CIP Monthly Status Report – October 2019

Post Date:11/06/2019

In October, the Advanced Facility Control and Meter Replacement – Phase 2 Project passed Stage Gate 5: Authorization to Bid of the Project Delivery Model. The project is expected to be advertised in January.

The contractor for the Digester and Thickener Facilities Upgrade Project completed the two driveway approaches to the new sludge screening building as well as the hot water supply and return piping connections to the new cogeneration facility. 

The Advanced Facility Control and Meter Replacement – Phase 1 Project contractor installed drain plates in eight of 11 returnactivated sludge (RAS) meter vaults and will complete the last three next month. Operational testing is anticipated to commence in December.

For the Switchgear M4 Replacement and G3 & G3A Removal Project, the City evaluated the two bids received and will recommend that Council award the construction contract to the lowest responsive bidder in December.   

The City issued an NTP for the Digested Sludge Dewatering Facility Project to the design-builder authorizing preliminary services. The City held a partnering workshop with the design-builder.

CIP Monthly Status Report - October 2019
View all CIP Monthly Status Reports

External Monthly Report Oct 2019 Final2