To:   HONORABLE MAYOR                             From:   Katy Allen

                        AND CITY COUNCIL                                               Sara L. Hensley

 

   Subject:   ALMADEN WINERY                                Date:   12-09-03

                        COMMUNITY CENTER

                        SEISMIC RETROFIT PROJECT

 

Council District: 10

 

REASON FOR SUPPLEMENTAL MEMO

To provide additional information after bids were opened.

RECOMMENDATION

 

Report on bids and award of contract for the Almaden Winery Community Center Seismic Retrofit Project to the lowest responsive bidder, John Plane Construction, Inc. to include the base bid and Add Alternate No. 1, in the amount of $1,764,000, and approval of a contingency in the amount of $176,400. 

CEQA:  Exempt, PP03-10-328.

 

 

ANALYSIS

 

Bids were opened on November 25, 2003 with the following results: 

 

 

 

Contractor

 

 

Base Bid

 

Add Alt. No.1

 

 

 

Total Bid

 

Variance Amount

Over/

(Under)

Percent

 

Chegwin Construction, Inc.

  (San José)

$2,280,000

 

$180,000

$2,460,000

$647,000

36

California Plus Engineering

  (San José)

2,100,000

120,000

2,220,000

407,000

22

BRCO Construction, Inc.  

  (Loomis)

2,030,000

180,000

2,210,000

397,000

22

Aztec Consultants

  (San Ramon)

2,042,000

65,000

2,107,000

294,000

16

Tinney Construction

  (Redwood City)

1,848,000

40,000

1,888,000

75,000

4

Engineer’s Estimate

1,813,000

---

1,813,000

---

---

Apex Construction Co.

  (Los Gatos)

1,798,500

0

1,798,500

(14,500)

(1)

Garden City Construction

  (San José)

1,784,025

0

1,784,025

(28,975)

(2)

John Plane Construction

  (Burlingame)

1,764,000

0

1,764,000

(49,000)

(3)

Kudsk Construction, Inc.

  (Berkeley)

1,755,000

0

1,755,000

(58,000)

(3)

Trident Builders, Inc.

  (San Mateo)

1,707,000

10,000

1,717,000

(96,000)

(5)

 

The fourth low bidder, Garden City Construction, submitted a letter on December 3, 2003 protesting the award of a contract to any of the three lowest bidders, Trident Builders, Inc., Kudsk Construction, Inc. and John Plane Construction, Inc.  The letter is attached.  The reasons in summary for the protest are as follows:

 

1.                  Trident Builders, Inc. and Kudsk Construction, Inc. failed to list the value of work to be performed by subcontractors.

2.                  John Plane Construction, Inc. failed to identify all subcontractors.

 

Staff evaluated the protest letter and found that the protest regarding the first two low bids has merit.  It does not have merit with regard to the third low bidder.  The reasons are as follows:

 

1.                  The bid form used by the City required the bidders to identify the name and address of the subcontractors performing over a specified amount of work, the kind of work to be performed by the subcontractors, and the value of such work.   The bid of the two lowest bidders failed to provide the value of the work to be performed by the listed subcontractors.  Their respective failure to provide the information requested by the bid, results in their bids being nonresponsive.  This failure to provide information expressly requested by the City cannot be waived as a minor irregularity.  Accordingly, staff recommends rejecting these bids.

 

The bid protest also speculates that the third low bidder, John Plane Construction, Inc., failed to list all subcontractors that it intends to use.  This is not obvious from the face of the bid.  Furthermore, Section 2-1.15A.4 of the City’s standard specifications states that if the contractor fails to specify a subcontractor, the contractor agrees it is fully qualified to do the work and that it shall perform such work.  Accordingly, for any work for which John Plane Construction, Inc. did not list a subcontractor, it agrees that it is qualified to do that work and that it will perform such work.  Accordingly, staff recommends awarding the contract to John Plane Construction, Inc.

 

Based upon the above findings, staff recommends rejecting the bids from Trident Builders, Inc. and Kudsk Construction, Inc. and awarding this contract to the third low bidder, John Plane Construction, Inc.  The bid submitted by John Plane Construction, Inc. is three percent under the Engineer’s Estimate.  Staff considers this reasonable for the work involved.

 

In addition to the base bid, there is one add alternate that is recommended for award.   The add alternate provides for a revised construction sequencing to allow for a faster completion date.   Construction is scheduled to begin in January with completion in December 2004.

 

Council Policy provides for a standard contingency of 15 percent on public works projects involving the renovation of a building. However, a contingency of 10 percent is being requested because staff feels that on a project of this size, $176,400 will be sufficient to handle any unforeseen conditions that may arise during construction.

 

 

COORDINATION

 

This project and memo have been coordinated with the City Attorney’s Office and the Departments of General Services, Fire, Planning, Building and Code Enforcement, Information Technology, the City Manager’s Budget Office, Council District 10 and the County of Santa Clara, Department of Environmental Health.

 

 

COST IMPLICATIONS

 

1.         AMOUNT OF RECOMMENDATION:  $1,764,000

 

2.         COST OF PROJECT:

Project Delivery

       $   794,600

*

Construction

             1,764,000        

 

Contingency

            176,400

 

         TOTAL

       $2,735,000

 

 

* A total of $408,209 was expended/encumbered in Fiscal Year 1999-2000 through Fiscal Year 2002-2003 for project delivery costs. 

 

3.         SOURCE OF FUNDING:       001 – General Fund

            389 – Construction & Conveyance Tax Fund, Council District 10

 

4.         FISCAL IMPACT:  This project is consistent with the Council approved Budget Strategy Economic Recovery section in that it will spur construction spending in our local economy.  $67,210 personnel cost and $40,000 non-personnel cost are estimated as the net annual operating costs for this facility.  The increase in expenditure is not a significant amount since a portion of the additional staffing has already been addressed, the existing facility is being maintained by the General Services Department and increased anticipated revenue will offset costs.

 

 

BUDGET REFERENCE

 

 

 

Fund

#

 

Appn #

 

Appn. Name

 

RC #

 

Total Appn.

 

Amt. for Contract

 

Adopted Budget Page

 

 

Last Budget Action

(Date, Ord. No.)

001

6980

Almaden Winery Center Conversion

117543

 2,164,000

1,764,000

Page 543

10/14/2003, Ord. No. 26997

389

4172

Almaden Winery Center Conversion

106363

197,000

--

Page 543

10/14/2003, Ord. No. 26997

 

 

Total

 

2,361,000

1,764,000

 

 

 

 

CEQA

 

Exempt, PP03-10-328.

 

 

KATY ALLEN                                                            SARA L. HENSLEY

Director, Public Works Department                              Director, Parks, Recreation and

                                                                                    Neighborhood Services