To: HONORABLE MAYOR AND From: Katy Allen
CITY COUNCIL Larry D. Lisenbee
Subject: MUNICIPAL ROSE GARDEN Date: 05-13-03
RENOVATION PROJECT
Council District:
6
To provide additional information after bids were opened.
1. Report on bids and award of contract for the Municipal Rose Garden Renovation Project to the lowest responsive bidder, Robert A. Bothman, Inc., to include the base bid and Add Alternate Nos. 1 and 2 in the amount of $1,511,000, and approval of a contingency in the amount of $151,000.
2. Adoption of the following Appropriation
Ordinance Amendments in the City-Wide Construction and Conveyance Tax Fund:
a. Establish the Municipal Rose Garden
Renovation Project for $210,000.
b.
Decrease
the Ending Fund Balance by $210,000.
3. Adoption of the following Appropriation
Ordinance Amendments in the Parks and Recreation Bond Fund:
a. Increase the Municipal Rose Garden Project by
$66,000.
b.
Decrease
the Ending Fund Balance by $66,000.
Bids were opened on April 17, 2003 with the following results:
|
Contractor |
Base
Bid |
Add Alt Total |
Total
Bid |
Variance Amount |
Over/ (Under) Percent |
|
Frank Surian and Sons, Inc. (Gilroy) |
$1,647,596 |
$229,342 |
$1,876,938 |
$267,938 |
16 |
|
Kin Wo Construction, Inc. (San Francisco) |
1,463,176 |
208,417 |
1,671,593 |
62,593 |
4 |
|
Chegwin Construction, Inc. (San José) |
1,351,000 |
151,000 |
1,502,000 |
(107,000) |
(6) |
|
Engineer’s Estimate |
1,275,000 |
334,000 |
1,609,000 |
--- |
|
|
Robert A. Bothman, Inc. (San José) |
1,254,000 |
257,000 |
1,511,000 |
(98,000) |
(6) |
|
John Plane Construction, Inc. (San José) |
964,003 |
126,000 |
1,090,003 |
(518,997) |
(32) |
|
Contractor |
Add
Alt. No. 1 |
Add Alt. No. 2 |
|
Frank Surian and Sons, Inc. (Gilroy) |
$31,282 |
$198,060 |
|
Kin Wo Construction, Inc. (San Francisco) |
23,855 |
184,562 |
|
Chegwin Construction, Inc. (San José) |
60,000 |
91,000 |
|
Engineer’s Estimate |
119,000 |
215,000 |
|
Robert A. Bothman, Inc. (San José) |
31,000 |
226,000 |
|
John Plane Construction, Inc. (San José) |
23,000 |
103,000 |
John Plane Construction, Inc. submitted the lowest base bid in the amount of $964,003. Three working days after bid opening, John Plane Construction, Inc. sent a faxed letter to the Director of Public Works indicating they made a mathematical error in their bid price and requested to withdraw their bid. According to City of San Jose Standard Specifications Section 2-1.095, the contractor submitted supplemental documentation showing that masonry work associated with bid item “brick columns and walls” was entered incorrectly as $18,000 when the actual amount was $180,000.
City staff reviewed the documentation provided and verified that the contractor made a clerical error in the bid. Staff recommends that John Plane Construction, Inc. be released from its bid on the basis of their claim.
The withdrawal of John
Plane Construction, Inc. makes the lowest responsive bidder Robert A. Bothman,
Inc. Robert A. Bothman’s bid is six
percent below the Engineer’s Estimate and is considered reasonable for the work
involved in the project. Add
Alternative No.2 which is an integral part of the original Parks Bond scope of
work, requires an additional $66,000 be appropriated from the Parks and
Recreation Bond Fund Ending Fund Balance.
Although the project is primarily financed by the Parks Bond Fund, State Proposition 12/Roberti-Z’-Berg Harris Urban Open Space and Recreation Grant Funding provides funding for the new maintenance/office building and security lighting improvements totaling $210,000. The City applied for this grant funding and was directed from the State of California to proceed with this project in December 2002. Because Proposition 12 funding is available on a reimbursement basis, it is anticipated that the City would receive this funding in 2003-2004 when the Proposition 12 funded portion of this project is completed. In the current year, the Department of Parks, Recreation and Neighborhood Services recommends the use of the Parks City-Wide Construction and Conveyance Tax Fund Ending Fund Balance to establish a project appropriation. This fund would be replenished in Fiscal Year 03-04 when the grant funds are received.
Council Policy provides for a standard contingency of ten percent on public works building projects. The standard contingency is appropriate for this project.
An alternative to hiring a contractor for this work is for the work to be done by existing City staff. Staff considered this alternative and recommends using a contractor because current City staff is fully utilized for coordination and construction management services and there are no
available existing City
staff resources with appropriate expertise or licensing requirements to perform
construction work related to historic
buildings.
1. AMOUNT OF RECOMMENDATION: $1,511,000
2. COST OF PROJECT:
|
Construction |
1,511,000 |
|
|
Project Delivery* |
421,900 |
|
|
Contingency |
151,100 |
|
|
TOTAL |
$2,084,000 |
|
* $135,603 for the consultant agreement was expended/encumbered in FY 2001-02.
3. SOURCES OF FUNDING: 471 - Parks and Recreation Bond Projects Fund
391 - Parks City-Wide C&C Fund
4. FISCAL
IMPACT: This project is consistent with
the Council-approved Budget Strategy’s Economic Recovery section in that it
will spur construction spending in our local economy. However, the adopted Capital Improvement Program includes the
following annual operating and maintenance impacts.
|
Fund # |
Appn # |
Appn. Name |
RC # |
Total Appn. |
Amt. for Contract |
Adopted Budget Page |
Last Budget Action (Date, Ord. No.) |
|
471 |
6928 |
Municipal Rose
Garden |
11910X |
1,618,000** |
1,511,000 |
Page 620 |
10/15/02-Ord. No. 26755 |
|
|
|
|
|
|
|
|
|
|
|
|
Total |
|
1,618,000** |
1,511,000 |
|
|
Exempt; HP02-020.
KATY
ALLEN LARRY
D. LISENBEE
Director, Public Works Department Director, Budget Office