LAND USES AND ZONING |
Completed by: MM |
|
|
North: Industrial, Retail IP Industrial
Park and A(PD) Planned Development |
||
|
East: Industrial IP
Industrial Park Zoning Districts |
||
|
South: Industrial IP
Industrial Park and Heavy Industrial |
||
|
West: Industrial and Vacant IP
Industrial Park, HI Heavy Industrial and A Agricultural |
||
|
ENVIRONMENTAL STATUS |
Completed by: MM |
|
|
[x]
Environmental Impact Report found complete November 12, 1987 [ ] Negative
Declaration circulated on |
[ ] Exempt [ ]
Environmental Review Incomplete |
|
|
FILE HISTORY |
Completed by: MM |
|
|
Annexation Title: Orchard No. 69 |
Date: April 26, 1977 |
|
|
PLANNING DEPARTMENT RECOMMENDATIONS AND ACTION |
||
|
[x] Approval [ ] Approval with Conditions [ ] Denial |
Date: _________________________ |
Approved
by: ____________________________ [ ] Action [ ]
Recommendation |
|
APPLICANT/DEVELOPER |
OWNER |
|
|
Frank
Jesse BEA
Systems, Inc. 2315
North First Street San
Jose, CA 95131 |
Frank
Jesse BEA
Systems, Inc. 2315
North First Street San
Jose, CA 95131 |
|
|
PUBLIC AGENCY COMMENTS RECEIVED
Completed by: MM |
|
Department of
Public Works None received |
|
Other
Departments and Agencies See
Attached Memorandum from the Airport Department and the Fire Department |
|
GENERAL CORRESPONDENCE |
|
None received |
|
ANALYSIS AND RECOMMENDATIONS |
BACKGROUND
The applicant, BEA Systems Inc., is requesting a
conforming Planned Development Rezoning from IP(PD) Planned Development Zoning
District to IP(PD) Planned Development Zoning District to modify the zoning
development standards for the subject 40.92 acre site located on the west side of
North First Street and on either side of Component Drive.
The
subject site is currently zoned and entitled for the development of up to 1.4
million square feet of industrial park uses.
The current zoning also includes development standards for the site
generally consistent with those established within the City’s standard
Industrial Park zoning district and consistent with the General Plan. The proposed rezoning would maintain the
previously approved land use and development intensity but would modify the
development standards to match current City standards for the Industrial Park
district, would allow a reduction in the parking requirement and would
implement an associated General Plan
Amendment request (GP03-T-09) to increase the allowable building height on the
subject site from 105 feet to 210 feet.
A Planned Development Zoning (PDC93-05-017) for the
subject site was first approved by City Council on March 1, 1994, permitting
1.4 million square feet of research and development uses and including various
development standards. The property was
subsequently rezoned by the City Council on November 20, 2001 to implement a
change to the General Plan maximum height limit for the subject property from 90
feet to 105 feet. This previous rezoning
also included minor text modifications reflecting completed traffic
improvements and incorporating revised Zoning Ordinance requirements for
bicycle/shower facilities.
The project site is generally surrounded by similar
industrial park uses. A medium-sized
commercial retail development is located to the north of the project site.
ENVIRONMENTAL
REVIEW
The
environmental impacts of this project were addressed by a Final EIR entitled,
"Rincon de Los Esteros Redevelopment Plan," and findings were adopted
by City Council Resolution No. 60197 on November 12, 1987.
GENERAL
PLAN CONFORMANCE
The proposed conforming rezoning to IP(PD) Planned
Development Zoning District is consistent with the San José 2020 General Plan
Land Use/Transportation Diagram designation of IP Industrial Park in that it
would implement the associated General Plan Text Amendment (GP03-T-09) and
would facilitate development of the project site with industrial park
uses. General Plan consistency is
further discussed below.
ANALYSIS
The
primary issues associated with this rezoning are consistency of the proposed
development with the overall goals and objectives of the previously approved PD
Zoning, consistency with applicable policies and ordinances typically applied
to industrial park properties and consistency with the General Plan.
