Coyote Valley Specific Plan Draft Work Plan
Task Force Meeting #2

To view this information in graph form, click here.

Phase No. Plan Phase Description Estimated Duration* Estimated Duration* Estimated Duration* Estimated Duration* Estimated Duration* Estimated Duration* Cum.. Total
1) CVSP Introductory / Pre-Visioning: Select group 1 consultants (biologist, hydrologist, traffic engineer, civil/infrastructure engineer) to complete analysis of opportunities and constraints. Task Force Meetings Nos. 1 - 5 18 weeks           18 wks (4.5 mths)
  HCP Predevelopment Stage: Select group 1 consultants (biologist, attorney, and facilitator); develop scoping and planning agreement with responsible agencies; form institutional structure with stakeholders, TAC, and independent science advisory commission; develop project description and begin initial environmental inventory.              
2) CVSP Goals and Objectives: Develop goals and objectives based on opportunities and constraints; select group 2 consultants (land planner, fiscal/market analyst, economist, and environmental consultant). Include urban design competition in selection process. Task Force Meeting Nos. 6 - 10 External TAC Meeting Nos. 1 - 2 Community Workshop No. 1 Stakeholder Interviews 16 weeks           34 wks (8.5 mths)
  HCP Development and EIS stage: Select group 2 consultants (EIS/NEPA, facilitator, and additional biological specialists). Refine project description; identify project impacts; delineate HCP boundaries or plan area; perform additional studies as appropriate; identify proposed activities in plan area likely to result in "take;" quantify anticipated "take" levels; identify indirect effects, plants, and critical habitat; develop mitigation programs and standards; develop economic analysis; develop implementation funding; develop alternatives for "taking."              
3) CVSP Land Planning: Define urban structure and the public, semi-public, and private realms; develop alternative land use plans; continue compiling environmental documentation and analyzing constraints. Task Force Meeting Nos. 11 - 14 External TAC Meeting No. 3 Community Workshop No. 2 17 weeks           51 wks (13 mths)
  HCP Draft HCP and EIS Stage:              
4) CVSP Development of Draft Specific Plan: Prepare specific plan based on selected urban structure and land use plan including land use element, transportation/circulation plan, infrastructure plan, community facilities plan, financing and phasing plan, and administration plan. Task Force Meeting Nos. 15 - 17 External TAC Meeting No. 4 Community Workshop No. 3 16 weeks           67 wks (17 mths)
  HCP Finalized draft HCP and EIS for City adoption:              
5) CVSP Refinement of Draft Specific Plan: Circulate draft specific plan; present at community workshops and Task Force meetings; incorporate public comments; and prepare revised draft specific plan. Task Force Meeting Nos. 18 - 19 External TAC Meeting No. 5 Community Workshop No. 4 8 weeks           75 wks (19 mths)
  HCP City adoption of draft HCP and EIS; and application submittal to USFWS              
6) CVSP Preparation of Design Guidelines: Develop street and trail typologies, building typologies and massing, landscape design concepts, design concepts for open space and public facilities, and appropriate policies for land use, circulation, infrastructure, public facilities, etc. Task Force Meeting Nos. 20 - 22 External TAC Meeting No. 6 Community Workshop No. 5 - 6 24 weeks           99 wks (25 mths)
  HCP Ongoing coordination with USFWS              
7) CVSP Preparation of Coyote Valley Zoning District: Prepare custom zoning based on design guidelines' principles and policies; develop procedure for zoning administration. Task Force Meeting Nos. 23 - 26 External TAC Meeting No. 7 Community Workshop No. 7 24 weeks           123 wks (31 mths)
8) CVSP Completion of Environmental Documentation: Complete Administrative Draft EIR review; circulate Draft EIR for review and comment; address and include public comments. Task Force Meeting Nos. 27 10 weeks           133 wks (33 mths)
9) CVSP Public Hearings: Present Specific Plan, Guidelines, Zoning and EIR at Bicycle and Pedestrian Advisory Committee, Senior Commission, Parks and Rec. Commission, and Housing Advisory Commission; include comments into final documents for Planning Commission recommendation and City Council consideration. 8 weeks           141 wks (35 mths)
  HCP HCP and EIS approval by USFWS:              
      141 weeks            
Notes:
*Duration starts with execution of funding agreement between City and property owners.
The work plan phases overlap as illustrated in the Work plan Overview graphic.
CVSP refers to Coyote Valley Specific Plan