SUBJECT: REPORT ON BIDS – SAN JOSE/SANTA CLARA WATER POLLUTION CONTROL PLANT, FY 2000/2001 CAPITAL IMPROVEMENT PROGRAM, SETTLED SEWAGE PUMP STATION DISCHARGE PIPING AND CONCRETE VAULT REHABILITATION
RECOMMENDATION
Report on bids and approval of award of contract for the construction project entitled “San Jose/Santa Clara Water Pollution Control Plant, FY 2000/2001 Capital Improvement Program, Settled Sewage Pump Station Discharge Piping and Concrete Vault Rehabilitation” to the sole bidder, Anderson Pacific Engineering Construction Incorporated, in the amount of $574,000, and approval of a contingency in the amount of $57,000. CEQA: Exempt.
BACKGROUND
This project provides for the reinforcement of three corroded settled sewage pump station discharge pipe headers. In addition, the corroded concrete in the wet well will be rehabilitated.
Bids were opened on May 17, 2001 for the project. The results of the bids are as follows:
|
|
|
|
Variance Over / (Under) |
|
|
|
Contractor |
City |
Bid Amount |
Amount |
Percent |
|
|
|
|
|
|
|
|
|
Engineer’s Estimate |
|
$570,000 |
|
|
|
|
|
|
|
|
|
|
|
Anderson Pacific Engineering Construction Incorporated |
Santa Clara |
$574,000 |
$4,000 |
0.7% |
|
|
|
|
|
|
|
|
Award to the sole bidder, Anderson Pacific Engineering Construction Incorporated, in the amount of $574,000 is recommended. This bid is 0.7 percent above the Engineer's Estimate. This project includes application of a pipe wrap system and concrete repair work in a confined space. The single bid may have resulted from the specialized nature of the work.
The bid documents have been evaluated and found to be in order. Anderson Pacific has successfully completed several projects in the past for the Water Pollution Control Plant. A contingency in the amount of $57,000 is requested for any unforeseen conditions that may arise during construction.
This construction project was advertised in the San Jose Mercury News and San Jose Post Record. Bid packages for all Environmental Services Department construction projects are routinely provided to a standard list of contractor organizations, builder’s exchanges, and disadvantaged business organizations, including United Minority Business Entrepreneurs.
COORDINATION
The project has been coordinated with the Office of the City Attorney, Office of Equality Assurance, and Risk Management, and was scheduled to be heard at the June 14, 2001, Treatment Plant Advisory Committee meeting.
Existing funds are available for this purpose. No appropriation action is required.
BUDGET REFERENCE
Page
787
The City of San Jose Nondiscrimination Requirements are included in this project as required in Chapter 4.08 of the San Jose Municipal Code.
CEQA
CEQA: Exempt.
CARL W. MOSHER
Director, Environmental Services Department