Subject: MUNICIPAL ROSE GARDEN RENOVATION
PROJECT
Council District: Citywide
Report on bids and take appropriate action based on the evaluation of bids for the Municipal Rose Garden Renovation Project.
BACKGROUND
The Municipal Rose Garden is a regional
park and designated historic site on Naglee Avenue (map attached). The project, funded by the City Parks Bond Measure will renovate
existing facilities for code and regulation compliance, including Americans
with Disabilities (ADA) standards.
The proposed Municipal Rose Garden Renovation Project will make improvements to the east side of the site. The base bid of the project will renovate the existing men’s and women’s restrooms, construct a new maintenance/office building, install infrastructure for the future addition of lighting, replace existing perimeter fencing and install decomposed granite pathways in the rose garden. Construction is scheduled to begin in June with completion in April 2004.
In addition to the base bid scope of work there are two Add Alternate bid items as follows:
|
Description |
Engineer’s Estimate |
|
Add Alternate No. 1: Purchase and installation of six park electroliers. |
$119,000 |
|
Add Alternate No. 2: Demolition and replacement of the existing asphalt central pathway with decorative material. |
215,000 |
A supplemental memorandum will be provided after bids are opened on April 17, 2003.
Although the project is primarily financed by the Parks Bond Fund, State Proposition 12/Roberti-Z’-Berg Harris Urban Open Space and Recreation Grant Funding provides funding for the new maintenance/office building and security lighting improvements totaling $210,000. The City applied for this grant funding and was directed from the State of California to proceed with this project in December 2002. Because Proposition 12 funding is available on a reimbursement basis, it is anticipated that the City would receive this funding in 2003-2004 when the Proposition 12 funded portion of this project is completed. In the current year, the Department of Parks, Recreation and Neighborhood Services (PRNS) will recommend the use of the Parks City-Wide Construction and Conveyance Tax Fund (C&C) Ending Fund Balance to establish a project appropriation. This fund would be replenished in Fiscal Year 03-04 when the grant funds are received.
Council Policy provides for a standard contingency of ten percent on public works building projects. The standard contingency is appropriate for this project.
The City Charter requires that public works projects exceeding $100,000 in labor charges must be contracted.
Two community meetings were held on June 17, 2002 and August 15, 2002 to gather input for the design of this project. Additionally, to solicit contractors, this project was listed on the City’s Internet Bid Line and advertised in the San José Mercury News and San José Post Record. Bid packages for all Department of Public Works construction projects are provided to various contractor organizations and builder’s exchanges.
This memo has been coordinated with the Departments of Finance, Planning, Building and Code Enforcement, General Services, Parks, Recreation and Neighborhood Services, the City Attorney’s Office and the City Manager’s Budget Office.
1. AMOUNT OF RECOMMENDATION: Engineer’s Estimate $1,275,000
2. COST OF PROJECT:
|
Project Development |
$63,000 |
|
|
Construction |
1,275,000 |
|
|
Consultant* |
199,000 |
|
|
Design & Construction Management |
195,000 |
|
|
Contingency |
127,500 |
|
|
TOTAL |
$1,859,500 |
|
* $135,603 for the consultant
agreement was expended/encumbered in FY 2001-02.
3. SOURCES OF FUNDING: 471 - Parks and Recreation Bond Projects Fund
391 - Parks
City-Wide C&C Fund
4. OPERATING
COSTS: This project is consistent with
the Council-approved Budget Strategy’s Economic Recovery section in that it
will spur construction spending in our local economy. The estimated minimal annual operating and maintenance costs are $1,750. .
|
Fund: |
471 |
|
Appn: |
6928-Municipal Rose Garden |
|
RC: |
119108 |
|
Amount: |
$1,618,000** |
|
Budget Document: |
2002-2003 Adopted Capital Budget, Page 620, as amended on 10/15/2002, Ordinance Number 26755. |
** An appropriation action of $210,000 will be recommended in the supplemental memo for this project.
**An additional $54,000 is allocated from Fund 471 in Fiscal Year 03-04.
Exempt, HP02-020.
KATY ALLEN
Director, Public Works Department