SUBJECT: AMENDMENT TO THE MASTER AGREEMENTS WITH MOORE IACOFANO GOLTSMAN, INC., THE BEALS GROUP, INC., COTTONG & TANIGUCHI LANDSCAPE ARCHITECTS AND MPA DESIGN FOR VARIOUS PARK AND RECREATION PROJECTS.
COUNCIL DISTRICT: Citywide
SNI AREA: N/A
RECOMMENDATION
Approval
of first amendments to four master agreements for design consultant services
with four landscape architecture firms for Various Park and Recreation
Projects, increasing the maximum amount of compensation as follows:
|
Consultant |
Proposed
Maximum Compensation |
|
Moore Iacofano Goltsman, Inc. $500,000 $800,000 300,000 800,00 500,000 |
$800,000 |
|
the beals group, inc. |
800,000 |
|
Cottong & Taniguchi |
600,000 |
|
MPA Design |
500,000 |
BACKGROUND
A total of 69 play area and restroom renovation projects were identified in the Parks Bond Measure that passed in November 2000. The first nine projects were begun under separate consultant agreements or service orders in FY 2000-01. Seven of these nine projects have construction contracts awarded and are currently under construction or will soon start construction. The remaining two projects are under design.
In June 2001, the City entered into a master agreement with five landscape architect consultants, Moore Iacofano Goltsman, Inc., the beals group, inc., Cottong & Taniguchi, MPA Design and Tom Richman & Associates, Inc., for design services for 36 play area and restroom renovation projects under the Parks Bond Measure. To date, design work for 20 of the 36 projects has been authorized under these master agreements, and the other 16 projects are either under negotiation with the consultants or are scheduled to begin in January 2002.
The remaining 24 play area and restroom renovation projects which were not included under the five original master agreements are scheduled to begin in the later half of FY 2001-02 and in FY 2002-03.
The five firms cited above were selected through a competitive process involving both City and external professional evaluators. One firm, Tom Richman & Associates, Inc., has limited capacity for additional work at this time and is therefore not recommended for an increase in contracting authority.
In order to proceed with the remaining 24 play area and restroom renovation projects, it will be necessary to increase the maximum compensation amount in the existing master agreements. Staff recommends increasing the maximum compensation amount in four of the five master agreements as follows so that scheduling and work for these 24 projects may begin without delay:
|
Consultant |
Current
Maximum Compensation |
Amount
of Increase |
Proposed Not-to-Exceed Amount |
|
Moore Iacofano Goltsman, Inc. $500,000 $800,000 300,000 800,00 500,000 |
$500,000 |
$300,000 |
$800,000 |
|
the beals group, inc. |
300,000 |
500,000 |
800,000 |
|
Cottong & Taniguchi |
300,000 |
300,000 |
600,000 |
|
MPA Design |
300,000 |
200,000 |
500,000 |
|
TOTAL AMOUNT OF INCREASE |
$1,400,000 |
$1,300,000 |
$2,700,000 |
PUBLIC
OUTREACH
Not applicable.
This master agreement was coordinated with the Offices of the City Attorney and Risk Manager; and the Department of Parks, Recreation and Neighborhood Services.
1. COST OF RECOMMENDATION: $1,300,000
2. COST OF PROJECT:
Master Agreement $1,400,000 *
Amendment 1,300,000
Administration 80,000
TOTAL $2,780,000
* Master Agreement funds encumbered in FY 2000-01
3. SOURCE OF FUNDING: 471 – Parks & Recreation Bond Fund
4. START DATE OF AGREEMENT: June 5, 2001
5. ESTIMATED COMPLETION DATE OF AGREEMENT: July 31, 2003
BUDGET
REFERENCE
Fund: |
471 |
|
APPN: |
6927 |
RC:
|
119088
|
Amount:
|
$57,000
|
Budget Document: |
2001-02 Appropriation Ordinance, Section 31.01 |
Fund: |
471 |
|
APPN: |
6932 |
RC:
|
119168
|
Amount:
|
$95,000
|
Budget Document: |
2001-02 Appropriation Ordinance, Section 31.01 |
Fund: |
471 |
|
APPN: |
6818 |
RC:
|
113988
|
Amount:
|
$144,000
|
Budget Document: |
2001-02 Appropriation Ordinance, Section 31.01 |
Fund: |
471 |
|
APPN: |
6919 |
RC:
|
119028
|
Amount:
|
$56,000
|
Budget Document: |
2001-02 Appropriation Ordinance, Section 31.01 |
Fund: |
471 |
|
APPN: |
6925 |
RC:
|
119068
|
Amount:
|
$108,000
|
Budget Document: |
2001-02 Appropriation Ordinance, Section 31.01 |
Fund: |
471 |
|
APPN: |
6918 |
RC:
|
119018
|
Amount:
|
$150,000
|
Budget Document: |
2001-02 Appropriation Ordinance, Section 31.01 |
Fund: |
471 |
|
APPN: |
6940 |
RC:
|
119228
|
Amount:
|
$108,000
|
Budget Document: |
2001-02 Appropriation Ordinance, Section 31.01 |
Fund: |
471 |
|
APPN: |
6835 |
RC:
|
119118
|
Amount:
|
$51,000
|
Budget Document: |
2001-02 Appropriation Ordinance, Section 31.01 |
Fund: |
471 |
|
APPN: |
6937 |
RC:
|
119208
|
Amount:
|
$56,000
|
Budget Document: |
2001-02 Appropriation Ordinance, Section 31.01 |
Fund: |
471 |
|
APPN: |
6526 |
RC:
|
118938
|
Amount:
|
$60,000
|
Budget Document: |
2001-02 Appropriation Ordinance, Section 31.01 |
Fund: |
471 |
|
APPN: |
6933 |
RC:
|
119178
|
Amount:
|
$97,000
|
Budget Document: |
2001-02 Appropriation Ordinance, Section 31.01 |
Fund: |
471 |
|
APPN: |
6923 |
RC:
|
119058
|
Amount:
|
$108,000
|
Budget Document: |
2001-02 Appropriation Ordinance, Section 31.01 |
Fund: |
471 |
|
APPN: |
6916 |
RC:
|
118998
|
Amount:
|
$61,000
|
Budget Document: |
2001-02 Appropriation Ordinance, Section 31.01 |
Fund: |
471 |
|
APPN: |
6926 |
RC:
|
119078
|
Amount:
|
$108,000
|
Budget Document: |
2001-02 Appropriation Ordinance, Section 31.01 |
Fund: |
471 |
|
APPN: |
6930 |
RC:
|
119138
|
Amount:
|
$56,000
|
Budget Document: |
2001-02 Appropriation Ordinance, Section 31.01 |
RAJEEV BATRA
Acting Director, Public Works Department