| Phase No. |
Plan |
Phase Description |
Estimated Duration* |
Estimated Duration* |
Estimated Duration* |
Estimated Duration* |
Estimated Duration* |
Estimated Duration* |
Cum.. Total |
| 1) |
CVSP |
Introductory / Pre-Visioning:
Select group 1 consultants (biologist, hydrologist, traffic engineer, civil/infrastructure engineer) to complete analysis of opportunities and constraints.
Task Force Meetings Nos. 1 - 5
|
18 weeks |
|
|
|
|
|
18 wks
(4.5 mths) |
| |
HCP |
Predevelopment Stage:
Select group 1 consultants (biologist, attorney, and facilitator); develop scoping and planning agreement with responsible agencies; form institutional structure with stakeholders, TAC, and independent science advisory commission; develop project description and begin initial environmental inventory.
|
|
|
|
|
|
|
|
| 2) |
CVSP |
Goals and Objectives:
Develop goals and objectives based on opportunities and constraints; select group 2 consultants (land planner, fiscal/market analyst, economist, and environmental consultant). Include urban design competition in selection process.
Task Force Meeting Nos. 6 - 10
External TAC Meeting Nos. 1 - 2
Community Workshop No. 1
Stakeholder Interviews
|
16 weeks |
|
|
|
|
|
34 wks
(8.5 mths) |
| |
HCP |
Development and EIS stage:
Select group 2 consultants (EIS/NEPA, facilitator, and additional biological specialists). Refine project description; identify project impacts; delineate HCP boundaries or plan area; perform additional studies as appropriate; identify proposed activities in plan area likely to result in "take;" quantify anticipated "take" levels; identify indirect effects, plants, and critical habitat; develop mitigation programs and standards; develop economic analysis; develop implementation funding; develop alternatives for "taking."
|
|
|
|
|
|
|
|
| 3) |
CVSP |
Land Planning:
Define urban structure and the public, semi-public, and private realms; develop alternative land use plans; continue compiling environmental documentation and analyzing constraints.
Task Force Meeting Nos. 11 - 14
External TAC Meeting No. 3
Community Workshop No. 2
|
17 weeks |
|
|
|
|
|
51 wks
(13 mths) |
| |
HCP |
Draft HCP and EIS Stage:
|
|
|
|
|
|
|
|
| 4) |
CVSP |
Development of Draft Specific Plan:
Prepare specific plan based on selected urban structure and land use plan including land use element, transportation/circulation plan, infrastructure plan, community facilities plan, financing and phasing plan, and administration plan.
Task Force Meeting Nos. 15 - 17
External TAC Meeting No. 4
Community Workshop No. 3
|
16 weeks |
|
|
|
|
|
67 wks
(17 mths) |
| |
HCP |
Finalized draft HCP and EIS for City adoption:
|
|
|
|
|
|
|
|
| 5) |
CVSP |
Refinement of Draft Specific Plan:
Circulate draft specific plan; present at community workshops and Task Force meetings; incorporate public comments; and prepare revised draft specific plan.
Task Force Meeting Nos. 18 - 19
External TAC Meeting No. 5
Community Workshop No. 4
|
8 weeks |
|
|
|
|
|
75 wks
(19 mths) |
| |
HCP |
City adoption of draft HCP and EIS; and application submittal to USFWS
|
|
|
|
|
|
|
|
| 6) |
CVSP |
Preparation of Design Guidelines:
Develop street and trail typologies, building typologies and massing, landscape design concepts, design concepts for open space and public facilities, and appropriate policies for land use, circulation, infrastructure, public facilities, etc.
Task Force Meeting Nos. 20 - 22
External TAC Meeting No. 6
Community Workshop No. 5 - 6
|
24 weeks |
|
|
|
|
|
99 wks
(25 mths) |
| |
HCP |
Ongoing coordination with USFWS
|
|
|
|
|
|
|
|
| 7) |
CVSP |
Preparation of Coyote Valley Zoning District:
Prepare custom zoning based on design guidelines' principles and policies; develop procedure for zoning administration.
Task Force Meeting Nos. 23 - 26
External TAC Meeting No. 7
Community Workshop No. 7
|
24 weeks |
|
|
|
|
|
123 wks
(31 mths) |
| 8) |
CVSP |
Completion of Environmental Documentation:
Complete Administrative Draft EIR review; circulate Draft EIR for review and comment; address and include public comments.
Task Force Meeting Nos. 27
|
10 weeks |
|
|
|
|
|
133 wks
(33 mths) |
| 9) |
CVSP |
Public Hearings:
Present Specific Plan, Guidelines, Zoning and EIR at Bicycle and Pedestrian Advisory Committee, Senior Commission, Parks and Rec. Commission, and Housing Advisory Commission; include comments into final documents for Planning Commission recommendation and City Council consideration.
|
8 weeks |
|
|
|
|
|
141 wks
(35 mths) |
| |
HCP |
HCP and EIS approval by USFWS:
|
|
|
|
|
|
|
|
| |
|
|
141 weeks |
|
|
|
|
|
|
Notes: *Duration starts with execution of funding agreement between City and property owners. The work plan phases overlap as illustrated in the Work plan Overview graphic.
CVSP refers to Coyote Valley Specific Plan
|