SUBJECT:     THIRD AMENDMENT TO THE AGREEMENT WITH INTERGRAPH CORPORATION FOR THE INTEGRATED DEVELOPMENT TRACKING SYSTEM (IDTS) AND APPROVAL OF THE IDTS MAINTENANCE AND SUPPORT AGREEMENT(S)

 

 

RECOMMENDATION

 

It is recommended that the City Council:

 

1.      Approve the Third Amendment to the agreement between the City of San Jose and the Intergraph Corporation for the IDTS project to:

 

a)      Increase the compensation by $25,000 for additional Consulting and Training Services; and

b)      Extend the term of the agreement from December 30, 2001 to December 31, 2002.

 

2.      Adopt a resolution authorizing the City Manager to negotiate and execute agreement(s) with Intergraph Corporation and/or IDTS subcontractors for Maintenance and Support of the IDTS in an amount not to exceed $375,000. 

 

BACKGROUND

 

The Integrated Development Tracking System (IDTS) will integrate the land use tracking subsystems in various departments into one comprehensive system that contains all permit, land use, and geographic data pertaining to a specific parcel.  This “integrated” system will provide the means of tracking development projects from start to finish.  Ultimately it will establish a “virtual one-stop permit center” for submitting development applications and issuing permits over the Internet.  A $8.3 million budget has been approved and funded for the project. 

 

On February 9, 1999, the City Council authorized the City Manager to execute an agreement with Intergraph Corporation for project management and integration services on the IDTS project.  Besides providing project management services, Intergraph is responsible for integrating the City’s existing FileNETTM document management software, Geographic Information System, and the permit tracking software. 

 

On December 19, 1999, the City Council approved an amendment to the agreement with Intergraph to include Synertech Systems as a subcontractor to Intergraph.  Synertech’s role is to provide, install and configure the permit software that will be used by each department to process development permits. 

 

On December 19, 2000, the City Council approved the second amendment to the agreement with Intergraph.   This amendment increased the amount of the agreement by $100,000 from $5,639,451 to $5,739,451 so that the contractors could complete custom reports for the Building Division that were not part of the original project scope.  In addition, the resolution approved by City Council authorized the City Manager to negotiate and execute change orders with Intergraph in an amount not to exceed $200,000.  Two change orders totaling $121,456 have since been issued raising the total amount of the agreement from $5,739,451 to $5,860,907.

 

Project Overview

 

There are three main components of the IDTS project:   These include:  1) The Permit System, 2) Inspection Request and Result Entry, and; 3) Internet Permits.

 

1)  Permit System

 

The foundation of the IDTS project is the new Permit System.  The System will integrate the workflow of all departments responsible for development review into one seamless process.  This includes the Building Division, Bureau of Fire Prevention, Planning, Public Works Development Services, and the Redevelopment Agency.  Electronic data from legacy computer systems will be converted to the new system so that all historical project information is maintained.  This project component includes integration of the Permit System with the City’s Geographic Information System (GIS) and Document Management Systems (DMS).

 

2)  Inspection Request and Result Entry

 

This IDTS component will integrate inspection requests from Building and Fire customers with the Permit database to ensure that inspectors are scheduled for construction that is ready for inspection.  The new system will also automate the City’s current process for manually assigning and dispatching inspections based on inspector trade and availability.  In addition, system will accommodate the automatic entry of inspection result data through the automatic scanning and indexing of inspection result forms.  Currently, these results are not electronically integrated with the permit approval process.  Upon completion of this project component, the City’s ability to ensure that all inspection requirements are met will be vastly improved.

 

3)  Internet Permits

 

The current on-line permit system, initially implemented in May 2000, will be redesigned and expanded to issue a greater number of permit types.  Due to recent changes in State law, the system can now be redesigned to allow for much wider use by customers.  In addition, on-line query via GIS Map will allow citizens to track projects in their neighborhoods.  Development applicants will be able to monitor the status of their projects through their own personal account.

 

Upon completion of the three core project elements, the major objectives of the IDTS project will be successfully achieved.  At that point, the following non-core functionality will be evaluated and scheduled for implementation.  These include the three following functional components 1) 

an Interactive Voice Response (IVR) system that will allow customers to use touch-tone phones to request inspections and obtain estimated inspection times; 2) Field entry of inspection results by inspectors using a mobile computing device; and 3) Electronic submittal of building plans. A benefit-cost analysis needs to be completed prior to completion of these non-core functions. 

