Subject:  BAILEY EXTENSION OVER UNION PACIFIC RAILROAD

 

Council District:  2

 

RECOMMENDATION

 

a.       Adoption of a resolution authorizing the Director of Public Works to execute an agreement with Caltrans for reimbursement to the City from the State Grade Separation Fund for the Bailey Avenue Extension over Union Pacific Railroad in an amount not to exceed $5,000,000. 

 

b.      Adoption of the following appropriation ordinance amendments in the Building and Structure Construction Tax Fund to:

 

1.      Establish an appropriation to the Department of Transportation for the Bailey Avenue Above-Grade Crossing at UPRR in the amount of $950,000.

2.      Reduce the Reserve for the VTA: Bailey/101 Improvement Project by $950,000.

 

c.       Adoption of a resolution authorizing the City Manager to negotiate and execute any amendments to existing agreements as needed to implement the Bailey Avenue Above-Grade Crossing at UPRR and any new agreements, as may be appropriate and necessary to implement the proposal set forth in this memorandum.

 

 

BACKGROUND

 

On October 24, 2000, Council approved the rezoning for the properties of Coyote Valley Research Park (CVRP) for the development of 6,600,000 square feet of campus industrial uses on 688 acres of land that CVRP owns within the 1,444-acre North Coyote Valley Campus Industrial Area.  One of the major improvements necessary for the development of North Coyote Valley is the Bailey Extension Project.

 

1.   Original Bailey Extension Project

 

The original Bailey Extension Project involved extending Bailey Avenue from its current terminus to the east across Route 101, where it would connect with Malech Road in the County of Santa Clara.  The original project included a grade separation over the Union Pacific Railroad tracks (UPRR) and Monterey Road including two connecting ramps at Monterey Road, a bridge over Coyote Creek, and a full interchange at Route 101.  The total project cost was estimated to be $45 million, with the VTA contributing $4.5 million, the State contributing up to $18 million, and CVRP contributing $22.5 million.

 

2.   Revised Bailey Extension Project

 

Due to the economic downturn, CVRP reduced its commitment to the project to $2 million.  This, along with the need to award the project by March 2003 in order to maintain State funding, resulted in the City substantially modifying the project into 2 phases.  On November 12, 2002, Council approved this modified project and the necessary funding for it.

 

Phase 1 of the modified project consists of two segments.  Segment A (Phase 1A) involves construction of a six-lane Bailey Avenue bridge over Coyote Creek and a full interchange at Highway 101.  Segment B (Phase 1B) involves an at-grade connection ramp between the elevated Bailey Avenue and Monterey Road including a traffic signal at Monterey Road.  Phase 2 of the modified project involves constructing a grade separation over the UPRR tracks and Monterey Road, and an additional connecting ramp at Monterey Road. 

 

The VTA is currently constructing Phase 1A of the modified project.  As of the November 12, 2002 Council action, the estimated cost of Phase 1 was approximately $30,065,600.  It was anticipated that, with the VTA’s $4.5 contribution and the State’s contribution of up to $18 million, CVRP would need to fund $7,565,600.  On November 12, 2002, Council approved the following financing plan: 

 

·        CVRP to provide funding of $2,000,000.  Most of CVRP’s contribution will be in the form of right-of-way and the mitigation land required for Phase 1 of the modified project.

 

·        City to form a Community Facilities District (CFD) on the site of CVRP’s proposed development and issue special tax bonds to provide $1,515,000 for Phase 1 of the modified project.

 

·        City to provide a cash advance estimated at $4,050,000, and a Reserve Fund in the amount of $950,000 to fund cost over-runs.  The City’s cash advance and any needed Reserve Fund is secured by liens against the properties in the CFD.

 

3.   Bond Sale

 

On December 17, 2002, Council formed the CFD and authorized the issuance and sale of special tax bonds in an amount not to exceed $15,000,000.  On January 29, 2003, the City sold $13,560,000 worth of special tax bonds of the CFD, $1,515,000 of which shall be applied towards Phase 1 of the modified project.  The remaining bond proceeds shall be used to redeem existing bonds from a prior bond sale to finance public infrastructure required from the properties in the CFD.

