
To: HONORABLE MAYOR AND From: Katy Allen
CITY COUNCIL Dale Foster
Subject: FIRE STATION NO. 4 UPGRADE Date: 08-19-03
District: 6
SNI: Burbank/Del Monte
To provide additional information after bids were opened.
RECOMMENDATION
Report on bids and award of contract for the Fire Station No. 4 Upgrade Project to the low bidder, D.L. Falk Construction, Inc., in the amount of $754,813, and approval of a contingency in an amount of $113,222.
CEQA: Exempt, PP02-12-389.
On March 5, 2002, San José’s voters passed the Neighborhood Security Act Bond Measure. This bond measure provides for the construction of 36 public safety projects including the upgrades of 20 fire stations. One of the first fire stations to be upgraded under this bond measure is Fire Station No. 4, located at 710 Leigh Avenue.
The project upgrades conform to the intent of the Neighborhood Security Act Bond Measure by incorporating operational and livability efficiencies that will maintain and extend fire and paramedic response times to established neighborhoods and planned developments within the City. The planned upgrades will also enable the fire station to meet the “Essential Facility” designation with the addition of a new emergency generator. Construction is scheduled to begin in October with completion in April 2004.
ANALYSIS
Bids were opened
on August 12, 2003 with the following results:
|
|
|
|
(Under) |
|
Contractor |
Total Bid |
Amount |
Percent |
|
ESR Construction, Inc. (San Jose) |
984,000 |
217,200 |
28 |
|
Chegwin
Construction, Inc. (San Jose) |
942,000 |
187,187 |
25 |
|
Rushford
Construction Co., Inc. (Santa Clara) |
892,000 |
161,400 |
22 |
|
D & K
Painting Co., Inc. (Millbrae) |
870,000 |
139,400 |
19 |
|
Tinney Construction
Corp. (Redwood City) |
857,000 |
126,400 |
17 |
|
Kin Wo
Construction, Inc. (San Francisco) |
854,800 |
124,200 |
17 |
|
Pencon (San Ramon) |
836,000 |
105,400 |
14 |
|
R.C Benson
& Sons, Inc.(Mountain View) |
804,434 |
73,834 |
10 |
|
ICC General
Contractors, Inc. (Sunnyvale) |
768,000 |
37,400 |
5 |
|
HRB
Construction, Inc. (San Jose) |
766,800 |
36,200 |
5 |
|
D.L. Falk
Construction, Inc. (So San Francisco) |
754,813 |
$24,213 |
3 |
|
Engineer’s Estimate |
$730,600 |
--- |
-- |
The low bid,
submitted by D.L. Falk Construction, Inc., is three percent over the Engineer’s
Estimate. Staff considers this
reasonable for the work involved.
Council Policy
provides for a standard contingency of 15 percent on public works projects
involving building renovations. The
standard contingency is appropriate for this project.
PUBLIC OUTREACH
To solicit contractors, this project was listed on the City’s Internet Bid Line and advertised in the San José Post Record and other Bay Area publications. Bid packages for all Department of Public Works construction projects are provided to various contractor organizations and builder’s exchanges.
COORDINATION
This project and memo have been coordinated with the
Departments of Fire, Finance, General Services, Planning, Building and Code
Enforcement, the City Manager’s Budget Office and City Attorney’s Office.
|
1. |
AMOUNT OF RECOMMENDATION: |
$754,813 |
|
||||||
|
2. |
COST OF PROJECT: |
|
|
||||||
|
|
|
Project Delivery |
$299,715 |
||||||
|
|
|
Construction (Allocated) |
$754,813 |
||||||
|
|
|
Contingency |
113,222 |
||||||
|
|
|
TOTAL |
$1,167,750 |
||||||
|
|
|
|
|
||||||
|
3. |
SOURCE OF FUNDING: |
475 - Neighborhood Security Bond |
|||||||
|
4. |
FISCAL IMPACT: This project is consistent with the
Council-approved Budget Strategy Economic Recovery section in that it will
spur construction spending in our local economy. The proposed operating and maintenance costs of this project
have been reviewed and it has been determined that the project will have no
significant adverse impact on the General Fund operating budget. |
||||||||
|
Fund # |
Appn # |
Appn Name |
RC # |
Total Appn*. |
Amt. For Contract |
Proposed Budget Page |
Last Budget Action (Date, Ord. No.) |
|
475 |
4548 |
Fire Station Upgrades |
122815 |
$7,327,000 |
$754,813 |
p. 246 |
Amended with MBA #23 and MBA #37, p. 24 |
Exempt, PP02-12-389.
DALE FOSTER KATY ALLEN
Acting Fire Chief, Fire Department Director, Public Works Department