 

ANALYSIS

 

The term of the current IDTS agreement with Intergraph will expire on December 31, 2001.  The contract needs to be extended so that the project can be completed.  A current status of the project is provided below.

 

Project Schedule

 

Permit System: 

 

Implementation of the permit software in the Building Division and Bureau of Fire Prevention was completed in July, 2001.  Planning will implement the software on February 4, 2002.  This date was moved from October 1, 2002 in order to incorporate other major planning initiatives into the work priorities for the Department of Planning, Building & Code Enforcement. 

 

One initiative is the recently completed revision of the Environmental Review Process.  This revision was required to ensure that recent changes in California Environmental Quality Act regulations were incorporated into the design of the new system.  In addition, the Department must implement 72 recommendations from the Housing Production Team designed to streamline the development of housing in San Jose.  The number of General Plan Amendments that needed to be processed was much greater than anticipated.

 

The challenge for the Department is that it has a limited number of experienced Planning project managers that have the process knowledge required to design a permit system that meets the City’s requirements.  These same individuals are also in high demand to complete other major Planning initiatives and oversee major development projects. The need to strategically utilize the limited Planning project managers to complete the planning initiatives required a schedule change to February 4, 2002.  There will be no impact on the project budget as a result of this change.

 

Public Works is scheduled to implement the permit software in March 2002.  The Redevelopment Agency will adopt Planning’s permit system setup once it is implemented.   This will complete the Permit System component of the project.

 

Other Core Project Components: 

 

Detailed specifications for the Inspection Entry and Results component and Internet Permits component of the project are being completed by Intergraph as required in the contract.  Once the specifications are complete, a detailed schedule will be approved.  This is schedule to occur in February.  A  This will occur in mid-February.  Dates for these components will be presented to the City Council at that time.

 

Project Quality

 

The permit software configured in the Building Division and Bureau of Fire prevention has met City requirements and staff expectations.   Planning and Public Works staff is also comfortable with the software’s ability to meet their needs.  The integration between GIS and the Permit system has also been successfully implemented.

 

Contractor Relations

 

The contractor and subcontractors remain committed to the project.  They have been responsive to the City’s requests for changes identified through acceptance testing.  The contractors have also been amenable to the City’s requests to change the order of milestone delivery in order to accommodate the workload of other projects on the organization.

 

Contractor Capability

 

The contractors have demonstrated a high level of technical capability.  They have successfully completed the integration of GIS and Permits.  They are completing the final changes to meet our requirements for Permit System and DMS integration.

 

City Project Team

 

Over 280 days of software training have been provided to Building, Fire, Planning and IT staff as part of the IDTS project.  As a result, the staff assigned to the project have acquired sufficient knowledge to design and support the IDTS system.  This project has brought together a core team of development experts that are very focused on integrating the various development systems and practices into one seamless process.  

 

Project Cost

 

The total project budget is $8,340,000.   The $5.8 million agreement with Intergraph has a balance of $3.8 million.  Payments are tied to acceptance of specific project milestones.  The contract balance is sufficient to complete the project scope as summarized in this memo.

 

As part of the IDTS implementation agreement with Intergraph, the City is recommending that $25,000 be added for consulting services.  These funds will be used by Intergraph to provide advanced training to City technical support staff on how to make detailed modifications to the system configuration.  This may reduce the need for contractor support services in the future.

 

Accomplishments

 

Implementation of the permit software in the Building Division and Bureau of Fire Prevention was completed in July, 2001.  Most of the system integration, data conversion, and system interfaces for the entire project were completed at that time.  The City and its development customers have realized a number of benefits as a result of the implementation.  Project accomplishments to date are summarized below. A complete list of accomplishments is provided as Attachment One to this memo.

 

­One-Stop Counter Initiatives:  Integration of Building and Fire work processes and forms has forged the groundwork for the One-Stop Development Counter.

 

Improved Property Database Management for the City:  Improved accuracy and consistency of GIS data was achieved through the creation of a single GIS data repository.

 

Improved Compliance:   Customers are notified of Fire Department requirements at the permit application intake stage. because Fire requirements have been incorporated into the system.    

 

Improved Access to Project Information:   All information needed to process Building and Fire permits is now maintained on-line.