 

4.   Bids For Phase 1A

 

VTA is currently managing the bid, award and construction of Phase 1.  The construction cost for Phase 1A was originally estimated at $18,740,000.  The bid opening was held on February 6, 2003.  The low bidder was Granite Construction Company/Meyers Joint Venture with a contract amount of $14,850,000.  With this cost saving of $3,890,000 for Phase 1A, the State subsequently reduced its $18 million contribution to $14.8 million.  The balance of $690,000 in cost saving shall be applied towards Phase 1.

 

 

ANALYSIS

 

1.   Constructing An Above-Grade Crossing At Monterey Road

 

As a result of the low bids on Phase 1A and the opportunity for some additional State funds from the State Grade Separation Fund, staff believes that at this time there may be the opportunity to construct the above-grade crossing at Monterey Road.  As part of Phase 2, this would involve constructing a 4-lane bridge (ultimately 7 lanes) from the bridge over Coyote Creek easterly over Monterey Road and the UPRR tracks.  At this time, it is contemplated that the City would construct the above-grade crossing. 

 

The advantage to constructing the above-grade crossing now, as opposed to sometime in the future, is being able to capture up to $5 million additional State grant funds and to take advantage of the current favorable bidding environment.  It also would provide additional traffic capacity sooner for the development within North Coyote Valley.

 

2.   Financing Strategy

 

The total cost of designing and constructing the 4-lane above-grade crossing is approximately $7,954,000.  Staff proposes to finance the above-grade crossing as follows:

 

a.                                                       $400,000 Funds from UPRR

 

On September 10, 2001, the City executed an agreement with UPRR to allow construction of the Bailey Extension over UPRR and a not to exceed $400,000 UPRR contribution towards the over crossing. 

 

b.      Approximately $1,604,000 Developer Contribution

 

CVRP has agreed to contribute approximately $1,604,000 towards right-of-way acquisition and grading of the above-grade crossing embankments.  This would be in addition to CVRP’s $2,000,000 commitment and the CFD liens placed on their property.

 

c.       $5,000,000 from a State Grade Separation Funding Agreement

 

On March 26, 2002, Council adopted a resolution providing for filing of an application for funding from the State Grade Separation Program for the Bailey Avenue Extension over UPRR, and stating that sufficient local funds will be made available as the work of the project progresses.

 

On June 27, 2002, the California Transportation Commission, acting by and through the Director of Caltrans, allocated the amount of $5,000,000 from the Grade Separation Fund for the 2002-2003 Fiscal Year, to be used as a contribution towards the Bailey Avenue Extension over UPRR.  The funds would be reimbursed to the City at 80% of the direct costs of the project up to the maximum of $5,000,000.

 

The State funding agreement requires the City to award a contract for construction of the above-grade crossing within one year after allocation of the $5,000,000 by the Director of Caltrans.  This means the City would need to award the construction contract for the above-grade crossing work by June 27, 2003.  However, the City’s current estimated award date for this work being awarded is April 2004. 

 

Staff has requested Caltrans to extend the June 27, 2003 date.  Caltrans has indicated that before it would consider extending the award deadline, the proposed agreement must be executed first prior to June 5, 2003.  Otherwise, the $5,000,000 allocation will be reverted and reallocated to another city.  If Caltrans refuses to extend the award deadline after execution of the funding agreement, the City would likely lose the $5,000,000 State grant.

 

The State funding agreement also requires the City to certify that it has sufficient funds available to finance its share of the project costs.  As discussed below, staff believes that the City can certify the availability of sufficient local funds from those funds already allocated by the City to the modified Bailey Extension Project.

 

d.      $950,000 of Local Funds.

 

Staff believes that the remaining $950,000 needed to construct the above-grade crossing can be obtained from City funding already appropriated for the modified Bailey Extension Project.  No additional local funds are needed.