The proposed
rezoning would maintain the previously approved land use and development
intensity but would modify the development standards to include; (1) an
increase in the maximum allowable building height from 105 to 210 feet; (2)
changes to the number of required off-street parking from the original zoning;
(3) conformance to the Industrial Park Zoning standards.
1) Maximum Height
The applicant has applied for an associated General Plan
Amendment (GP03-T-09) to increase the allowable building height on the subject
site from 105 feet to 210 feet.
Presuming that this Amendment is approved, the subject zoning would
allow development of the subject site to be reconfigured to include buildings
of up to 210 feet in height, consistent with the General Plan. The appropriateness of this height is
further discussed in the GP03-T-09 staff report. The proposed zoning does not dictate the location of buildings on
the site and so their design would be resolved through the Planned Development
Permit stage. Increasing the maximum
height will allow the applicant greater flexibility in the development of the
site, including the ability to concentrate the building square footage in
proximity to North First Street and the Guadalupe
Light Rail Corridor, consistent with the City’s goals for economic development
and the concentration of development in proximity to transit.
The General Plan Transportation Policies
state that development in the vicinity of airports should be regulated in
accordance the Federal Aviation Administration guidelines. Review by the
Federal Aviation Administration (FAA) will be required at the Planned
Development Permit stage. Specific
information including building orientation, the precise coordinates for each
corner of future structures, building dimensions and types of building
materials is required in order for the FAA to complete a determination of a No
Hazard Clearance.
San Jose’s
Zoning Ordinance sets a citywide parking standard for research and development
projects of 1.0 space per 350 square feet of net floor area. Per this standard a minimum of 3,451 parking
spaces would normally be required for this development. The General Plan and North San Jose Development
Policy recommend that sites located adjacent to light rail stations should be
designed to encourage pedestrian access and discourage auto-oriented
design. San Jose’s Zoning Ordinance
also specifically allows a 10% reduction in required parking for any property
located within 2,000 feet of a light rail station.
The required
number of off-street parking facilities is proposed to be modified in the
subject rezoning to allow a 25% reduction from the citywide standard
requirement for the minimum number of parking spaces on the subject site. This would allow the number of parking
spaces to be reduced by 15% beyond the currently allowed 10% reduction. This additional reduction to the minimum
off-street parking requirement is appropriate for this type of large-scale
development for several reasons. The
project would concentrate a large amount of development in close proximity to
an existing light rail station and so strongly encourage use of the transit
system. The project will also
incorporate a variety of transit demand measures, including shuttle connections
to other transit facilities and employee incentives use of carpools or
transit. The project would also include
on-site amenities such as a cafeteria to reduce the employees’ need to drive.
3) Industrial
Park Zoning Standards
The proposed
rezoning would also incorporate some minor text modifications to reflect
changes to City policies and ordinances enacted subsequent to the original
zoning. The proposed zoning would
modify the setback standards contained within the existing zoning to match
those included within the City’s Zoning Ordinance for Industrial Park zoned
properties. The proposed rezoning would
also include text to clarify that the subject property will be governed by the
City Council Lighting Policy.
This
proposed height limit change will bring the zoning for this development into
conformance with the pending General Plan Text Amendment to increase the
allowable height for this site from 120 feet to 210 feet and will be consistent
with the City’s policies for industrial development, without lessening the
overall quality of the project. The
proposed land uses will not be modified from those previously approved and the
new standards will allow reconfiguration to facilitate the development of the
site with industrial uses consistent with City policy along transit corridors.
Staff
has determined that the proposed modification of the PD Zoning is minor, will
not jeopardize the City’s overall objectives for the site, and can be supported
as a conforming rezoning.
PUBLIC
OUTREACH
A notice of the public hearing was distributed to the
owners and tenants of all properties located within 500 feet of the project
site.
RECOMMENDATION
Planning staff recommends approval of the proposed
Conforming Rezoning for the following reasons:
1.
The proposed rezoning is consistent with the San Jose 2020 General Plan
Land Use/Transportation designation of IP Industrial Park.
2. The proposed rezoning is compatible with
surrounding land uses.
3. The proposed rezoning will facilitate
redevelopment of the subject site in conformance with the General Plan.
MM:AC