 

Maintenance, Support & Consulting Services

 

An agreement for software maintenance and support is required to ensure the effective operation of the system.  The City received cost proposals for software maintenance along with the original project bids.  The cost for the software maintenance agreements is $232,000.  This amount has been incorporated into the City’s base budget.  The maintenance agreements essentially provide the City with software upgrades and bug fixes to the standard software.

 

In addition to software maintenance, software support services are also required.  These services cover support for the custom interfaces that integrate the permitting, GIS, and Document management systems.  Support services are also required in situations where the City staff is unable to address the cause of a system problem.  The City has received a proposal from Intergraph to provide coordinated support services at a cost of $143,000.  It is the City’s desire to have one overall agreement for maintenance and support with Intergraph at a total cost of $375,000.  The City may need to have a separate agreement with the permit software vendor for maintenance.  The cost would not exceed the total amount of $375,000 in the event that there are two agreements instead of one.  The first year of support services will funded from IDTS maintenance funds that were rebudgeted from last fiscal year.  A proposal for future funding of support costs will need to be addressed through the annual budget process.  As mentioned, maintenance costs are already incorporated into the base budget.

 

PUBLIC OUTREACH

 

Not Applicable.

 

COORDINATION

 

This memorandum has been coordinated with the Departments of Finance, Planning, Building and Code Enforcement, and Information Technology, the City Attorney’s Office and the Manager’s Office.

 

COST IMPLICATIONS

 

There is no cost associated with extending the Intergraph contract for implementation of the IDTS project.   The Maintenance, Support and Consulting Services Agreement will be funded from the General Fund (001) from monies currently allocated to the Department of Information Technology’s General Fund appropriation.

 

BUDGET REFERENCE

 

Fund:  General Fund – (001) Amount: $375,000.   Budget Document: 2001-2002 Adopted Operating Budget, Page 325

 

 

Del D. Borgsdorf

City Manager  


 

Attachment One

IDTS Accomplishments

 

­One-Stop Counter Initiatives:

 

Integration of Building and Fire Plan Check - Using the new system, staff creates a digital project file that allows Building and Fire staff to simultaneously view the status of work performed by either group to ensure a consistent interpretation of Building Codes. 

 

Created Universal Invoice and Receipt Documents – Building and Fire are now utilizing a standard invoice and receipt.  This is a prerequisite for a One-stop Development Counter.

 

Centralized Fee Collection - As a precursor to the one-stop permit center, the permit system is being set up so that fees assessed by multiple departments can be collected at any location.  Building has reduced customer trips by collecting fees for Fire that previously had to be collected at 4 N. 2nd Street.

 

Improved Property Database Management for the City: 

 

Established a New, City-wide GIS Framework – The Oracle Spatial database created for storing GIS data necessary for IDTS will become the central repository for storing all GIS data.   All Departments will be able to access one, consistent data source regardless of the GIS software used by the end-user. 

 

Created A Single, Property Database for the City – IDTS has created a database that will ultimately be used by all Departments that need to access property by address or Assessor’s Parcel Number (APN).  This will improve the accuracy of data currently being used and reduce system support requirements.

 

Reduced GIS Research and Data Entry – Over 29 GIS files were cleansed and implemented into the GIS database.   This has eliminated the need for manual research and data-entry on permit applications.

 

Consolidated/Eliminated Three Building databases (ABPIS, PG&E, CRIS) – This has reduced maintenance, consolidated data, and improved access to information.

 

Improved Compliance:

 

Improved Customer Notification of Fire Inspection Requirements - By implementing one job card for use by both Building and Fire Inspectors, development customers are now notified up-front that they may need to obtain a Fire Inspection.   Prior to IDTS, customers often did not know they needed a Fire Inspection until construction was complete.

 

Improved Ability Track Projects By Applicant – The system allows staff the ability to flag an applicant that has code enforcement or payment issues so that staff are notified any time a person with unresolved issues applies for a permit.

 

Addressed Auditor Issues – The new Permit System was configured to address four outstanding City Auditor Recommendations pertaining to permit fee collection consistency that could not be accommodated by the prior system.

 

Improved Access to Project Information

 

Automated Project File – All information needed to process Building and Fire permits is now on-line.  This allows for tracking and reporting of all information associated for a project.  The capture of additional project information vastly improves the City’s ability to measure workload data.