CIP Monthly Status Report – June 2018

Post Date:08/21/2018

In June, the Treatment Plant Advisory Committee and San José City Council approved three items: A design-build contract for preliminary services for the Headworks Project, three master consultant agreements for various capital improvement projects at the Wastewater Facility, and a $25 million increase to the Digester and Thickener Facilities Upgrade Project.

The Facility Wide Water Systems Improvements Project team selected a preferred alternative for each of the water systems and the design consultant began drafting the alternatives analysis report documenting the process and resulting recommendations. The Filter Rehabilitation Project design consultant submitted the draft preliminary design report and cost estimate. The City advertised the construction contract for the Blower Improvements Project; bids are due in August and construction award is anticipated in November.

The construction contract for the Advanced Facility Control and Meter Replacement Phase 1 Project was executed. The City participated in factory acceptance testing of the four new cogeneration engines for the Cogeneration Facility Project. All tests were successfully completed, and the engines are expected to be delivered to the Wastewater Facility by mid-September.

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer