Attachment C
CUSP SUB-PROJECTS
·
Project
Charter & Executive Sponsorship – First step in the enterprise CUSP
project that was taken by the executives who had a vision for an integrated
system. Project charter concluded with
the City Council’s approval to develop an RFP for an integrated Customer
Service, Billing, and Contract Enforcement.
The Sponsorship task will continue for the length of the project.
·
Business
Question Assessment – The project manager assessed the need for this
solution at a very high level.
·
Discovery
– Project manager and key business experts examine background, current
systems and draw up a roadmap for the project.
·
Request
for Information (RFI) – An RFI was issued in order to educate staff on
solutions in the market and to gather data from the industry on published
prices and possible solutions.
·
Business
Process Improvement Project (PIP) – UBS and IWM business processes are
shaped by antiquated solutions and systems that are available to business
units. In order not to model the new system
after the existing processes and procedures, a PIP was initiated for all
business units in the CUSP scope.
During this process cost savings were also documented that will play a
big role in the Return On Investment (ROI) analysis later in the project.
·
Stabilize Current System (IRIS/Socrates, etc) – In order to
avoid duplicating improvements and efficient use of resources, improvements to
the current system are now part of the CUSP project.
·
Current
IT Infrastructure & Integration Requirements Study – This task
is required for the development of a successful RFP.
·
RFP
Process – This process starts with documenting requirements and high
level features gathered through the previous sub-projects and ends with the
start of the Implementation phase.
·
ROI
Analysis – Analysis of cost savings compared to solutions proposed
by the top few proposers is one of the selection criteria. This analysis will also serve as a measure
for success of the system every year.
·
Detail
Technical and Functional Requirements & Specification (Solution Specific) – This
sub-project is completed with the selected vendor and is designed to create a
detail technical and functional map of the system.
·
Implementation
– Accomplished with conjunction with the contractor. The City’s project manager will be managing
the overall project. Contractor’s
project manager will report to the City’s project manager.
·
Functional
& Technical QA – Test plans will be developed by City staff or third
party consultants and applied to the system before final acceptance.
·
Deployment
– Preparations and carrying out of the switch over to CUSP.
·
Project
Termination – Resource re-allocation.
·
Maintenance
– Our method requires that a team consisting of IT, business stakeholders
and budget analysts be formed and exist for the life cycle of the system and
have periodic business process reviews and feature and upgrade checks and do
not allow home grown databases to develop because of lack of functionality that
can easily be obtained through regular feature upgrades or new system reports.
·
Risk
Management (Continuous Throughout the Project) – This
task started with a Risk Assessment Matrix and will continue
to the end of the Termination sub-project.