Temporary Certificate of Occupancy

A Temporary Certificate of Occupancy (TCO) enables occupancy or partial occupancy of a building prior to the building project being completed. A TCO may be granted for a reasonable timeframe if the Inspection Services Division Manager finds that no substantial hazard will result from such occupancy.

Each TCO request is evaluated on a case-by-case basis.

How to Apply

Before you begin All required final inspections must have been attempted, although not necessarily passed, before you can apply for temporary occupancy.

Write a Request Letter as outlined here

Example Request

 

Provide copies of all permits, inspection cards (both sides), and permit review documents

 

Failure to include all documents will delay the processing of your request.

Use your company’s official letterhead. The letter must include:

  1. Business name and address of the project.
  2. Building Permit Number and Plan Check Number.
  3. Proposed Effective Date and Ending Date for the TCO.
  4. The reason for needing occupancy prior to final inspection.
  5. Itemized status of all inspections and deferred submittals that have not been completed or approved.
  6. Include the stipulations as explained in the sidebar and shown in the example letter.
  7. Signatures of both the Business Owner and Construction Company.
  8. Email address to which the approval/denial will be sent.

Please include copies of:

  • Building permit, any sub-trade permits (plumbing/mechanical/electrical), any permits associated with the building shell.
  • Any inspection notices (sub-trades or Fire inspections: Fire Sprinkler, Fire Alarm and Fire Architectural inspections).
  • If the project will be phased, you must also provide a plan for exiting, accessibility, emergency lighting, and barricades.

Submit your letter
(not a copy) and copies of permit documents in person to:


Attn: Inspection Services Division Manager
Building Division, 2nd Floor
City of San José - Dept. of Planning, Building & Code Enforcement
200 E. Santa Clara Street
San José, CA 95113

 

How long will it take to process my request?


Requests are typically processed in one to three business days. If approved, the TCO request letter will be endorsed and a copy will be emailed to the applicant. The endorsed letter constitutes a Temporary Certificate of Occupancy. No occupancy of the building may occur until authorized by the Building Division and a copy of the endorsed letter is available at the site.

 
What if all inspections are approved except Building?

If the Fire Department has signed the Fire Final on the permit card and all other final inspections are approved, then your Building Inspector has authority to grant temporary occupancy. Follow these steps:

  • Call the Field Coordinator (phone number on inspection slip) and request an inspection for temporary occupancy.
  • Provide the Inspector with a Request Letter as described in this bulletin. If approved, the Inspector will spell out the requirements and limitations applicable to your TOC on the inspection slip and give you a copy. The inspector will handle processing of your Request Letter at the Permit Center.

Fees

  • A processing fee of $502 is to be paid with your submittal.
  • If you do not have a Fire Department Final, an additional $518 will be required at submittal for Fire Department review.

Required Stipulations

  • Your letter must stipulate that you agree to pursue scheduled inspections and to resolve inspection issues to the City’s satisfaction.
  • If you fail to do so prior to the expiration of your TCO, you must vacate the premises and terminate all temporary occupancy until renewal of a TCO is approved or you obtain a final Certificate of Occupancy for the building.

Office Procedure

  • Email a copy of the approved TCO letter to the applicant
  • Send the approved letter and attachments to the Imaging Section to be filed with the building permit.
  • Monitor TCO expiration date and advise Inspection Division Manager when a TCO expires.

A pdf handout version of this information is available on our Building Handouts and Forms page.

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer