THIRD
AMENDMENT TO AGREEMENT FOR
INTEGRATED DEVELOPMENT TRACKING SYSTEM
BETWEEN THE CITY OF SAN JOSE
AND INTERGRAPH CORPORATION
This Third Amendment to Agreement is made and
entered into as of this day of December, 2001, by and between the
City of San José, a municipal corporation (hereinafter "City"), and
Intergraph Corporation, a Delaware corporation (hereinafter "Contractor”).
RECITALS
WHEREAS, on March 31,
1999, City and Contractor entered into an agreement entitled “AGREEMENT FOR
INTEGRATED DEVELOPMENT TRACKING SYSTEM BETWEEN THE CITY OF SAN JOSÉ AND
INTERGRAPH CORPORATION. (“Agreement”); and
WHEREAS, on December 2, 1999, City and Contractor entered into a First Amendment to the Agreement to include a subcontract with Synertech/CSDS for permit issuance software and related integration services, and extending the term of the Agreement to September 30, 2001, and increasing the total compensation to an amount not to exceed $5,639,451; and
WHEREAS, on December 19, 2000, City and Contractor entered into a Second Amendment to the Agreement to create custom reports for the Building Division and increase the total compensation to an amount not to exceed $5,739,451; and
WHEREAS, on July 11,
2001, City and Contractor entered into Change Order No. 1, which among other
things resulted in Third Revised Exhibit B; and
WHEREAS, on September
25, 2001, City and Contractor entered into Change Order No. 2, which among
other things resulted in Fourth Revised Exhibit B; and
WHEREAS, City now desires to amend the Agreement to
include $25,000 in additional consulting and training services and to extend
the term of the Agreement.
NOW,
THEREFORE, the City and Contractor agree to amend the agreement as follows:
SECTION 1. Section 1 of the Agreement is amended to read as follows:
The
documents forming the entire Agreement between City and Contractor shall
consist of this Agreement including:
EXHIBIT A - Scope of Services and Software
Licenses
SCHEDULE A-1 – Intergraph End User Limited
Warranty (Domestic)
SCHEDULE A-2 – Software Licenses
Geomedia Shrink Wrap Software License
CSDC End User License Agreement – AMANDA
SYNERTECH End User License Agreement –
Net.Connect
Addendum I to Revised Exhibit A
Addendum II to Revised Exhibit A
EXHIBIT B – Installation and Payment Schedule (as Revised)
EXHIBIT C – Insurance Requirements
EXHIBIT D – Ownership of Work Product
EXHIBIT E – Functional Requirements List
In the
event any discrepancies or inconsistencies between the provisions of this
Agreement and any of the above-referenced documents arise, the provisions of
this Agreement will prevail.
This
Agreement and the Exhibits set forth above and the revisions to each of them as
contained in the Amendments referred to above, contain all of the agreements,
representations and understandings of the parties hereto, and supersede and
replace any previous understandings, commitments, or agreements, whether oral
or written.
SECTION 2. Section 3 of the Agreement is amended to read as follows:
The term of this Agreement shall be from January 26, 1999 to December
31, 2002.
Time is of the essence in this Agreement.
SECTION 3. Exhibit A of the Agreement is amended by adding the services set forth in the Attached Addendum II to Revised Exhibit A.
SECTION 4. Exhibit B of the Agreement is amended to read as set forth in the Attached Fifth Revised Exhibit B.
SECTION 5. All of the terms and conditions of the Agreement not modified by this Third Amendment shall remain in full force and effect.
WITNESS THE EXECUTION HEREOF on the day and year first hereinabove written.
|
APPROVED AS TO FORM: _____________________ Brian Doyle Senior Deputy City Attorney |
City of San José a municipal corporation By_____________________________ Name: Title: |
|
|
Intergraph Corporation a Delaware corporation By ____________________________ Name: Title: |
ADDENDUM II TO
REVISED EXHIBIT A
CITY OF SAN JOSE IDTS
PROJECT
SCOPE OF SERVICES AND SOFTWARE LICENSES
CONSULTANT shall provide training on the database structure which will provide City staff with the ability to make changes to AMANDA folder configuration. Tasks performed shall be directed and approved by the City’s Designated Project Contact. Specific training tasks are listed below.
Advanced Admin Training
– Provide PBCE & IT staff with in-depth training on AMANDA table structure
sot that IT staff can make fixes/enhancements to the program.
Report Building Training
– Train IT and other staff on how to produce custom reports
Word Merge Document
Training – Train IT and other staff on how to create Word Merge documents
The cost for these services (including travel and expenses) shall not exceed $25,000. Services will be billed on a time and materials basis at the rate of $1,600 per day (200 per hour). All training and cost estimates for training shall be pre-approved by the City’s Project
FIFTH REVISED EXHIBIT B
INSTALLATION AND PAYMENT SCHEDULE
The maximum amount payable for all products and Contractor services provided under this Agreement shall not exceed Five Million Seven Hundred Thirty-nine Thousand Four Hundred Fifty-one Dollars ($5,739,451).
