Subject:  EVERGREEN BRANCH LIBRARY

 

Council District: 8

 

RECOMMENDATION

 

Approval of an agreement with STUDIOS Architecture for consultant services including project design, preparation of construction documents, and construction administration services for the Evergreen Branch Library Project, for a term from June 1, 2003 to September, 2006, in the amount of $810,000.

 

 

BACKGROUND

 

The Evergreen Branch Library is the seventh library to be initiated under the Branch Facility Master Plan.  The branch will be located at the existing branch location on Aborn Road.

 

Public Works and Library Department staff conducted the architectural consultant interview and selection process per the Department of Public Works Consultant Selection Procedure, and recommend the retention of STUDIOS Architecture to provide the design for this project.

 

The scope of work will include program review, conceptual design, schematic design, design development, preparation of construction documents, bidding and award, construction administration, preparation and compiling of record documents and project closeout. The conceptual design and schematic design scope of work will include community outreach. Construction is estimated to begin in Fall 2004 with completion in Spring 2006.

 

 

ANALYSIS

 

Public Works, the Library and other panel members including library volunteers, community representatives and related professionals interviewed five firms, and as a result, STUDIOS Architecture was selected for the Evergreen Branch Library. San José architectural firms have been selected for five of the first eight projects of the Branch Library Bond Program.

 

 

Library and Public Works staff believe $810,000 is a reasonable fee for this work. The amount noted includes a reserved additional service amount and reimbursables. The schedule requires the architect to start work in early June.

 

An innovative delivery method will be utilized for this project, sharing portions of the consultant’s professional workload with available City staff.  City staff will provide integrated professional civil and landscape design services, combining available staff resources with suitable expertise, along with the depth and staffing flexibility of the outside consultant.  There are no remaining available City staff resources with appropriate qualifications suitable for additional project integration.  City staff will continue to provide an appropriate level of service for project facilitation, coordination and plan review.

 

An architect who is LEED Certified will be included on the Design Team for this facility.  The facility will be designed in accordance with the Green Building Policy.

 

 

PUBLIC OUTREACH

 

The Request for Qualifications was published in the San José Mercury News and in various others Bay Area newspapers. A programming community meeting was held on March 26, 2003. Future project meetings will be advertised at various branch library locations for conceptual design and the schematic design processes.

 

 

COORDINATION

 

This agreement and memo been coordinated with the Departments of Library, Planning, Building and Code Enforcement, and Finance, the City Manager’s Budget Office and City Attorney’s Office.

 

 

COST IMPLICATIONS

 

1.

AMOUNT  OF RECOMMENDATION:

 

 $810,000

 

 

 

2.

COST OF PROJECT:

 

 

 

Project Delivery

1,929,000

 

 

Construction (Allocated)

6,750,000

 

 

Construction Contingency

675,000

 

 

TOTAL

 $9,354,000

 

 

 

 

 

3.

SOURCE OF FUNDING:

472 - Branch Libraries Bond Projects Fund

 

 

 

 

 

4.

OPERATING COST:   This project is consistent with the Council-approved Budget Strategy Economic Recovery section in that it will spur construction spending in our local economy.  This project will have minimal impact on the operating budget.  It is estimated the General Services Department will have an ongoing maintenance cost increase of $15,000 annually once occupancy is taken.  This cost will be offset by a reduction in Library operating costs of approximately $49,000 per year. 

 

 

BUDGET REFERENCE

 

 

Fund

#

 

Appn.

#

 

Appn. Name

 

RC #

 

Total

Appn.

 

Amt. For Contract

 

Adopted Budget Page

 

Last Budget Action

(Date, Ord. No.)

 

472

4540

Evergreen Branch

124973

$ 1,233,000

$810,000

Page 185

06/18/02, Ord. No. 26674

 

 

 

 

 

 

 

 

 

 

CEQA

 

Exempt, PP03-04-132.

 

 

KATY ALLEN

Director, Public Works Department