 

As part of the November 12, 2002 funding action, the City appropriated $950,000 as a reserve for Phase 1 of the project.  The $950,000 was originally reserved for cost overruns on Phase 1.  However, now that there is already $690,000 of cost saving from the bid result being applied towards Phase 1, staff recommends appropriating the $950,000 from the reserve for Phase 1 established in November 12, 2002 to the above-grade crossing.  Staff believes that with the recent favorable construction cost environment, the $690,000 of cost saving should be sufficient to cover any cost over-runs for Phase 1. 

 

Moreover, construction of the above-grade crossing would not occur until approximately May 2004.  By that time, Phase 1A should be substantially completed.  If at any time prior to awarding the above-grade crossing project it looks like Phase 1 will involve unanticipated cost overruns in excess of $690,000, the City can shift some or all of $950,000 funds appropriated for the above-grade crossing project back to Phase 1.  If this were necessary, the City could look for ways to reduce the scope of the above-grade crossing project and/or seek additional funding sources.  The worst case scenario is that unanticipated cost overruns would result in the City not being able to proceed with construction of the above-grade crossing, which would result in the City losing the $5,000,000 in grant funding from the State.

 

The following is a summary of the Financing Strategy for the above-grade crossing:

 

                          Funds from UPRR                                                      $   400,000

                          Developer Contribution                                                 1,604,000

                          Funds from State Grade Separation Program     5,000,000

                          City Advance                                                                   950,000

                                                                                                Total    $7,954,000

 

 

CONCLUSION

 

Based on all of the above, staff believes that it is prudent for the City to proceed with efforts to construct the above-grade crossing.  Accordingly, staff recommends that Council:

 

·        Approve the agreement with Caltrans for reimbursement to the City in an amount not to exceed $5,000,000 for the Bailey Avenue above-grade crossing at UPRR.

 

·        Reduce the $950,000 Bailey/101 Reserve Fund to zero, and establish an appropriation for the Bailey Avenue above-grade crossing at UPRR in the amount of $950,000.

 

 

PUBLIC OUTREACH

 

Numerous neighborhood and community meetings were held by CVRP’s consultant, the Morley Hunter Group, informing the public about CVRP’s development and the public infrastructure associated with its development.

 

 

COORDINATION

 

Preparation of this staff memo has been coordinated with the City Attorney’s Office and the Department of Transportation.

 

 

COST IMPLICATIONS

 

1.                                                                                                                              AMOUNT OF RECOMMENDATION:  $950,000

 

2.                                                                                                                              COST OF PROJECT:

 

      Construction                                                                                               $4,900,000

      Design and Construction Management                                                           1,079,000

      Right-Of-Way  Acquisition                                                                           1,370,000

      Contingency                                                                                                    605,000

TOTAL                                                                                          $7,954,000

 

3.      SOURCE OF FUNDING:

 

Fund 429 – Building and Structure Construction Tax Fund                          $   950,000

Developer Contribution                                                                                1,604,000

State Contribution                                                                                        5,000,000

UPRR Contribution                                                                                         400,000

TOTAL                                                                                                      $7,954,000

 

4.   FISCAL IMPACT:  The total cost of recommendation is an amount not to exceed $950,000 and is consistent with many of the principles outlined in the Council-approved Budget Strategy.  The opportunity to implement the development of high-priority transportation infrastructure needs with the development of the Bailey/101 Project will provide significant public benefit related to cost effectiveness and reduced construction impacts associated with the future development.

 

 

BUDGET REFERENCE

 

 

Fund

#

 

Appn.

#

 

Appn. Name

 

RC #

 

Total

Appn.

 

Amt. For Contract

Adopted Budget Page

Last Budget Action

(Date, Ord. No.)

429

7595

VTA: Bailey/101 Improvements Project Reserve

 

950,000

 

 

11/12/02-Ord. No. 26747

 

 

TOTAL

 

950,000

 

 

 

 

 

CEQA

 

Resolution No. 68705.

 

 

KATY ALLEN

Director, Public Works Department

 

LARRY D. LISENBEE

Budget Director