To: HONORABLE MAYOR AND From: Katy Allen
CITY COUNCIL
Subject: TERRELL & T.J. MARTIN Date: 06-02-03
PARKS PLAY AREA
RENOVATION
PROJECTS
Council Districts: 9 & 10
Report on bids and award of contract for
the Terrell & T.J. Martin Parks Play Area Renovation Projects to the low
bidder, HRB Construction, Inc., in the amount of $442,062, and approval of a
contingency in the amount of $22,000.
Funding for this contract is included in the 2003-2004 Capital Budget
that is scheduled to be approved by the City Council on June 17, 2003. This action is contingent on the approval of
the budget.
BACKGROUND
Terrell and T.J. Martin Parks are existing neighborhood parks in Council Districts 9 and 10, respectively. Terrell Park is located at the intersection of Kenton Lane and Normington Way; and T.J. Martin Park is located at the intersection of Burchell Avenue and The Strand (maps attached).
The City Parks Bond Measure provides funding for the renovation of park play areas and restrooms in neighborhood parks. The project includes the renovation of the existing tot lot play area at Terrell Park, the existing T.J. Martin Park play area comprised of a combined youth and tot lot, and miscellaneous landscape improvements for both Terrell and T.J. Martin Parks. Community preference and the large square footage of the T.J. Martin Park play area requires additional funding to completely renovate this area. This funding is provided in the Council District 10 Construction and Conveyance Tax Fund and is included in the 2003-2004 Proposed Capital Budget.
Construction is scheduled to begin in September with completion in February 2004.
Bids were opened on May 15, 2003 with the following results:
|
Contractor |
Total
Bid |
Variance Amount |
Over/(Under) Percent |
|
Lone Star Landscape (San Martin) |
$544,500 |
118,500 |
28 |
|
JFC Construction, Inc. (Lafayette) |
488,084 |
62,084 |
15 |
|
Robert A. Bothman, Inc. (San José) |
476,555 |
50,555 |
12 |
|
HRB Construction, Inc. (San José) |
442,062 |
16,062 |
4 |
|
Engineer’s Estimate |
426,000 |
---- |
---- |
The low bid submitted by
HRB Construction, Inc. is four percent above the Engineer's Estimate. Staff considers this reasonable for the work
involved in this project.
Council Policy provides for a
standard contingency of five percent on public works parks projects. The standard contingency is appropriate for
this project.
One community meeting
was held for each park to gather input for the design of the renovation
projects. The community meetings for
T.J. Martin Park and Terrell Park were held on
November 6, 2002 and
November 7, 2002, respectively.
To solicit contractors, the projects were listed on the City’s Internet Bid Line and advertised in the San José Mercury News and the San José Post Record. Bid packages for all Department of Public Works construction projects are provided to various contractor organizations and builder’s exchanges.
The project and memo were coordinated with the City
Attorney’s Office, the City Manager’s Budget Office and the Departments of
Finance, Planning, Building and Code Enforcement, General Services and Parks,
Recreation and Neighborhood Services.
1. AMOUNT OF RECOMMENDATION: $442,062
2. COST OF PROJECT:
|
Project Delivery |
$160,900 |
|
|
Construction |
442,062 |
|
|
Contingency |
22,000 |
|
|
TOTAL |
$624,962 |
|
3. SOURCES OF FUNDING: 471 - Parks Bond Measure Fund
389 - Council District 10 C&C Fund
4. FISCAL IMPACT: These projects are consistent with the Council-approved Budget
Strategy Economic Recovery section in that it will spur construction spending
in our local economy. They provide for
the renovation of the existing play areas and, therefore, will have a
negligible impact on the operating budget.
|
Fund # |
Appn # |
Appn. Name |
RC # |
Total Appn. |
Amt. for Contract* |
Budget Page* |
Last Budget Action (Date, Ord. No.) |
|
471 |
4637 |
Terrell
Park Play Area Renovation |
12372B |
287,000 |
168,805 |
2002-2003 Adopted Budget
Page 566 |
2/25/03-Ord. No. 26840 |
|
471 |
4535 |
T.J.
Martin Park Play Area Renovation |
12353B |
265,000 |
165,757 |
2002-2003 Adopted Budget
Page 598 |
NA |
|
389 |
TBD |
T.J. Martin Park Play Area Renovation |
TBD |
200,000 |
107,500 |
2003-2004 Proposed Budget Page 479 |
NA |
|
|
|
Total |
|
752,000 |
442,062 |
|
|
|
|
|
|
|
|
|
|
|
· * This contract will be funded by the 2003-2004 Capital Budget. A portion of the funds budgeted in 2002-2003 will be rebudgeted to 2003-2004 for this contract. The 2003-2004 Capital Budget is expected to be approved by the City Council on June 17, 2003, and the implementing appropriation ordinance is scheduled to be adopted on June 24, 2003.
Terrell: Exempt; PP03-02-051.