Pre-Final Electrical Meter Release Requirements

When an electric meter is needed prior to final electrical approval, the owner can request a Pre-Final Meter.

This option is NOT available for shell-only projects, speculative space-only projects, or projects that have not received issuance of permits as required for tenant improvements. For all other projects, follow these steps to request a Pre-Final Meter:

Commercial and Multi-Family Projects

  • The applicant has completed the Pre-Final Meter Request Form with the specific areas, and equipment requested to be energized
  • The equipment requested to be energized is completely inspected and approved
  • All conductors not complete are capped and deenergized in an electrically safe condition
  • The electrical room has a lockable door, with access to only the electrical contractor
  • There is adequate permanent lighting in the electrical room
  • The contractor has an adequate lock out tag out procedure on site
  • Any electrical approved for the temporary use of personnel shall have GFCI protection

R-3 Residential Projects

  • The applicant has completed the Pre-Final Meter Request Form with the specific areas, and equipment requested to be energized
  • The field inspector has conducted a final electrical inspection and all code violations and/or incomplete electrical items are noted in the correction
  • The equipment requested to be energized is completely inspected and approved
  • All conductors not complete are capped and deenergized in an electrically safe condition
  • Any electrical approved for the temporary use of personnel shall have GFCI protection

Complete and submit the Pre-Final Meter Request Form to the area field coordinator.

After the required inspection, a City Inspector will review the request. If approved, the inspector will issue a Meter Release, leaving one copy on the job site, and taking one copy to the Permit Center where staff will handle notifying PG&E of the approval.

The owner must contact PG&E no sooner than 2:00 p.m. on the day following the inspection to arrange for the meter installation.


A pdf handout version of this information is available on our Building Handouts and Forms page.

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer