East William Street Recycled Water Project (Alignment G)
This project was constructed during 2011, and is now online. The project included approximately 4,900 LF of pipe and connections to six customers with a combined estimated recycled water demand of 116 AFY.

Story Road Recycled Water Project (Alignment H)
This project was constructed during 2011, and is now online. The project included approximately 21,930 LF of pipe and connections to 21 customers with a combined estimated recycled water demand of 377 AFY.

Oakland Road Recycled Water Project (Alignment C)
This project is currently under construction. The project includes approximately 47,930 LF of pipe and connections to 101 customers with a combined estimated recycled water demand of 677 AFY. 

Download a map of Phase One extensions.