Subject: TUERS-CAPITOL GOLF COURSE MITIGATION
PROJECT SUPPLEMENTAL MEMO
COUNCIL DISTRICT: 7
SNI AREA: N/A
REASON
FOR SUPPLEMENTAL MEMO
To report on the bid results obtained after bids were opened on November 29, 2001.
RECOMMENDATION
Report on bids and award of contract for the Tuers-Capitol Golf Course Mitigation Project to the low bidder, Ecological Concerns Incorporated dba Central Coast Wilds, to include the base bid and Add Alternate No. 1 in an amount not to exceed $284,598.13, and approval of a contingency in the amount of $29,000. CEQA: EIR.
BACKGROUND
A memorandum dated November 26, 2001 was forwarded to the City Council for the December 18, 2001 Council meeting. The purpose of this supplemental memorandum is to provide additional information obtained after the bid opening.
The items in the base bid scope of work include the development of four acres of riparian vegetation consisting of site clearing and preparation, the installation of an irrigation system, the planting of 1,500 native trees and shrubs and a 335 calendar day maintenance period.
In addition to the base bid scope of work, there was one Add Alternate bid item which includes the maintenance of 22 acres of grassland within the setback/buffer adjacent to the riparian corridor along the Coyote Creek for 335 calendar days.
Bids were received on November 29, 2001 with the following results:
|
Contractor |
Base
Bid |
Add Alternate Total |
Total
Bid |
Variance Amount |
Over/ (Under) Percent |
|
Lone Star Landscape (San Martin) |
$655,000.00 |
$160,000.00 |
$815,000.00 |
$229,160.00 |
39% |
|
Engineer’s Estimate |
524,840.00 |
60,000.00 |
585,840.00 |
----- |
----- |
|
Karleskint-Crum, Inc (San Luis Obispo) |
492,860.00 |
68,600.00 |
561,460.00 |
- 24,380.00 |
(4) |
|
Watkin & Bourtolusssi, Inc. (San Rafael) |
327,000.00 |
65,000.00 |
392,000.00 |
- 193,840.00 |
(33) |
|
Ecological Concerns Inc. DBA Central Coast Wilds (Santa Cruz) |
233,156.51 |
51,441.61 |
284,598.13 |
301,241.87 |
(51) |
The low bid submitted by Ecological Concerns, Inc., in the
amount of $284,598.13, is 51 percent below the Engineer's Estimate. A review of the individual bid items
revealed that the contractor’s prices for many of the construction items were
below the Engineer’s Estimate. The low bid contractor
specializes exclusively in native plant propagation and native habitat
construction. The low bid price
reflects this area of focus and familiarity with such installations. Staff has discussed the low bid with Ecological
Concerns, Inc., who has indicated that he interpreted
the plans correctly and can successfully complete the work within the bid
amount. There are no clerical errors.
The Engineer’s Estimate was developed from a standard landscape installation perspective. The bidding process was open to general landscape contractors. The variance in the bid results is indicative of that broader perspective. The low bid is consistent with the specific focus of a particular contractor extremely familiar with native habitat installations, that is the objective of the proposed project.
Staff recommends awarding a contract to the low bidder.
A contingency reserve budget in the amount of $29,000 is requested for any unforeseen conditions that may arise during construction of this project.
This
proposed project was listed on the City’s Internet bid line and advertised in
the San José Mercury News and San José Post Record. Bid packages for all Department of Public
Works construction projects are routinely provided to a standard list of
various contractor organizations, builder’s exchanges and disadvantaged
business organizations, including United Minority Business Enterprises and the
San José Minority Business Development Center.
This proposed project was coordinated with the City Manager’s Budget Office; Offices of the City Attorney, Risk Manager and Equality Assurance; and the Departments of Planning, Building and Code Enforcement; Conventions, Arts and Entertainment; Environmental Services; General Services, and Parks, Recreation, and Neighborhood Services.
1. COST OF RECOMMENDATION: $284,598.13
2. COST
OF PROJECT:
|
Construction |
$284,600 |
|
|
Design & Construction Management |
32,000 |
* |
|
Contingency |
29,000 |
|
|
TOTAL |
$345,600 |
|
|
|
|
|
* Design services were accomplished as part of the Tuers-Capitol Golf Course consultant agreement.
3. SOURCE OF FUNDING: 001 - General Fund
4. ESTIMATED START DATE OF CONSTRUCTION: January 2002
5. ESTIMATED COMPLETION DATE OF CONSTRUCTION: March 2002
BUDGET
REFERENCE
|
Fund: |
001 |
|
Appn: |
6874 |
|
RC: |
117123 |
|
Amount: |
$1,879,000 |
|
Budget Document: |
2001-2002 Appropriation Ordinance, Section 2.26, item 7 (h) |
The City of San José Nondiscrimination Requirements are included in this project as required by Chapter 4.08 of the San José Municipal Code.
EIR dated 12/21/99, pp 98-03-064
RAJEEV BATRA