Progress payments shall be made to Contractor by City net thirty (30) days following acceptance of designated milestones below. The cumulative amount of progress payments to Contractor shall be based upon completed phases, and shall not exceed ninety percent (90%) of the amount stated above other than for Phase 0 vendor selection and delivery of Software products. The final payment of not less than ten percent (10%) of the above amount applicable to Contractor’s services (excluding Phase 0) shall be paid to Contractor within forty-five (45) days following City’s final acceptance of the System.
Work shall commence immediately upon execution of the agreement. The timeline entries indicate approximate dates. If the target date falls on a weekend or holiday the target date will be moved to the close of business on the next business day.
The following schedule incorporates the item mentioned in this 3rd Amendment.
|
|
|
MS#
|
Total,
|
Less Holdback,
|
|
|
TOTAL PROJECT |
|
5,885,907 |
5,885,907 |
|
|
|
|
|
|
|
Phase 0 – Select Permitting Vendor |
|
45,000 |
45,000 |
|
|
Complete |
(a) Issue RFP |
IG0-1 |
20,000 |
20,000 |
|
|
(b) Select vendor |
IG0-2 |
25,000 |
25,000 |
|
|
|
|
|
|
|
Phase 1 – Software
Infrastructure |
|
1,741,630 |
1,708,739 |
|
|
|
|
|
|
|
|
Complete |
Sign Contract |
IG0-3 |
40,000 |
36,000 |
|
|
Adjustment for additional RFP costs |
IG0-4 |
50,000 |
50,000 |
|
|
(a) Conduct a formal Project Kickoff
meeting with the City and each of the Subcontractors. |
MS01 |
50,911 |
45,820 |
|
|
(b) Evaluate changes to following phases
as a result of selecting Synertech as the permit vendor |
IG-05 |
58,328 |
52,495 |
|
|
(c) Setup all required IDTS servers as
needed with supplied software, (excludes operating systems, e-mail systems,
SNS Site Acceptance Tests and hardware); |
IG-06 |
39,952 |
35,957 |
|
|
(d) Ensure the network suitability for the
applications, |
IG-07 |
36,250 |
32,625 |
|
|
(e) Deliver and load all the GIS and
Imaging interface software to City: |
IG-08 |
51,730 |
46,557 |
|
|
|
|
|
|
|
|
Deliver Software
Products – Software Subtotal
|
|
1,362,714 |
1,362,714 |
|
Complete |
1. Intergraph GeoMedia |
IG-09 |
255,000 |
255,000 |
|
Complete |
2. Intergraph GeoMedia Professional |
IG-10 |
159,269 |
159,269 |
|
Complete |
3. Intergraph GeoMedia Web Map |
IG-11 |
76,500 |
76,500 |
|
|
4. SpatialENTERPRISE GIS Security System |
SE-01 |
10,800 |
10,800 |
|
|
5. seGIS Desktop |
SE-02 |
120,000 |
120,000 |
|
|
5a. Modify SpatialENTERPRISE to utilize
City’s CHRIS database model |
SE-03 |
39,000 |
39,000 |
|
|
7. AMANDA software and Licenses (desktop) |
MS03-1 |
456,000 |
456,000 |
|
|
8. Net.Connect software (for AMANDA) |
MS03-2 |
60,000 |
60,000 |
|
|
9. IVR Software and specialized equipment |
MS03-3 |
90,000 |
90,000 |
|
|
10. Remote Inspection option |
MS03-4 |
96,000 |
96,000 |
|
|
11. Maintenance |
|
|
|
|
|
By agreement with the City, the original
IDM software items listed in the table will be obtained by the City from
FileNET or their business partners.
SE will modify their software to handle CHRIS database structure |
|
145 |
145 |
|
|
Move Item 6 and 6.a to Phase 2 |
|
|
|
|
|
(f) Load GIS and Imaging software to end
user seats as needed. |
|
|
|
|
|
(g) Load Permitting software to user seats
as needed |
|
|
|
|
|
(h) During this phase, Intergraph will
review, and create a detailed Project Plan for, all project phases. This plan
will: |
MS02 |
51,746 |
46,571 |
|
|
1. Establish project review meeting formats and schedules, |
|
|
|
|
|
2. Establish lines of communication, |
|
|
|
|
|
3. Identify interfaces to be built, |
|
|
|
|
|
4. Provide low-level detail of all activities to be performed by each
Intergraph Team member and the City’s IDTS Project Team |
|
|
|
|
|
5. Estimate the City’s committed resource requirements in each phase |
|
|
|
|
|
6. Document software versions, |
|
|
|
|
|
7. Formalize roles and responsibilities, |
|
|
|
|
|
8. Identify all data to be converted, |
|
|
|
|
|
9. Identify risks to be mitigated, |
