To:   HONORABLE MAYOR AND                   From:   Katy Allen

                        CITY COUNCIL                                                        Dale Foster

 

Subject: FIRE STATION NO. 4 UPGRADE             Date:     08-19-03

 

District: 6

 

SNI: Burbank/Del Monte

 

REASON FOR SUPPLEMENTAL MEMO

 

To provide additional information after bids were opened.

 

 

RECOMMENDATION

 

Report on bids and award of contract for the Fire Station No. 4 Upgrade Project to the low bidder, D.L. Falk Construction, Inc., in the amount of $754,813, and approval of a contingency in an amount of $113,222.

CEQA:  Exempt, PP02-12-389.

 

 

BACKGROUND

 

On March 5, 2002, San José’s voters passed the Neighborhood Security Act Bond Measure.  This bond measure provides for the construction of 36 public safety projects including the upgrades of 20 fire stations.  One of the first fire stations to be upgraded under this bond measure is Fire Station No. 4, located at 710 Leigh Avenue.

 

The project upgrades conform to the intent of the Neighborhood Security Act Bond Measure by incorporating operational and livability efficiencies that will maintain and extend fire and paramedic response times to established neighborhoods and planned developments within the City.  The planned upgrades will also enable the fire station to meet the “Essential Facility” designation with the addition of a new emergency generator.  Construction is scheduled to begin in October with completion in April 2004.

 

 

ANALYSIS

 

Bids were opened on August 12, 2003 with the following results:

 

 

 

 

(Under)

Contractor

Total Bid

Amount

Percent

ESR Construction, Inc. (San Jose)          

  984,000

  217,200

    28

Chegwin Construction, Inc. (San Jose)

  942,000

  187,187

     25

Rushford Construction Co., Inc. (Santa Clara)

  892,000

  161,400

     22

D & K Painting Co., Inc. (Millbrae)

  870,000

  139,400

     19

Tinney Construction Corp. (Redwood City)

  857,000

  126,400

     17

Kin Wo Construction, Inc. (San Francisco)

  854,800

  124,200

     17

Pencon  (San Ramon)

  836,000

  105,400

     14

R.C Benson & Sons, Inc.(Mountain View)

  804,434

  73,834

     10

ICC General Contractors, Inc.  (Sunnyvale)

  768,000

  37,400

      5

HRB Construction, Inc.  (San Jose)

  766,800

  36,200

      5

D.L. Falk Construction, Inc.  (So San Francisco)

  754,813

$24,213

      3

Engineer’s Estimate

$730,600

     ---

      --

 

The low bid, submitted by D.L. Falk Construction, Inc., is three percent over the Engineer’s Estimate.  Staff considers this reasonable for the work involved.

 

Council Policy provides for a standard contingency of 15 percent on public works projects involving building renovations.  The standard contingency is appropriate for this project.

 

 

PUBLIC OUTREACH

 

To solicit contractors, this project was listed on the City’s Internet Bid Line and advertised in the San José Post Record and other Bay Area publications.  Bid packages for all Department of Public Works construction projects are provided to various contractor organizations and builder’s exchanges.

 

 

COORDINATION

 

This project and memo have been coordinated with the Departments of Fire, Finance, General Services, Planning, Building and Code Enforcement, the City Manager’s Budget Office and City Attorney’s Office.

 

 

COST IMPLICATIONS

 

1.

AMOUNT OF RECOMMENDATION:

 

$754,813

 

2.

COST OF PROJECT:

 

 

 

 

Project Delivery

$299,715

 

 

Construction (Allocated)

$754,813

 

 

Contingency

113,222

 

 

TOTAL

$1,167,750

 

 

 

 

3.

 

SOURCE OF FUNDING:

 

475 - Neighborhood Security Bond

4.

 

FISCAL IMPACT:  This project is consistent with the Council-approved Budget Strategy Economic Recovery section in that it will spur construction spending in our local economy.  The proposed operating and maintenance costs of this project have been reviewed and it has been determined that the project will have no significant adverse impact on the General Fund operating budget.

 

 

BUDGET REFERENCE

 

 

Fund

#

 

Appn

#

 

Appn Name

 

RC #

 

Total Appn*.

 

Amt. For Contract

 

Proposed Budget Page

 

Last Budget

Action

(Date, Ord. No.)

475

4548

Fire Station Upgrades

122815

$7,327,000

$754,813

p. 246

Amended with MBA #23 and MBA #37, p. 24

 

 

CEQA

 

Exempt, PP02-12-389.

 

 

DALE FOSTER                                                           KATY ALLEN

Acting Fire Chief, Fire Department                                Director, Public Works Department