In order to maintain the schedule for this project, staff requests Council approval at its May 20, 2003 meeting.
a) Increase
contingency budget authorization by $51,000 from $66,000 to $117,000.
b) Adoption of
the following Appropriation Ordinance amendments in the Park Yards Fund:
1) Increase the
Kelley Park Service Yard Renovation Project by $107,000
2) Decrease the Ending
Fund Balance by $107,000
c) Adoption of a resolution authorizing the City Manager to negotiate and execute a continuation agreement with Garcia Teague Architecture + Interiors for the Kelley Park Service Yard Project, to expand the scope of services, increase the compensation by an amount not to exceed $26,000, and extend the term of the agreement from April 30, 2003 to November 30, 2003.
BACKGROUND
Kelley Park is a 172-acre park site located at the
southeast intersection of Senter and Story Roads The service yard is located in
the northwest corner of Kelley Park (map attached). On August 7, 2002, Council
approved a contract for the Kelley Park Service Yard Project. This project
improves the service yard, including replacement of the existing structure with
a new 3,360 square foot metal structure building with a large storage and
equipment area, roll-up doors, restrooms and shower facility, office, chemical
storage, emergency shower and eye-wash station and building alarm. It also
includes site improvements including material holding bins, vehicle and
equipment wash areas, new paved parking lot and electrical upgrade.
In Fiscal Year 2001-02, funds were appropriated in the
Parks Capital Improvement Program Budget for the development of plans to
replace the 30-year old facility. The intent for the project was to
construct a new pre-engineered metal building tailored to meet the function of
the facility within the project budget.
On September 18, 2001, the City Manager approved a minor consultant
agreement (compensation under $100,000) with Garcia Teague Architecture +
Interiors, Inc. to provide design services for the project.
Funds for construction of the project were appropriated in
Fiscal Year 2002-03 and construction for the Kelley Park Service Yard Project
began in November 2002 with completion estimated in June 2003.
During the construction of the project, the City had to address a number of existing and unforeseen conditions that were not reflected in the plans and specifications for the project. These included integration of electrical services and adjustments to the diesel fueling operation for Happy Hollow. To date, Public Works has approved change orders amounting to $46,129. Some additional changes orders are anticipated to be necessary to complete the project. Staff recommends increasing the project budget by $107,000, including an increase to the construction contingency authorization of $51,000 and an increase in the maximum compensation for the consultant of $26,000.
The work involved in the construction of this project has been greater than originally anticipated, but it is still within the normal range of construction and construction management costs for the project. With the approval of this $107,000, the projected breakdown for project costs will be approximately 67 percent for construction and 33 percent for project delivery costs.
This agreement and memo have been coordinated with the Departments of Parks, Recreation and Neighborhood Services, General Services, Finance and Planning, Building and Code Enforcement and the City Attorney’s Office.
Not applicable.
1. AMOUNT OF RECOMMENDATION: $107,000
2. COST OF PROJECT:
|
Project Delivery |
$292,000* |
|
|
Construction |
657,750* |
|
|
Contingency |
66,000* |
|
|
|
Sub total: |
$ 1,015,750 |
|
|
|
|
|
Continuation Agreement |
26,000 |
|
|
Construction Change Orders |
51,000 |
|
|
Additional construction management |
30,000 |
|
|
Sub
total |
107,000 |
|
|
Total |
$1,122,750 |
|
*A total of $192,338 was expended/encumbered during
2000-2001and 2001-2002.
3.
SOURCE OF FUNDING: 398 –
Park Yards Fund
391
– Construction
and Conveyance Fund – City-wide
4.
FISCAL IMPACT: This project
is consistent with the Council-approved Budget Strategy Economic Recovery
section in that it will spur construction spending in our local economy.
|
Fund # |
Appn # |
Appn. Name |
RC# |
Total Appn. |
Amt. For Contract |
Last Budget Action (Date, Ord. No.) |
|
398 |
4499 |
Kelley Park Maintenance Yard Renovation |
100744 |
$815,000 |
$815,000 |
8/27/02-Ordinance Number 26722 |
|
391 |
6551 |
Kelley Park Maintenance Area Improvements |
100743 |
$8,000 |
$8,000 |
10/15/02-Ordinance Number 26755 |
CEQA
Mitigated Negative Declaration - PP01-10-186.
KATY ALLEN LARRY D. LISENBEE
Director, Public Works Department Budget Director