|
|
|
|
|
10. Update the list of all project deliverables. |
|
|
|
|
|
11. Update the project schedule for the following phases |
|
|
|
|
|
|
|
|
|
|
Phase 2, Permit Issuance Software |
|
2,448,931 |
2,217,912 |
|
|
|
|
|
|
|
|
|
Building and Fire
|
|
1,425,945 |
1,289,486 |
|
|
(a) Initial Installation |
MS03 |
110,928 |
99,835 |
|
|
(b) Conduct a formal Business Fit Analysis |
MS04 |
128,049 |
115,244 |
|
|
(c) Conversion Analysis and Plan |
MS05 |
96,335
|
86,701
|
|
|
(d) Requirements study for
integration |
MS06 |
135,391
|
121,852
|
|
|
(e) Detailed Project Plan |
MS07 |
12,462
|
11,216
|
|
|
(f) System administration training |
MS09 |
20,309
|
18,278
|
|
|
(g) Create first half of departments folders 1-6 CCF# A5, CCF# A8, CCF# FE8 |
MS13 MS13a |
30,771 11,700 |
27,694 10,530 |
|
|
(h) Forms x4 |
MS15 |
29,848 |
26,863 |
|
|
(i) Create second half of the folders 7-12
CCF# F11 |
MS19 MS19a |
30,771 3,100
|
27,694 2,790
|
|
|
(j) Data Conversion |
MS11 |
135,644
|
122,080
|
|
|
(k) Interfaces |
MS17 |
101,544 |
91,390 |
|
|
(l) SITUS and GIS
integration |
MS08 |
67,696 |
60,926 |
|
|
(m) Imaging and MS Office integration |
MS12 |
40,617 |
36,555 |
|
|
(m)-1 SEI OLE link from permit s/w |
SE-04 |
13,680 |
12,312 |
|
|
(m)-1 SEI OLE link to permit s/w |
SE-05 |
13,680 |
12,312 |
|
|
(n) MAPI and FileNET integration |
MS18 |
67,696 |
60,926 |
|
|
(o) User Training |
MS22 |
108,313 |
97,482 |
|
|
(p)
Performance test |
MS29 |
|
|
|
|
(q) Production system – permit issuance |
MS31 |
27,078 |
24,370 |
|
|
(r) Inquiry for remaining departments before their
implementation is done |
MS36/7 |
120,028 |
108,025 |
|
|
(s) Additional Reports (t) Word-Merge Documents (u) 1 week of additional resources (v) Travel expenses for 1 week of additional resources *Additional Reports will be developed on a time and
materials basis, up to a total not-to-exceed amount of $50,000 (which will
include any travel expenses). The charge will be $1,791.20 per day (for an 8
hour day). Travel charges will require pre-approval by the city. Weekly
status reports will be required. The city will be invoiced on a monthly basis
for all days expended during that month. |
MS74 MS75MS76 MS79 |
50,000* 58,950 8,956 2,400 |
50,000* 53,055 8,956 2,400 |
|
|
Planning
and Redevelopment |
|
547,096 |
500,125 |
|
|
(a) Initial Installation |
MS10 |
26,001 |
23,401 |
|
|
(b) Conduct a formal Business Fit Analysis |
MS20 |
91,389 |
82,250 |
|
|
(c) Conversion Analysis and Plan |
MS14 |
34,428 |
30,985 |
|
|
(d) Requirements study for
integration |
MS16 |
20,309 |
18,278 |
|
|
(e) Detailed Project Plan |
MS21 |
53,871 |
48,483 |
|
|
(f) System administration training |
MS24 |
20,309 |
18,278 |
|
|
(g)
(Intentionally Omitted) |
|
|
|
|
|
(h) Create 8
folders and 3 Forms |
MS28 |
67,696 |
60,926 |
|
|
(i) (Intentionally
omitted) |
|
|
|
|
|
(j) Data Conversion |
MS23 |
50,772 |
45,695 |
|
|
(k) Interfaces |
MS26 |
23,693 |
21,324 |
|
|
(l) (Intentionally
omitted) |
|
|
|
|
|
(m) (Intentionally
omitted) |
|
|
|
|
|
(n) Integration with other systems |
MS32 |
23,693 |
21,324 |
|
|
(o) User Training |
MS35 |
30,463 |
27,417 |
|
|
(p)
Performance test |
MS40 |
|
|
|
|
(q) Production system – permit issuance |
MS41 |
27,078 |
24,370 |
|
|
(r) 7 weeks of additional resources |
MS77 |
62,694 |
62,694 |
|
|
(s) Travel expenses for 7 weeks of additional
resources |
MS78 |
14,700 |
14,700 |
|
|
Public
Works |
|
475,891 |
428,301 |
|
|
(a) Initial Installation |
MS25 |
26,001 |
23,401 |
|
|
(b) Conduct a formal Business Fit Analysis |
MS33 |
91,389 |
82,250 |
|
|
(c) Conversion Analysis and Plan |
MS27 |
27,078 |
24,370 |
|
|
(d) Requirements study for
integration |
MS30 |
20,309 |
18,278 |
|
|
(e) Detailed Project Plan |
MS34 |
8,308 |
7,477 |
|
|
(f) System administration training |
MS39 |
20,309 |
18,278 |
|
|
(g) (Intentionally
omitted) |
|
|
|
|
|
(h) Create 8
folders and 3 forms |
MS44 |
67,696 |
60,926 |
|
|
(i) (Intentionally
omitted) |
|
|
|
|
|
(j) Data Conversion |
MS38 |
50,772 |
45,695 |